Section 60: 1 Factories

Guwahati Building ByelawsState Rules of Assam · 2010

Every room in such building shall be lighted and ventilated by sufficient number of windows, ventilators and skylight exclusive of doors having clear opening not less 1/15 of the floor area abutting on open air space of width not less than 1/3 rd the height of the part of the building-abutting-such-open-space.

Provided that this requirement may be relaxed if artificial lighting and ventilation are installed to the satisfaction of the Authority.

60.2 Height of the floors:- The height of the ground floor and each of the upper floors shall not be less than 4.2m and 3.9 m. respectively and the height of the cellar or basement shall in no part be less than 2.4 m.

provided that these provisions shall not apply to the extensions of the ground floor and upper floors of the existing building.

61. Special regulations for construction in hilly areas:

(a) The Authority may ask for detailed topographic survey map of the site, showing the proposed ground levels of the plot and the remedial construction measures to check the undesired erosion that may effect the adjoining areas. The Authority may also give special direction for framing the proposal in such a way which involves least disturbance to the natural terrain and keeping of bare land which is not allowed.

(b) If terrace cutting is done for building constructed on hill the depth and slope of the cut should be restricted according to the soil characteristic of the area.

(c) Adequate drainage provision should be kept to the satisfaction of the Authority so that rain water and waste water can drain out from the plot without causing soil erosion.

(d) In hill areas with slope greater than 10o special protection measures will have to be provided as specified by the Authority. Local ground conditions shall be taken into account in the determination of the appropriate precautionary work and protection walls as well as relevant code of B.I.S. as specified in Chapter- VI.

(e) The maximum height of cutting for development should generally be 4 m. to 6m and cutting of slope over a height of 6m. shall not be ordinarily permitted. Height of 6m earth cutting should be from face of 1st cutting.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [50]

(f) If however Authority feels that special protective measures are required in the plot prior to any construction in the plot, no construction of building may be allowed by the Authority in such plot unless the protective measures are completed as directed by the Authority first.

62. Environmental-aspects-and-landscaping.

The Authority may impose special provision for landscaping, in special type of building/ plot that is nature and number of plantation to be carried out, maintenance of vegetable cover in the plot for the environmental upgradation of-the-area-and-to-restrict-soil-erosion.

(i) In every plot at least 20% of the land should be utilized for tree plantation and greenery.

63. (a) The Authority may impose special condition to the developer to develop the road and drain abutting that particular plot.

(b) If however, developer agree to contribute towards the development charge for developing adjoining roads and drains or decides to relinquish a part of these land for improvement of road, drain or creation of open space for the locality without asking for any compensation to the satisfaction of the Authority, the Authority may consider allowing additional proportionate F.A.R. in that particular plot development of the area.

(c) For allowing additional FAR under this provision, detail procedure is given in Chapter-VII.

64. In Group Housing project and projects where a number of apartment blocks are proposed in a single plot the Authority may impose special regulations for drains, recreational open space, garbage disposal etc. in addition to the regulations contained in these Byelaws.

65. Every building shall provide one or more rain harvesting structures to collect the roof top run off. The total dimension of recharging/percolating pits/trenches should be at least 5 cubic metre dimension for every 100 sq.mtr. of roof area.

Provided further that such rain water harvesting structure shall also be provided in cases of all apartment, institutional and similar buildings and buildings in hill areas.

65. (i) CONSERVATION AND HARVESTING OF RAIN WATER IN GROUP HOUSING-SCHEMES/APARTMENT-AND-COMMERCIAL COMPLEXES/ INSTITUTIONAL BUILDINGS Every Group Housing Scheme etc. shall be provided with required facilities and infrastructure for conservation and harvesting of rain water, viz., a. Percolation Pits:

The paved surface around the building shall have percolation pits of 1.2m x 1.2m x 1.2m covering at least 30% of such area. Such pits shall be filled with small pebbles or brick jelly or river sand and covered with perforated concrete slabs.

The following requirements are optional and to be provided depending on the site conditions.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [51] b. Terrace water collection:

The terrace shall be connected to a sump or the well through a filtering tank by PVC pipe. A valve system shall be incorporated to enable the first part of the rain water collected to be discharged out to the soil if it is dirty.

The filtering tank measuring 0.6 m to 1.2 m square can be constructed near the sump. A tank can be divided by a perforated slab and one part should be filled by small pebbles and other by brick jelly. The bottom portion of the tank should have slope to avoid stagnation of water.

c. Open Ground:

Whenever there is open ground a portion of top soil should be removed and replaced with river sand to allow slow percolation of rain water.

OR d. Any other methods proved to be effective in conservation and harvesting of rain water may be adopted in each and every construction taken up.

66. The following areas of Guwahati to be earmarked by the Authority by notification from time to time if not already notified in the Master Plan should normally be excluded for permission of multistoreyed building.

1. National Heritage zones consisting of places of pilgrimage and worship (like, Satra, Namghar, Devalaya, Mandir, Math, Masjid, Dargah, Gurudwara, Church) and sites of historical and cultural importance.

2. Areas falling on or abutting natural drainage channels.

3. Areas falling on or abutting wetlands.

4. Areas earmarked for infrastructure of civic amenities in the Master Plan and Zoning Regulation for Guwahati.

5. Sites on hills and foothills requiring excavation that is likely to cause soil erosion, land slide or instability of hill slope; and sites below overhanging embedded rocks without proper protection work as specified in these rules. In this regard the foot hill areas of Sarania, Kamakhya, Narakasur hills are most vulnerable.

6. Government land in the hills and in the water bodies like beels.

7. The notified forest land falling within the Guwahati Master Plan area.

8. Areas between river Brahmaputra and the main road from Raj Bhawan to Kamakhya hill.

The Authority will judiciously examine all building proposals including multistoreyed buildings in the vicinity of the above areas before such proposal are cleared/allowed with such condition / modification as the Authority may decide from time to time. The protective measures to be taken in natural hazard prone areas has been given in Chapter –VI Cl. 6.12.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [52] Chapter VI

67. ADDITIONAL PROVISIONS IN BUILDING REGULATIONS /BYELAWS FOR STRUCTURAL SAFETY.

67.1 STRUCTURAL DESIGN For any building under the jurisdiction of these regulations structural design/ retrofitting shall only be carried out by a Registered Structural Engineer on Record (SER) or Structural Design Agency on Record (SDAR). Proof checking of various designs/ reports shall be carried out by competent authority as per Table-1 wherever applicable.

Generally, the structural design of foundations, elements of masonry, timber, plain concrete, reinforced concrete, pre-stressed concrete and structural steel shall conform to the provisions of part VI Structural Design Section – 1 Load Section – 2 Foundation Section – 3 Wood Section – 4 Masonry Section – 5 Concrete Section – 6 Steel of National Building Code of India (NBC), taking into consideration the Indian Standards as given below:

For General Structural Safety

1. IS: 456:2000 “Code of Practice for Plain and Reinforced Concrete

2. IS: 800-1984 “Code of Practice for General Construction in Steel

3. IS: 801-1975 “Code of Practice for Use of Cold Formal Light Gauge Steel Structural Members in General Building Construction

4. IS 875 ( Part 2):1987Design loads ( other than earthquake ) for buildings and structures Part2 Imposed Loads

5. IS 875 ( Part 3):1987Design loads ( other than earthquake ) for buildings and structures Part 3 Wind Loads

6. IS 875 ( Part 4):1987Design loads ( other than earthquake ) for buildings and structures Part 4 Snow Loads

7. IS 875 ( Part 5):1987Design loads ( other than earthquake ) for buildings and structures Part 5 special loads and load combination

8. IS: 883:1966 “Code of Practice for Design of Structural Timber in Building

9. IS: 1904:1987 “Code of Practice for Structural Safety of Buildings:

Foundation”

10. IS1905:1987 “Code of Practice for Structural Safety of Buildings: Masonry Walls

11. IS 2911 (Part 1): Section 1: 1979 “Code of Practice for Design and Construction of Pile Foundation Section 1 Part 1: Section 2 Based Cast-in-situ Piles Part 1: Section 3 Driven Precast Concrete Piles Part 1: Section 4 Based precast Concrete Piles Part 2: Timber Piles Part 3 Under Reamed Piles Part 4 Load Test on Piles NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [53] For Cyclone/Wind Storm Protection

12. IS 875 (3)-1987 "Code of Practice for Design Loads (other than Earthquake) for Buildings and Structures, Part 3, Wind Loads"

13. Guidelines (Based on IS 875 (3)-1987) for improving the Cyclonic Resistance of Low rise houses and other building For Earthquake Protection

14. IS: 1893-2002 "Criteria for Earthquake Resistant Design of Structures (Fifth Revision)"

15. IS:13920-1993 "Ductile Detailing of Reinforced Concrete Structures subjected to Seismic Forces - Code of Practice"

16. IS:4326-1993 "Earthquake Resistant Design and Construction of Buildings - Code of Practice (Second Revision)"

17. IS:13828-1993 "Improving Earthquake Resistance of Low Strength Masonry Buildings - Guidelines"

18. IS:13827-1993 "Improving Earthquake Resistance of Earthen Buildings - Guidelines",

19. IS:13935-1993 "Repair and Seismic Strengthening of Buildings - Guidelines" For Protection of Landslide Hazard

20. IS 14458 (Part 1): 1998 Guidelines for retaining wall for hill area: Part 1 Selection of type of wall.

21. IS 14458 (Part 2): 1997 Guidelines for retaining wall for hill area: Part 2 Design of retaining/breast walls

22. IS 14458 (Part 3): 1998 Guidelines for retaining wall for hill area: Part 3 Construction of dry stone walls

23. IS 14496 (Part 2): 1998 Guidelines for preparation of landslide – Hazard Zonation maps in mountainous terrains: Part 2 Macro-Zonation Note: Whenever an Indian Standard including those referred in the National Building Code or the National Building Code is referred, the latest revision of the same shall be followed except specific criteria, if any, mentioned above against that code.

67.2 STRUCTURAL DESIGN BASIS REPORT In compliance of the design with the above Indian Standard, the Registered Structural Engineer on Record will submit a structural design basis report in the proforma attached herewith covering the essential safety requirements specified in the Standard.

(i) The “Structural Design Basis Report (SDBR)”consists of four arts(FormNo.6) Part-1 - General Information/ Data Part-2 - Load Bearing Masonry Buildings Part-3 – Reinforced Concrete Buildings Part-4 - Steel Buildings NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [54]

(ii) Drawings and Documents to be submitted for approval of appropriate authorities shall include SDBR as detailed below:

Part - 1 Completed Part - 2 (if applicable) – completed Part -3 (if applicable) – undertaking that completed Part 3 will be submitted before commencement of construction.

Part– 4 (if applicable) – undertaking that completed Part 4 will be submitted before commencement of construction.

(iii) SDBR as detailed below shall be submitted to the appropriate authority as soon as design of foundation is completed, but not later than one month prior to commencement of construction.

Part-1 Completed Part-2, Part-3 or Part-4 ( if applicable) Completed

67.3 SEISMIC STRENGTHENING/RETROFITTING Prior to seismic strengthening/ retrofitting of any existing structure, evaluation of the existing structure as regards structural vulnerability in the specified wind/ seismic hazard zone shall be carried out by a RSE/RSDA. If as per the evaluation of the RSE/RSDA the seismic resistance is assessed to be less than the specified minimum seismic resistance as given in the note below, action will be initiated to carry out the upgrading of the seismic resistance of the building as per applicable standard guidelines.

Note: (a) for masonry buildings reference is to be made to IS: 4326 and IS: 13935 and

(b) for concrete buildings and structures reference to be made to BIS code on evaluation and seismic strengthening for retrofitting of RCC buildings under preparation at present.

67.4 REVIEW OF STRUCTURAL DESIGN

(i) The competent authority shall create a Structural Design Review Panel (SDRP) consisting of senior SER’s and SDAR’s whose task will be to review and certify the design prepared by SER or SDAR whenever it is decided to be referred by the competent authority.

(ii) The reviewing agency shall submit addendum to the certificate or a new certificate in case of subsequent changes in structural design.

(iii) Table-1 gives requirements of SDRP for different seismic zones namely III, IV and V and for structures of different complexities NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [55] TABLE – 1 PROOF CHECKING REQUIREMENTS FOR STRUCTURAL DESIGN SR NO.

TYPE OF STRUCTURE / RCC SUBMISSION FROM SER or SDAR TO BE PROOF - CHECKED 01 LOAD BEARING BUILDINGS UPTO 3 STOREYS SDBR* NOT TO BE CHECKED / SUBMITTED 02 BUILDINGS UPTO SEVEN STOREYS (R.C.C. / STEEL FRAMED STRUCTURE) SDBR TO BE CHECKED PRELIMINARY DESIGN NOT TO BE CHECKED BUT REQUIRED TO BE SUBMITTED 03 BUILDINGS MORE THAN SEVEN STOREYS ( R.C.C. / STEEL FRAMED STRUCTURE) SDBR TO BE CHECKED PRELIMINARY DESIGN TO BE CHECKED DETAILED STRUCTURAL DESIGN AND STRUCTURAL DRAWINGS TO BE CHECKED 04 PUBLIC BUILDINGS (A) LOAD BEARING BUILDINGS / RCC UPTO 3 STOREYS SDBR NOT TO BE CHECKED (B) R.C.C./STEEL STRUCTURES SDBR TO BE CHECKED PRELIMINARY DESIGN TO BE CHECKED DETAILED STRUCTURAL DSIGN AND STRUCTURAL DRAWINGS TO BE CHECKED 05 SPECIAL STRUCTURES SDBR TO BE CHECKED PRELIMINARY DESIGN TO BE CHECKED DETAILED STRUCTURAL DESIGN-AND STRUCTURAL DRAWINGS TO BE CHECKED * SDBR - Structural Design Basis Report Notes:

• Public building means assembly of large number of people including schools, hospitals, courts etc.

• Special structure means large span structures such as stadium, assembly halls, or tall structures such as water tanks, TV tower, chimney, etc.

It will be seen from the table that there is a wide range of structure typology, and the requirement by the competent authority for third party verification will depend on the type of structure.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [56]

67.5 CERTIFICATION REGARDING STRUCTURAL SAFETY IN DESIGN Registered Structural Engineer on Record (SER) or Structural Design Agency on Record (SDAR) shall give a certificate of structural safety of design as per proforma given in Form-3 and Form-14 at the time of completion.

67.6 CONSTRUCTIONAL SAFETY

67.6.1 Supervision All construction except RCC load bearing buildings upto 3 storeys shall be carried out under supervision of the Construction Engineer on Record (CER) or Construction Management Agency on Record (CMAR) for various seismic zones.

67.6.2 Certification of structural safety in construction CER/ CMAR shall give a certificate of structural safety of construction as per proforma given in Form-13 at the time of completion.

67.7 QUALITY CONTROL AND INSPECTION

67.7.1 Inspection All the construction for highrise buildings higher than seven storeys, public buildings and special structures shall be carried out under quality inspection program prepared and implemented under the Quality Auditor on Record (QAR) or Quality Auditor Agency on Record (QAAR) in seismic zones IV & V.

67.7.2 Certification of safety in quality of construction Quality Auditor on Record (QAR) or Quality Auditor Agency on Record (QAAR) shall give a certificate of quality control as per proforma given in Form-15.

Quality Inspection Programme to be carried on the site shall be worked out by QAR/ QAAR in consultation with the owner, builder, CER/ CMAR.

67.8.1 CONTROL OF SIGNS (HOARDINGS) AND OUTDOOR DISPLAY STRUCTURES AND PAGING TOWER AND TELEPHONE TOWER AND OUTDOOR DISPLAY STRUCTURES Following provisions shall apply for telecommunication infrastructure.

a) Location: The telecommunication infrastructure shall be either placed on the building roof tops or on the ground or open space within the premises subject to other regulations.

b) Type of structure NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [57]

(i) Steel fabricated tower or antennae on M.S. pole.

(ii) Pre-fabricated shelters of fibre glass or P.V.C. on the building roof top/terrace for equipment.

(iii) Masonry structure/ Shelter on the ground for equipment.

(iv) D.G. Set with sound proof cover to reduce the noise level.

c) Requirement:

(i) Every applicant has to obtain/ procure the necessary permission from the “Standing Advisory Committee on Radio Frequency Allocation” (SACFA) issued by the Ministry of Telecommunications.

(ii) Every applicant will have to produce the structural safety & stability certificate for the tower as well as the building from the Structural Engineer on Record (SER) which shall be the liability of both owner and SER.

(iii) Applicant has to produce / submit plans of structure to be erected.

d) Projection: No Pager and/or telephone tower shall project beyond the existing building line of the building on which it is erected in any direction.

67.9 STRUCTURAL REQUIREMENTS OF LOW COST HOUSING Notwithstanding anything contained herein, for the structural safety and services for development of low cost housing, the relevant provisions of applicable IS Codes shall be enforced.

67.10 INSPECTION The general requirement for inspection of the development shall also include the following regulations.

67.10.1 General Requirements The building unit intended to be developed shall be in conformity with Regulations on requirement of site. Generally all development work for which permission is required shall be subject to inspection by the competent authority as deemed fit.

The applicant shall keep a board at site of development mentioning the Dag No, Patta No., Revenue Village, Mouza, Building Permit No. name of owner and name of Architect on Record, Engineer on Record , developer, Structural Engineer on Record , Construction Engineer on Record .

67.10.2 Record of Construction Progress

(a) Stages for recording progress certificate and checking:- NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [58] i) Plinth, in case of basement before the casting of basement slab.

ii) First storey.

iii) Middle storey in case of highrise building.

iv) Last storey.

(b) At each of the above stages, the owner / developer / builder shall submit to the designated officer of the competent authority a progress certificate in the given formats ( Form No. 7-10 ) This progress certificate shall be signed by the Construction Engineer on Record.

(c) The progress certificate shall not be necessary in the following cases:

i) Alteration in building not involving the structural part of the building.

ii) Extension of existing residential building on the ground floor upto maximum 15 sq mt. in area.

(d) Completion Report i) It shall be incumbent on every applicant whose plans have been approved, to submit a completion report in Form No.11.

ii) It shall also be incumbent on every person / agency who is engaged under this Development Control Regulations to supervise the erection or re-erection of the building, to submit the completion report in Form No.12 and 13 prescribed under these Development Control Regulations.

iii) No completion report shall be accepted unless completion plan is approved by the competent authority.

(e) The final inspection of the work shall be made by the concerned competent authority within 21 days from the date of receipt of notice of completion report.

67.10.3 Issue of Occupancy Certificate The Authority issuing occupancy certificate before doing so shall ensure that following are complied with for consideration of safety against natural hazard.

(i) Certificate of lift Inspector has been procured & submitted by the owner regarding satisfactory erection of lift.

(ii) The certificate of competent authority and or fire department for completion and or fire requirements as provided in these regulations has been procured and submitted by the owner.

(iii) If any project consists of more than one detached or semi detached building / buildings in a building unit and any building / buildings thereof is completed as per provisions of D.C.R..

(such as parking, common plots, internal roads, height of the building, infrastructure facilities, lift and fire safety measures), the competent authority may issue completion certificate for NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [59] such one detached or semi detached building / buildings in a building unit.

The occupancy certificate shall not be issued unless the information is supplied by the owner and the Architect on Record/ Engineer on Record concerned in the schedule as prescribed by the competent authority from time to time.

67.11 MAINTENANCE OF BUILDINGS In case of building older than fifty years, it shall be the duty of the owner of a building, to get his building inspected by a Registered Structural Engineer (RSE) within a year from the date of coming into force of these regulations. The Structural Inspection Report (Form No.16) shall be produced by the owner to the appropriate authority. If any action for ensuring the structural safety and stability of the building is to be taken, as recommended by SER, it shall be completed within five years.

For other buildings, the owner shall get his building inspected after the age of building has crossed forty years. The procedure shall be followed as per above regulation.

67.12 PROTECTIVE MEASURES IN NATURAL HAZARDPRONE AREAS In natural hazardprone areas identified under the landuse Zoning Regulations, structures, buildings and installations which cannot be avoided, protective measures for such construction/ development should be properly safeguarded based on the suggestion given in Appendix A.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [60] APPENDIX –I MINIMUM NO. OF OFF-STREET PARKING SPACE Sl No. Type of Use One Parking space will be provided for every Car Scooter 1 Residential building (In case of Group housing & apartment buildings) Every unit of 60 sq. mt. Every unit below 60 sq.

mt to 40 sq. mt 2 Theatres, Cinemas, Auditorium 15 seats of accommodation 10 seats of accommodation 3 Retail business 50 sq. mt. or fraction thereof 20 sq. mt. of sales area 4 Office building 100 sq. mt. of area or fraction thereof 20 sq. mt. of office floor area 5 Hospital 5 beds (private) 10 beds (public) 5 beds of accommodation 6 Hotel 3 guest rooms 7 Restaurants 10 seats of accommodations 6 seats of accommodations 8 Industrial building 20 employees in the industry 15 employees in the industry 9 Wholesale and Warehouses 60 sq. mt. floor area and fraction thereof for car and scooter - 10 Educational 50 sq. mt. area or fraction thereof of the administrative office area and public service area - 11 Marriage Hall/Community Hall 50 sq. mt. plot area - 12 Stadium and exhibition center 30 seats - Minimum No. of Off-Street Parking space 1) For calculation of total car parking area the area of one car parking space will be as specified in 58 10 (4) 2) For calculation of scooter parking space, one car parking space will be equivalent to 6 scooter parking.

3) 2.5 car parking space will be equivalent to one parking space of heavy vehicle in Industrial and Whole-sale, Warehouse buildings.

4) In all building of various uses except residential buildings (as provided in Sl.1) as mentioned above, parking space of each car and scooter has to be provided.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [61] APPENDIX-II GUIDE FOR THE QUALIFICATIONS AND COMPETENCE OF PROFESSIONALS A-1 ESSENTIAL REQUIREMENTS A-1.1 Every building/ development work for which permission is sought under the code shall be planned, designed and supervised by registered professionals. The registered professionals for carrying out the various activities shall be: (a) architect, (b) engineer, (c) structural engineer, (d) supervisor, (e) town planner, (f) landscape architect, (g) urban designer, and (h) utility service engineer, Requirements of registration for various professionals by the Authority or by the body governing such profession and constituted under a statute, as applicable to practice within the local body’s jurisdiction.

Provided that no such license/ enrollment of technical personnel shall be necessary for various works of building permit in case of boundary walls, residential single storeyed A.T. building upto plinth area of 140 sq m and commercial building of single storeyed A.T. upto plinth area of 75 sq m. However considering the topography and other peculiar nature of plot and proposed construction the Authority may also require such schemes to be submitted by licensed/ enrolled technical personnel.

A-2 REQUIREMENTS FOR REGISTRATION AND COMPETENCE OF PROFESSIONALS A-2.1 Architect Practice of profession of Architecture by the registered architect should strictly be as per provision of the Architects Act, 1972 and their competence be as per comprehensive services as specified in Architect (Professional Conduct) Regulation, 1989.

A-2.2 Engineer The minimum qualifications for an engineer shall be graduate in civil engineering/ architectural engineering of recognized Indian or foreign university, or the Member of Civil Engineering Division/ Architectural Engineering Division of the Institution of Engineers (India) or the statutory body governing such profession, as and when established.

A-2.2.1 Competence The registered engineers shall be competent to carryout the work related to the building/ development permit as given below:

(a) All plans and informations connected with building permit;

(b) Structural detail and calculations of buildings on plot upto 500 m2 and upto 5 storyes or 16 m in height;

(c) Issuing certificate of supervision and completion for all buildings;

(d) Preparation of all service plans and related information connected with development permit; and

(e) Issuing certificate of supervision of land for all area.

A-2.3 Structural Engineer NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [62] The minimum qualification of structural engineer shall be graduate in civil engineering of recognized Indian or foreign university, or Corporate Member of Civil Engineering Division of Institution of Engineers (India), and with minimum 3 years experience in structural engineering practice with designing and field work.

Note:- The 3 years experience shall be relaxed to 1 year in the case of post-graduate degree of recognized Indian or foreign university in the branch of structural engineering. In case of doctorate in structural engineering, is not required.

A-2.3.1 Competence The registered engineers shall be competent to prepare the structural design, calculations and details for all buildings and supervision.

A-2.3.1.1 In case of buildings having special structural features, as decided by the Authority, which are within the horizontal areas and vertical limits specified in A-2.2.1 (b) and shall be designed only by structural engineers.

A-2.4 Supervisor The minimum qualifications for a supervisor shall be diploma in civil engineering or architecture or engineering equivalent to the minimum qualification prescribed for recruitment to non-gazetted service by the Government of India plus 5 years experience in building design, construction and supervision.

A-2.4.1 Competence The registered supervisor shall be competent to carryout the work related to the building permit as given below:

(a) All plans and related information connected with building permit for residential buildings on plot upto 100 m2 and upto two storyes or 7.5 m in height; and

(b) Issuing certificate of supervision for buildings as per (a).

A-2.5 Town Planner The minimum qualification for a town planner shall be the graduate/postgraduate degree in Town planning from recognized institute or qualifications required for Associate Membership of the Institute of Town planers India.

A-2.5.1 Competence The registered town planner shall be competent to carryout the work related to the development permit as given below:

(a) Preparation of plans for land sub-division/ layout and related information connected with development permit for all areas.

(b) Issuing of certificate of supervision for development of land ofall-areas.

Note: However, for land layouts for development permit above 5 hectare in area, and for land development infrastructural services for roads, water supplies, sewerage/ drainage, electrification, etc, the registered engineers for utility services shall be associated.

A-2.6 Landscape Architect The minimum qualification for a landscape architect shall be the bachelor or master’s degree in landscape architecture or equivalent from recognised Indian or foreign university.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [63] A-2.6.1 Competence The registered landscape architect shall be competent to carryout the work related to landscape design for building/ development permit for land areas 5 hectares and above. In case of metro-cities, this limit of land area shall be 2 hectare and above.

Note: For smaller areas below the limits indicated above, association of landscape architect may also be considered from the point of view of desired landscape development.

A-2.7 Urban Designer The minimum qualification for an urban designer shall be the master’s degree in urban design or equivalent from recognized Indian or foreign university.

A-2.7.1 Competence The registered urban designer shall be competent to carryout the work related to the building permit for urban design for land areas more than 5 hectares and campus area more than 2 hectares. He/She shall also be competent to carryout the work of urban renewal for all areas.

Note: For smaller areas below the limits indicated above, association of urban designer may be considered from the point of view of desired urban design.

A-2.8 Engineers for Utility Services For building identified in 12.2.5.1, the work of building and plumbing services shall be executed under the planning, design and supervision of competent personnel. The qualification for registered mechanical engineer (including HVAC), electrical engineer and plumbing engineers for carrying out the work of air-conditioning, heating and mechanical ventilation, electrical installations, lifts and escalators and water supply, drainage, sanitation and gas supply installations respectively shall be as given in Part 8 ‘Building Services’ and Part 9 ‘Plumbing Services’ or as decided by the Authority taking into account practices of the National professional bodies dealing with the specialist engineering services.

A-2.9 Geotechnical Engineers shall mean a Civil Engineer having at least 2

(two) years experience in soil and foundation engineering under similar soil/ geotehnical/ soil condition.

A-2.9.1 Competence To do all geotechnical investigation related to building construction.

A-3 BUILDER/ CONSTRUCTOR ENTITY The minimum qualification and competence for the builder/ constructor entity for various categories of building and infrastructural development shall be as decided by the Authority to ensure compliance of quality, safety and construction practices as required under the Code.

A-4 GROUP OR AGENCY:

When an agency or group comprising of qualified Architect/ Engineer/ Supervisor is practicing, then the qualifications and competence of work will be combination of the individual qualifications and competence, given under A-

2.1, 2.2, 2.3, 2.4, 2.5, 2.6, 2.7,2.8 and the agency shall be licensed by the Authority.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [64] A-5 ANNUAL RATE OF LICENSE/ ENROLMENT FEES OF TECHNICAL PERSONNEL:

Architect/ Engineer/ Group/ Agency/Others.

(a) Rs. 1500.00 (Rupees one thousand five hundred) only per year.

(b) Rs. 500.00 (Rupees five hundred) only for a single multistoreyed commercial building, apartment, residential and others.

Supervisor:

(a) Rs. 1000.00 (Rupees one thousand) only per year.

(b) Rs. 500.00 (Rupees five hundred) only for single multistoreyed project.

Renewal of license/ enrolment shall be made. Annual renewal fees to be equivalent to original fees provided that no renewal of license/ enrolment is permissible for single project.

(c) Rs. 250.00 (Rupees two hundred fifty) only for a single residential building.

PROCEDURE FOR APPLICATION OR LICENSE/ ENROLMENT IN THE AUTHORITY The Architect/ Engineer/ Group/ Agency/ Supervisor may apply in prescribed form (Form A & B) to the Authority with necessary fees as prescribed for license/ enrolment by the Authority.

DUTIES AND RESPONSIBILITIES OF LICENSED TECHNICAL PERSONNEL:

(i) It will be incumbent on every licensed technical personnel in all matters in which he/she may be professionally consulted or engaged to assist and cooperate with the Authority in carrying out and enforcing the provision of GMDA Act and any rules and Byelaws being in force under the same.

(ii) Every technical personnel shall in every case in which he may be professionally consulted or engaged be responsible so far as his professional connection with such case extends for due compliance with the provisions of GMDA Act and any rules and Byelaws for the time being in force under the said Act and in particular it will be obligatory on him to satisfy himself that all works are carried out as per rules and to prevent the use of any defective material therein and improper execution of any such work.

(iii) When a licensed Technical Personnel ceases to be in the employment for the development work, he shall report the case forthwith to the Authority.

(iv) Licensed technical personnel shall be required to submit a certificate (enclosed at Annexure-I) for designing/ supervision of proposed R.C.C.

building of above 2nd floor.

PENAL ACTION AGAINST DEFAULTING ARCHITECTS/ ENGINEERS/ GROUPS/ SUPERVISORS:

The Authority reserves the exclusive right to declare black listed, cancel license or take any other action that the Authority may decide to take against Architect/ Engineers/ Groups/ Supervisors if found to have diverged from the aesthetic and professional conduct or has made any misstatement or has misrepresented any material fact or has suppressed material facts.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [65] MISCELLANEOUS:

1. Provided that no such license/ enrolment will be required if the applicant himself is Technical Personnel with qualification as given in CL. 1 of these provisions.

2. Provided that no license fees will be required as given in CL. 2 of this provision for Architects registered under the Architects Act, 1972. any other fees as per CL A-5 are not applicable.

3. In the event of any doubt or disputes about any question relating to the above provisions, the Authority’s decisions shall be final and binding on all concerned.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [66] APPENDIX-III Penalties to be levied for violations of provisions of Master Plan/ Zoning Regulations & Byelaws.

(i) All provisions of Byelaws except items given below shall not be compounded/ regularized and shall have to be rectified by alteration/ demolition at the risk and cost of owner.

Compoundable Items:

(1) Coverage - Maximum of 5%

(2) F.A.R. - Maximum of 10%

(3) Setback - Upto 2′-6″

(4) Open space - maximum 10% reduction

(5) Total height of building - 1.5% Non compoundable Items:

(1) Use of building

(2) Addition of extra floor

(3) Parking norms

(4) Projection/ encroachment of public land.

Note: Additional floors will mean additional floors beyond the compoundable FAR.

Compoundable Items If a building or part thereof has been constructed unauthorisedly i.e. without obtaining the required building permit from the Authority as required by Building Byelaws the same shall be compounded at the following rates provided the construction otherwise conforms to the provisions of Building Byelaws & Master Plan and Zoning Regulations. For this party shall have to submit the request for permission in the prescribed procedure to the Committee headed by Vice Chairman in case of GMDA and Standing Appeal Committee in case of GMC.

Rates

(1) For building built prior to 1998.

(i) Five times the rate of normal permission fees for residential, public & semi public, institutional, educational buildings.

(ii) Ten times the rate of normal permission fees for commercial apartment, industrial & similar buildings.

(2) For buildings built after 1998 upto 2002.

(i) In addition to the rates prescribed in (I), the normal building permission fees will be charged.

N.B.: For incomplete building, the regularization fees to be computed on pro-rata basis.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [67]

(3) Rates for deviation of the Building Byelaws other than non-compoundable items specified in (i) of appendix –III shall be compounded at following rates for building constructed upto 2002.

(i) Rs. 500.00/sq.mtr. of area to be compounded for residential, public & semi public and educational buildings.

(ii) Rs. 3000.00/Sq.mtr. of area to be compounded for commercial, apartment, industrial building.

N.B: (i) 5% escalation charge /year will be added for buildings constructed after

2002.

(ii) The buildings not covered specifically under above categories shall be compoundable as decided by the Authority considering the merit of each case.

Residential & non residential buildings:

Upto 0.15mtr - No penalty Above 0.15 mtr to 0.3 mtr - Rs. 10.00 per sq. mtr.

Above 0.30 mtr to 0.75 mtr - Rs. 20.00 per sq. mtr.

If a building has more than one violation the total regularisation fee will be calculated after considering each violation separately as per these provisions.

Note: The Authority may however refuse regularisation of construction even with penalties as specified in the above provisions if in the opinion of the Authority this may infringe public safety and general environment of adjoining area.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [68] APPENDIX- IV Indemnity Bond for Basement/ Building/ Wall (For GMDA) (To be submitted on non-judicial stamp paper of Rs. 10 duly attested by the Magistrate.)

This Indemnity Bond is executed by Shri………………… hereinafter called the owners of ………………….. Guwahati in favour of GMDA, its successors or entitled.

Whereas the owner have submitted the plan of basement under building/ wall whereas he represented to the GMDA that if sanction is granted for the construction of the said basement/ building/ wall the owners shall indemnify the GMDA of any loss at the time of digging of foundation of the said basement/ building/ wall/ hill cutting or in the course of construction of the basement/ wall/ hill cutting or even thereafter.

And whereas the said owners have further agreed to indemnify the GMDA of any claims put up against the GMDA either by way or damage, compensation or in any other way in case the GMDA is required to pay any such amount to any person or the owner or owners of the adjoining properties. The owners hereby agree and undertake to indemnify the GMDA to pay full extent of the amount the GMDA may require to pay in the extent herein above mentioned.

The owners further undertake and agree to indemnify the GMDA for any such amount the GMDA may require to pay either by way of compensation or damage or any other amount and further undertake to indemnify the GMDA of all cost and expenses that the GMDA may require to defend any such action in any court of law.

The owners undertake that no excavation shall be carried out beyond the boundaries of the plot. Any damage occurring during or due to the excavation made at site to public sewers, water drains/ road shall have to be made good by the owners.

In consideration of the above matter, undertaking and indemnity given by the said owners the GMDA hereby under in this behalf grant the sanction in the said basement/ building/ wall to the said owners.

In witness hereof the owner above-mentioned put their hands and seal to the said indemnity bond on this …………………………………………… Witness:

1. ………………………………………… 1. …………………………………….

2. ………………………………………… 2. …………………………………….

(EXECUTANTS) N.B. Authority will ask for this Bond for building with Basement/ 4 storey and above/ in hills and in special cases where Authority may require.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [69] FORM-A Application for Enrolment as Competent Technical Personnel in G.M.D.A.

(individual) To, The Chief Executive Officer, Guwahati Metropolitan Development Authority, Bhangagrh, Guwahati-5 I hereby apply for enrolment of my name as competent Technical personnel to do the various works of schemes for Building Permit and supervision in the G.M.D.A.

under Sec. 123 of G.M.D.A. Act, in response to your Notification No. GMDA/ ……………………... as Architect/ Engineer/ Supervisor.

I do hereby also declare that I shall follow and will abide by all the rules and regulations now in force and that may be framed from time under the provision of the G.M.D.A. Act, 1985.

My personal bio-data are as follows- Name :

Qualification :

(Certificate to be enclosed) Past experience :

Father’s Name :

Age :

Present Address :

Permanent Address :

I deposit herewith annual enrolment fees of Rs………...

(Rupees………………..) only in cash as required.

Signature:

Dated:

N.B. I am not associated with any other similar group or agency in any manner for this purpose.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [70] FORM-B Application for Enrolment as Competent Technical Personnel in G.M.D.A. in Group or Agency To, The Chief Executive Officer, Guwahati Metropolitan Development Authority, Bhangagerh, Guwahati-5 We hereby apply for enrolment of our Group/Agency in the name and style as mentioned below, as competent technical personnel to do the various works of schemes for Building Permit and supervision under sec. 123 of G.M.D.A. Act in response to your notification No. GMDA/ …………………………..

We do hereby also declare that we shall follow and will abide by all the rules and regulations now in force and that may be framed from time to time under the provision of the G.M.D.A. Act, 1985. Name of the group and persons associated with personal bio-data are as follows-

1. Name of the Group or Agency: -

2. Present & Permanent Address: -

3. Name of persons associated: - with his/ her personal capacity and rank and personal bio-data (Certificates enclosed) (A) (B) (C) (D)

4. We deposit herewith the annual enrolment fees of Rs………...

(Rupees…………) only in cash as required.

Signature of head of the group or agency.

N.B. Any person associated with any group or agency will not be eligible for enrollment as an individual.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [71] FORM NO. 1 CERTIFICATE OF UNDERTAKING FOR HAZARD SAFETY REQUIREMENT TO, REF : Proposed work of _____________________________________________________ (Title of project) Dag No. _______________ Patta No.__________________ of Revenue Village _______ __ ___________________ under _____________ Mouza situated at _______________________ Guwahati.

1. Certified that the building plans submitted for approval will satisfy the safety requirements as stipulated under Building Regulation No. … and the information given therein is factually correct to the best of our knowledge and understanding.

2. It is also certified that the structural design including safety from hazards based on soil conditions shall be duly incorporated in the design of the building and these provisions shall be adhered to during the construction.

Signature of Owner with date _________________ Name in Block Letters _________ Structural Engineer on Record with date Address__________________ Name in Block Letters _______ _________________________ Address___________________ _________________________ _________________________ Signature of Developer Signature of the Architect on with date _________________ Record/ Engineer on Record with date _______ Name in Block Letters _______ Name in Block Letters ______ Address___________________ Address__________________ NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [72] FORM NO. 2 CERTIFICATE OF UNDERTAKING OF ARCHITECT ON RECORD/ ENGINEER ON RECORD To Ref : Proposal work of _____________________________________________________ (Title of the project) Dag No. _______________ Patta No.__________________ of Revenue Village _______ __ ___________________ under _____________ Mouza situated at _______ _____ ________ Guwahati.

For___________________________________________________________________ (Name of Owner /Developer/Builder) Address:_______________________________________________________________ Tel.No.:_______________________________________________________________ I am a member of Council of Architects/Institution of Engineers (India) and I am possessing current registration to act as registered Architect/Engineer.

I hereby certify that I am appointed as the Architect on Record / Engineer on Record to prepare the plans, sections and details as required under the provisions of the Act / Development control Regulations for the above mentioned project and that I have prepared and signed the same and that the execution of the project shall be carried out under my direction, and supervision of a Construction Engineer on Record, as per the approved drawings. I am fully conversant with the provisions of the Regulations, which are in force, and about my duties and responsibilities under the same and I undertake to fulfill them in all respects, except under the circumstances of natural calamities.

I also undertake to provide my guidance for the adequate measure to be taken by the owners for installation of plumbing, drainage, sanitation and water supply. The appointment of a Construction Engineer on Record, building contractor, plumbing contractor and electrical contractor shall be made at the appropriate stage by the owner before the relevant work commences.

Signature : _______________ Reg. No. ________Date:____ Name : _______________________ Address : _____________________ _____________________________ Tel. No. : _____________________ NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [73] FORM NO. 3 CERTIFICATE OF UNDERTAKING OF STRUCTURAL ENGINEER ON RECORD (SER) To Ref : Proposed work of _____________________________________________________ (Title of the project) Dag No. _______________ Patta No.__________________ of Revenue Village _______ __ ___________________ under _____________ Mouza situated at ____ ____ ______ __ Guwahati.

Owner:_______________________________________________________________ Address:______________________________________________________________ Tel. No.: _____________________________________________________________ I am a Registered Structural Engineer (RSE). This is to certify that I have been appointed as the Structural Engineer on record to prepare the Structural design basis report, detailed structural design and detailed structural drawings for above mentioned project. I am fully conversant of my duties and responsibilities under the Regulations and assure that I shall fulfill them in all respects.

I have prepared and signed a structural design basis report SDBR).

I undertake to carry out a detailed structural design and prepare detailed structural drawings of the proposed building as per the latest Indian Standard Specifications, and as indicated in the Structural design basis report.

I undertake to supply the owner and the supervisor the detailed structural drawings. If my services are terminated, I undertake to intimate the Authority in writing.

Signature : ________________ Reg. No. _______ Date : _____ Name : _________________________________ Address : _______________________________ Tel. No. : _______________________________ NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [74] FORM NO.4 CERTIFICATE OF UNDERTAKING OF THECONSTRUCTION ENGINEER ON RECORD To...............................................

...................................................

Ref : Proposed work of ...................................................................…………………….

(Title of the work ) Dag No. _______________ Patta No.__________________ of Revenue Village _______ __ ___________________ under _____________ Mouza situated at __________ ______ Guwahati.

Owner :

Address :

Tele. No........................................

I possess a current registration to act as Registered Construction Engineer.

I hereby certify that I am appointed as a Construction Engineer on Record on the above mentioned project and that all the works under my charge shall be executed in accordance with the drawings and specifications prepared for this project.

I am fully conversant with the provisions of the Regulations which are in force and about the duties and responsibilities under the same and I undertake to fulfill them in all respect.

* I undertake not to supervise more than ten works at a given time as provided in Development Control Regulations.

* I undertake not to supervise work simultaneously at one point of time on any other sites during my supervision of the execution of this work.

Signature:……………..………… Registration No............Date.........

Name.........................................................

Address.....................................................

Tele.No.....................................................

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [75] FORM NO. 5 DEVELOPMENT PERMISSION ______________________________________________________________________ Permission is hereby granted / refused under Section ___________________________ ______________________________________________________________________ to____________________________________________________________________ (Name of the person) for___________________________________________________________________ (Description of work) on the following conditions / grounds Conditions:

(in case of grant) subject to the submission of structural design basis report along with soil investigation report at least one month in advance and subsequent approval before the commencement of the work.

Grounds:

(in case of refusal) a) Documents / N.O.C. etc.: - Following documents / plans / N.O.C/ undertakings as mentioned in form no. --- --(application for Development permission) are not submitted.

b) Site Clearance: -

(i) Site is not cleared as per the provisions of Development Plan with respect to - Road line - Reservations - Zone - Other (specify)

(ii) Site is not cleared as per the provision of T.P. Scheme ……… with respect to - Road - Reservation - Final plot - Other (specify)

(iii) Proposed use is not permissible according to the width of road as per the provision No………… NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [76] FORM NO. 6 STRUCTURAL DESIGN BASIS REPORT

1. This report to accompany the application for Building Development Permission.

2. In case information on items 3, 10, 17, 18 and 19 can not be given at this time, it should be submitted at least one week before commencement of construction.

Part 1: General Data Sl No Description Information Notes 1 Address of the building • Name of the building • Plot number • Subplot number • TPS scheme a. Name b. Number • Locality/Township • District 2 Name of owner 3 Name of Builder on record 4 Name of Architect/Engineer on record 5 Name of Structural engineer on record 6 Use of the building 7 Number of storeys above ground level (including storeys to be added later, if any) 8 Number of basements below ground Level 9 Type of structure • Load bearing walls • R.C.C frame • R.C.C frame and Shear walls • Steel frame 10 Soil data • Type of soil • Design safe bearing capacity IS: 1893 Cl. 6.3.5.2 IS: 1904 11 Dead loads (unit weight adopted) • Earth • Water • Brick masonry • Plain cement concrete • Reinforced cement concrete • Floor finish • Other fill materials • Piazza floor fill and landscape IS: 875 Part 1 12 Imposed (live) loads • Piazza floor accessible to Fire Tender • Piazza Floor not accessible to Fire Tender IS: 875 Part 2 NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [77] . h�Floor loads . h�Roof loads 13 Cyclone / Wind • Speed • Design pressure intensity IS: 875 Part 3 14 Seismic zone IS:1893 2002 15 Importance factor IS:1893 (2002) Table 6 16 Seismic zone factor(Z) IS:1893 Table 2 17 Response reduction factor IS: 1893 Table-7 18 Fundamental natural period - approximate IS: 1893 Cl. 7.6 19 Design horizontal acceleration spectrum value (Ah) IS: 1893 Cl. 6.4.2 20 Expansion / Separation Joints Part 2: Load bearing masonry buildings Sl No Description Information Notes 1 Building category IS:4326 Cl. 7 read with IS: 1893 Bld/Zone II III IV V Ord. B C D E Important C D E E 2 Basement Provided 3 Number of floors including Ground Floor (all floors including stepped floors in hill slopes) 4 Type of wall masonry 5 Type and mix of Mortar IS:4326 Cl. 8.1.2 6 Re: size and position of openings (See note No.1) • Minimum distance (b5) • Ratio (b1+b2+b3)/l1 or (b6+b7)/l2 • Minimum pier width between consequent opening (b4) • Vertical distance (h3) • Ratio of wall height to thickness4 • Ratio of wall length between cross wall to thickness IS:4326 Table 4, Fig.7 7 Horizontal seismic band • at plinth level • at window sill level • at lintel level • at ceiling level • at eave level of sloping roof • at top of gable walls • at top of ridge walls P IP NA (see note no.2) IS:4326 Cl. 8.4.6 IS:4326 Cl. 8.3 IS:4326 Cl. 8.4.2 IS:4326 Cl. 8.4.3 IS:4326 Cl. 8.4.3 IS:4326 Cl. 8.4.4 8 Vertical reinforcing bar • at corners and T junction of walls • at jambs of doors and window openings IS:4326 Cl. 8.4.8 IS:4326 Cl. 8.4.9 9 Integration of prefab roofing/flooring elements through IS:4326 Cl. 9.1.4 NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [78] reinforced concrete screed 10 Horizontal bracings in pitched truss • in horizontal plane at the level of ties • in the slopes of pitched roofs Part 3 : Reinforced concrete framed buildings Sl No Description Information Notes 1 Type of Building i�Regular frames i�Regular frames with Shear walls i�Irregular frames i�Irregular frames with shear walls i�Soft storey IS: 1893 Cl. 7.1 2 Number of basements 3 Number of floors including ground floor 4 Horizontal floor system i�Beams and slabs i�Waffles i�Ribbed Floor i�Flat slab with drops i�Flat plate without drops 5 Soil data i�Type of soil iRecommended type of foundation - Independent footings - Raft - Piles iRecommended bearing capacity of soil iRecommended, type, length, diameter and load capacity of piles iDepth of water table iChemical analysis of ground water iChemical analysis of soil IS: 1498 6 Foundations iDepth below ground level iType • Independent • Interconnected • Raft • Piles 7 System of interconnecting foundations i�Plinth beams i�Foundation beams IS: 1893 Cl. 7.12.1 8 Grades of concrete used in different parts of building 9 Method of analysis used 10 Computer software used IS: 1893 Cl. 7.9 11 Torsion included 12 Base shear a. Based on approximate fundamental period b. Based on dynamic analysis IS: 1893 Cl. 7.5.3 NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [79] c. Ratio of a/b 13 Distribution of seismic forces along the height of the building IS:1893 Cl. 7.7 (provide sketch) 14 The column of soft ground storey specially designed IS:1893 Cl. 7.10 15 Clear minimum cover provided in • Footing • Column • Beams • Slabs • Walls IS: 456 Cl. 26.4 16 Ductile detailing of RC frame • Type of reinforcement used • Minimum dimension of beams • Minimum dimension of columns • Minimum percentage of reinforcement of beams at any cross section • Maximum percentage of reinforcement at any section of beam • Spacing of transverse reinforcement in 2-d length of beams near the ends • Ratio of capacity of beams in shear to capacity of beams in flexure • Maximum percentage of reinforcement in column • Confining stirrups near ends of columns and in beam-column joints a. Diameter b. Spacing • Ratio of shear capacity of columns to maximum seismic shear in the storey IS: 456 Cl. 5.6 IS:13920 Cl. 6.1 IS:13920Cl. 7.1.2 IS: 456 Cl. 26.5.1.1(a) IS:13920 Cl. 6.2.1 IS: 456 Cl. 26.5.1.1(b) IS:13920 Cl. 6.2.2 IS: 13920 Cl. 6.3.5 IS: 456 Cl. 26.5.3.1 IS: 13920 Cl. 7.4 General Notes

1. A certificate to the effect that this report will be completed and submitted at least one month before commencement of Construction shall be submitted with the application for Building Development Permission.

2. In addition to the completed report following additional information shall be submitted, at the latest, one month before commencement of Construction.

2.1 Foundations

2.1.1 Incase raft foundation has been adopted indicate K value used for analysis of the raft

2.1.2 Incase pile foundations have been used give full particulars of the piles, type, dia, length, capacity

2.1.3 Incase of high water table indicate system of countering water pressure, and indicate the existing water table, and that assumed to design foundations.

2.2 Idealization for Earthquake analysis

2.2.1 Incase of a composite system of shear walls and rigid frames, give distribution of base shear in the two systems on the basis of analysis, and that used for design of each system.

2.2.2 Indicate the idealization of frames and shear walls adopted in the analysis with the help of sketches.

2.3 Submit framing plans of each floor

2.4 Incase of basements, indicate the system used to contain earth pressures Part 4 : Buildings in Structural Steel 1 Adopted method of Design O Simple O Semi-rigid O Rigid IS: 800; Cl. 3.4.4 IS: 800; Cl. 3.4.5 IS: 800; Cl. 3.4.6 NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [80] 2 Design based on O Elastic analysis O Plastic analysis IS: 800; Section-9 SP: 6 (6) 3 Floor Construction O Composite O Non-composite O Boarded 4 Roof Construction O Composite O Non-composite O Metal O Any other 5 Horizontal force resisting system adopted O Frames O Braced frames O Frames & shear walls Note: Seismic force As per IS:

1893Would depend on system 6 Slenderness ratios maintained Members defined in Table 3.1, IS: 800 IS: 800; Cl. 3.7 7 Member deflection limited to Beams, Rafters Crane Girders Purlins Top of Columns IS: 800; Cl. 3.13 8 Structural members O Encased in Concrete O Not encased IS: 800; Section-10 9 Proposed material O General weld-able O High strength O Cold formed O Tubular IS: 2062 IS: 8500 IS: 801, 811 IS: 806 10 Minimum metal thickness Specified for corrosion protection O Hot rolled sections O Cold formed sections O Tubes IS: 800, Cl. 3.8 Cl. 3.8.1 to Cl. 3.8.4 Cl. 3.8.5 Cl. 3.8.5 11 Structural connections O Rivets O C T Bolts O S H F G Bolts O Black Bolts O Welding- Field Shop (Specify welding type proposed) O Composite IS: 800; Section-8 IS: 1929,2155,1149 IS: 6639, 1367 IS: 3757, 4000 IS: 1363, 1367 IS: 816, 814, 1395, 7280, 3613, 6419 6560, 813, 9595 Minimum Fire rating Proposed, with method O Rating ---------- hours O Method proposed- - In tumescent Painting - Spraying - Quilting - Fire retardant boarding IS: 1641, 1642, 1643 NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [81] FORM NO. 7 PROGRESS CERTIFICATE Plinth Stage / In case of basement casting of basement slab Reference No.

Owner's Name: Location:

Submitted on: Received on:

The Sir, We hereby inform you that the work of execution of the building as per approved plan, working drawing and structural drawings has reached the plinth level and is executed under our supervision. We declare that the amended plan is not necessary at this stage.

Yours faithfully, Signature of the Signature of the Construction Engineer on Record Owner/ Developer/ Builder Date:________________________ Date: ____________________ Name in block letters: Name in block letters _____________________________ _________________________ Address:______________________ Address ___________________ _____________________________ __________________________ _____________________________ __________________________ NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [82] FORM NO. 8 PROGRESS CERTIFICATE - FIRST STOREY Reference No.

Owner's Name: Location:

Submitted on: Received on:

The Sir, We hereby inform you that the work of execution of the building as per approved plan, working drawing and structural drawings has reached the first storey level and is executed under our supervision.

We declare that the amended plan is not necessary at this stage.

Yours faithfully, Signature of the Signature of the Construction Engineer on Record Owner/ Developer/ Builder Date:________________________ Date: ____________________ Name in block letters: Name in block letters _____________________________ _________________________ Address:______________________ Address ___________________ _____________________________ __________________________ _____________________________ __________________________ NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [83] FORM NO. 9 PROGRESS CERTIFICATE - MIDDLE STOREY IN CASE OF HIGH-RISE BUILDING Reference No.

Owner's Name: Location:

Submitted on: Received on:

The Sir, We hereby inform you that the work of execution of the building as per approved plan, working drawing and structural drawings has reached ___________ storey level and is executed under our supervision.

We declare that the amended plan is not necessary at this stage.

Yours faithfully, Signature of the Signature of the Construction Engineer on Record Owner/ Developer/ Builder Date:________________________ Date: ____________________ Name in block letters: Name in block letters _____________________________ _________________________ Address:______________________ Address ___________________ _____________________________ __________________________ _____________________________ __________________________ NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [84] FORM NO. 10 PROGRESS CERTIFICATE - LAST STOREY Reference No.

Owner's Name: Location:

Submitted on: Received on:

The Sir, We hereby inform you that the work of execution of the building as per approved plan, working drawing and structural drawings has reached ___________ storey level and is executed under our supervision.

We declare that the amended plan is not necessary at this stage.

Yours faithfully, Signature of the Signature of the Construction Engineer on Record Owner/ Developer/ Builder Date:________________________ Date: ____________________ Name in block letters: Name in block letters _____________________________ _________________________ Address:______________________ Address ___________________ _____________________________ __________________________ _____________________________ __________________________ NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [85] FORM NO. 11 COMPLETION REPORT Reference No.

Owner's Name: Location:

Submitted on: Received on:

The Sir, The work of erection/re-erection of building as per approved plan is completed under the Supervision of Architect/Construction Engineer who have given the completion certificate which is enclosed herewith.

We declare that the work is executed as per the provisions of the Act and Development Control Regulations / Byelaws and to our satisfaction. We declare that the construction is to be used for ______________ the purpose as per approved plan and it shall not be changed without obtaining written permission.

We hereby declare that the plan as per the building erected has been submitted and approved. We have transferred the area of parking space provided as per approved plan to an individual/association before for occupancy certificate.

Any subsequent change from the completion drawings will be our responsibility.

Yours faithfully, (Developer’s / Builder’s Signature) (Owner’s Signature) Name of Developer / Builder Name of Owner Date:

Address:

Encl: Completion Certificate NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [86] FORM NO. 12 BUILDING COMPLETION CERTIFICATE BY ARCHITECT ON RECORD Reference No.

Owner's Name: Location:

Submitted on: Received on:

The Sir,

1. The building/s has/have been constructed according to the sanctioned plan.

2. The building/s has /have been constructed as per approved plan and design as per detailed architectural drawings and specifications prepared by Architect on Record.

3. Construction has been done under our supervision / guidance and adheres to the drawings submitted.

Signature of the Owner Signature of Architect on Record Date Date Name in block letters: Name in block letters _____________________________ _________________________ Address:______________________ Address ___________________ _____________________________ __________________________ _____________________________ __________________________ NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [87] FORM NO. 13 BUILDING COMPLETION CERTIFICATE BY CONSTRUCTION ENGINEER ON RECORD Reference No.

Owner's Name: Location:

Submitted on: Received on:

The Sir,

1. The building/s has/have been constructed according to the sanctioned plan.

2. The building/s has / have been constructed as per - the detailed structural drawings and structural specifications prepared by the Structural Engineer on Record - the detailed Architectural drawings and Architectural specifications prepared by the Architect on Record.

- detailed drawings and specifications of all services

3. All materials used in the construction have been tested as provided in specifications and a record of test reports has been kept.

Signature of the Owner Signature of Construction Engineer on Record Date Date Name in block letters: Name in block letters _____________________________ _________________________ Address:______________________ Address ___________________ _____________________________ __________________________ _____________________________ __________________________ NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [88] FORM NO. 14 BUILDING COMPLETION CERTIFICATE BYTRUCTURAL ENGINEER ON RECORD Reference No.

Owner's Name: Location:

Submitted on: Received on:

The Sir, This is to certify that detailed structural drawings of the buildings/s has / have been prepared on the basis of a detailed analysis and a detailed design carried out according to relevant previsions of the latest Indian Standard Codes, National Building Code and as indicated in the structural design basis report.

Signature of the Owner Signature of Structural Engineer on Record Date Date Name in block letters: Name in block letters _____________________________ _________________________ Address:______________________ Address ___________________ _____________________________ __________________________ _____________________________ __________________________ NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [89] FORM NO. 15 MODEL PROFORMA FOR TECHNICAL AUDIT REPORT

1. Design COMMENTS

1.1 Design / Drawings available Y/N Design Category Type Design?

Specific design?

Y/N Design to be collected to refer to Design Consultant / H.O.

Drawings prepared / checked by competent Authority ? Y/N Design Drawings / details Structural detailed included Earthquake / cyclone resistant features included?

Y/N Design verified / vetted by Dept. / Govt. approved agency / competent authority?

Y/N Design changes approved by Dept. / Govt. approved agency / competent authority?

Y/N

2. Foundation

2.1 Foundation used Existing/New

2.2.1 If existing foundation used

2.2.1 Depth of foundation below ground : <50cm/50-70/>70cm

2.2.2 Type of foundation : Isolated/Combined/Raft/Piled etc.

2.2.3 Thickness of masonry (above ground) :

2.2.4 Mortar used and Mix of cement mortar : Cement-Sand/Lime and 1:4/1:6/Leaner

2.2.5 Grade of concrete (M20) : Y/N

2.2.6 Height up to Plinth : ________________ cm

2.2.7 If stone masonry

2.2.7.1 Through Stones : Yes/No, if Yes Adequate / Inadequate

2.2.7.2 Corner Stones : Yes/No, if Yes Adequate/Inadequate

2.3 If new foundation used

2.3.1 Depth of foundation below ground : _____ <50/50-70/>70cm

2.3.2 Type of foundation : Isolated/Combined/Raft/Piled etc.

2.3.3 Thickness of Masonry above plinth : ____________________________

2.3.4 Mortar used and Mix of cement mortar (1:4): Cement – sand/lime/mud and Y/N

2.3.5 Grade of concrete (M20) :Y/N

2.3.6 Height up to Plinth : <60/>60cm

2.3.7 If stone masonry

2.3.7.1 Through Stones : Yes/No, if Yes Adequate/Inadequate

2.3.7.2 Corner Stones : Yes/No, if Yes Adequate/Inadequate Vertical reinforcement in foundation : Yes/No NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [90] 3 Walling

3.1 Type of masonry : Brick/PCC Blocks/ Stone

3.2 Mortar used : Cement – Sand/Lime

3.3 Mix of cement mortar : 1:4/1:6/Leaner

3.4 Thickness of wall : >23cm/23cm/23cm

3.5 Mixing of mortar : OK/Not OK

3.6 Joint Property filled : OK/NOT OK

3.7 Wetting of bricks : Good/ Medium/ Poor

3.8 If stone masonry

3.8.1 Through Stones : Yes/No

3.8.2 Corner Stones : Yes/No

3.9 Overall workmanship : Good / Medium / Poor 4 Roofing

4.1 Type of roof : Flat/Sloping

4.2 If sloped : A.C. sheet/ G.I. sheet /Morbid tiles

4.3 Purlins : Angle-Iron / Timber / NA

4.4 Truss type : _______________________

4.5 Anchorage with wall : Adequate/ Inadequate/ NA 5 Materials

5.1 Cement

5.1.1 Source : Authorized Dealer/ Market

5.1.2 Type of cement : OPC/PPC/PSC

5.1.3 If OPC : Grade (33/ 43/ 53)

5.2 Sand

5.2.1 Type of sand : River sand / Stone dust

5.2.2 Presence of deleterious materials : Mild / Moderate/ High

5.3 Coarse Aggregates

5.3.1 Type coarse Aggregates : Gravel/ Crushed Stone

5.3.2 Presence of deleterious material : Mild/ Moderate / High

5.4 P.C.C. Blocks (Applicable for onsite production)

5.4.1 Type of P.C.C. Blocks : Solid blocks/Hollow blocks

5.4.2 Ratio of concrete in blocks : ______________________

5.4.3 Interlocking feature : Yes/No

5.4.4 Course aggregates used : Natural/ Crushed stone

5.5 Bricks Blocks, Stone etc.

5.5.1 Strength (field assessment) : Low/Medium/High

5.5.2 Dimensional accuracy : Yes/No

5.6 Concrete

5.6.1. Mix of concrete : M20/Design Mix

5.6.2 Batching : Weigh batching/Volume batching

5.6.3 Compaction : Vibrators/Thappies and rods

5.6.4 Workability : Low / Medium / High NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [91]

5.6.5 Availability of water : Optimum/Sufficient / Insufficient

5.6.6 Curing : Satisfactory/Unsatisfactory.

5.7 Reinforcing Steel

5.7.1 Type of Steel : Plain mild steel/HYSD bars

5.7.2 Source : Authorised Dealer/Market

5.7.3 Whether IS marked : Yes/No

5.7.4 Conditions of bars : Clean/Corroded

5.7.5 Fixing of reinforcement as per drawing : Yes/No

5.7.6 Suitable cover : Yes/No

5.7.7 Spacing of bars : Regular/Irregular

5.7.8 Overlaps as per specifications : Yes/ No

5.8 Form Work

5.8.1 Type of Form Work : Timber / Plyboard/ Steel

5.8.2 Use of mould oil : Yes/No

5.8.3 Leakage of cement slurry : Observed/Not observed

5.9 Source

5.9.1 Cement

5.9.2 Sand

5.9.3 Coarse Agg.

5.9.4 Bricks

5.9.5 PCC blocks.

6 Seismic resistance features

6.1 Masonry Structures

6.1.1 Provision of bands at Provided Adequate

6.1.1.1 Plinth level Yes/No Yes/No

6.1.1.2 Sill level Yes/No Yes/No

6.1.1.3 Lintel level Yes/No Yes/No

6.1.1.4 Roof level (if applicable) Yes/No Yes/No

6.1.2 If sloped Roof, whether seismic bands are provide at

6.1.2.1 Gable wall top Yes/No Yes/No

6.1.2.2 Eaves level Yes/No Yes/No

6.1.3 Provision of vertical steel in masonry at Provided Adequate

6.1.3.1 Each corner Yes/No Yes/No

6.1.3.2 Each T-junction Yes/No Yes/No

6.1.3.3 Each door joint Yes/No Yes/No

6.1.3.4 Around each window Yes/No Yes/No

6.1.4 Openings

6.1.4.1 Total width of openings : <50%/50*-60%/>60% (*-42% for double storey)

6.1.4.2 Clearance from corner : OK/Not OK

6.1.4.3 Pier width between two openings : OK/Not OK NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [92]

6.2 Framed Structures

6.2.1 Ductile detailing

6.2.1.1 Spacing of stirrup : OK/Not OK

6.2.1.2 Sizes of members : OK/Not OK

6.2.1.3 End anchorage : OK/Not OK

6.2.1.4 Lapping (length, location etc.) : OK/Not OK

6.2.1.5 Angle of stirrup hook : 90 / 135 degrees

6.3 Any testing carried out by Owner/Engg. Supervisor on Testing done Testing results

6.3.1 Water Yes/No OK/Not OK

6.3.2 Cement Yes/No OK/Not OK

6.3.3 Bricks/PCC blocks/Stones Yes/No OK/Not OK

6.3.4 Aggregate Yes/No OK/Not OK

6.3.5 Mortar Yes/No OK/Not OK

6.3.6 Concrete Yes/No OK/Not OK

6.3.7 Reinforcement Yes/No OK/Not OK NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [93] FORM NO. 16 STRUCTURAL INSPECTION REPORT (This form has to be completed by registered Structural Designer after his site Inspection and verification regarding compliance of all recommendation by the owner, which in the opinion of the registered structural designer are necessary for safety of the structure) I. Description by title and location of the property including T.P.No., F.P.No.

etc.

II. Name of the present owner :

III. Description of the structure :

Class I or Class II (Briefly describe the property in general and the structure in particular)

(a) Function (b) Framed construction Residence (with or without shops Apartments (with or without shops Office Bldg.

Shopp - ing Centre School, College Hostel Auditoria Factory 1 2 3 4 5 6 7 8 9 A. Load bearing masonry wall construction B. Framed structure Construction Construction and structural materials Critical load bearing element Brick RCC Stone Timber Steel Roof Floor RCC Timber RBC Steel Jackarch IV. Year of construction Year of subsequent additions or rectification’s (Please describe briefly the nature of additions or rectification’s). :

V. Date of last inspection report filed : Last filed by whom :

(This does not apply to the first report).

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [94] VI. Soil on which building is founded :

i) Any change subsequent to construction :

ii) Nearby open excavation :

iii) Nearby collection of water :

iv) proximity of drain :

v) underground water-tank :

vi) R.W. Pipes out-lets :

vii) Settlements :

VII. The Super-structure (R.C.C. Frame structure) I) Crack in beam or column nature and extent of crack :

probable causes.

ii) Cover spell :

iii) Exposure of reinforcement iv) subsequent damage by user for taking pipes, :

conduits, hanging, fans or any other fixtures, etc. :

vi) Crack in slab :

vii) Spalling of concrete or plaster of slab :

viii) Corrosion of reinforcement :

ix) Loads in excess of design loads :

VIII The Super-Structure (Steel Structure) I) Paintings :

ii) Corrosion :

iii) Joint, nuts, bolts, rivets, welds, gusset plates :

iv) Bending or buckling of members :

v) Base plate connections with columns or pedestals :

vi) Loading :

IX. The Super-Structure (Load bearing masonry structure) Cracks in masonry walls) (Please describe some of the major cracks, their nature, :

extent and location, with a sketch, if necessary.

X. Recommendations if any :

This is to certify that the above is a correct representation of facts as given to me by the owner and as determined by me after Site Inspection to the best of my ability and judgment.

The recommendations made by me to ensure adequate safety of the structure are compiled with by the owner to my entire satisfaction.

(Signature of the Registered Structural Engineer Date:______________________________________ Name of the registered structural Engineer:

Registration No. Address:

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [95] Chapter-VII Notification of “Additional FAR scheme for widening of roads and improvement of junctions” Guwahati Metropolitan Development Authority of Guwahati is taking up road widening and junction improvement programmes in Guwahati city with peoples’ cooperation.

Under Section 63(b) of Building Byelaws for Guwahati Metropolitan Area , 1998 the Authority may consider allowing additional FAR if any person relinquishes land for road widening or creation of open space, without asking for compensation. Hence the Authority framed the following guidelines for road widening and junction improvement programme for this purpose:

1. In addition to the “permissible F.A.R” to the total extent of the plot area an additional F.A.R (AFAR) of 100 shall be considered to the extent of the land affected in road widening and junction improvement and surrendered free of cost for constructing / reconstructing building as per land use of Master Plan. However the Authority will consider commercial use with 50 AFAR even if the Landuse is earmarked for Residential or other uses except Parks and Play Ground and Green Belt use as per Master Plan. The AFAR for commercial use can be utilized in any floor after obtaining permission of the Authority, who shall consider it keeping in view the developments existing on the road/junction , feasibility and smooth flow of traffic. “ Permissible FAR” is the FAR permissible in that particular plot irrespective of maximum FAR allowed as per Building Byelaws.

2. Wherever permissible FAR cannot be achieved on plots after road widening and junction improvement with the stipulated set backs as per Building Byelaws and Zoning Regulations the relaxation of set back and coverage can be considered by the Chief Executive Officer, Guwahati Metropolitan Development Authority.

3. While exercising the above powers the G.M.D.A. shall finalise a suitable building line (i.e.

front setback) for the complete portion of the road taken up for widening or junction taken up for improvement , keeping in view the developments existing on the road/junction , feasibility and smooth flow of traffic and notify the same for the benefit of owners of the sites affected in road widening /junction improvement. No construction shall be allowed in violation of such notified building line. While exercising the above powers the Guwahati Metropolitan Development Authority shall ensure public interest and safety and smooth flow of traffic.

4. The relaxation powers referred are applicable to roads notified for widening / junctions notified for improvement under this scheme by the Authority and no isolated case on a particular road or junction will be considered for this relaxation.

Example :- If the plot area is 500 sq. mts and the land affected in road widening is 100 sq.

mts and the permissible FAR as per regulation is 150* the normal floor area permissible is 750 sq.mts. The additional floor area permissible is as follows:- Use Proposed for Additional FAR Additional Floor Area.

Residential 100 Sq. Mts Commercial 50 Sq. Mts NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [96]

5. The relaxed FAR will be issued in the form of a bond to the owners of the affected plot which has to be utilized in a period of five years from the date of issue of this bond.

6. In case of building constructed unauthorizedly beyond the permissible FAR proposal will be considered for regularization up to the additional FAR allowed as per this scheme.

Chief Executive Officer, Guwahati Metropolitan Dev. Authority.

Bhangagarh, Guwahati-5 NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [97] APPLICATION FORMAT 1) Name of Applicant :

2) Father’s/Husband Name :

3) Name of land owner if applicant & :

land owner are separate.

4) Details of building permission, name, No. & date of issue :

5) State if land owner has given any NOC for construction to applicant :

6) Detail of building at site.

(i) No. of floors at present :

(ii) Area of each floor :

(iii) Use of building :

7) (a) Total plot area :

(b) Plot size. North……..….. South ……..……. East…………... West………… 8) Detail of plot :

(i) Dag No.________ Patta No____________

(ii) Revenue Village _____________________

(iii) Name of Road_______________________ I do hereby declare that the information given above are true to the best of my knowledge. In the event of submitting false information, I will be held responsible as per law. I hereby agree to relinquish the land for road widening in return of additional FAR given to me in my plot under the Additional FAR scheme under section 63(b) of Building Byelaws of GMDA declared vide Notification No.GMDA/GEN/8/99/Part-I/10 ,dated- 8/12/2003.

Applicant’s Signature.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [98] Area Statement (For all categories of buildings) (A) Plot area:- ……………………………………………………………………………………………………………..

(B) Plinth area (I) Existing plinth Area (if any):- ……………………………….………………………………………..

(II) Proposed plinth Area:- ……………….…………………………………………………………………...

(C) Floor area showing detail calculation of each floor (Existing + Proposed):- ……………………………………………………………………………………………………………...…………......… (D) Detail of mezzanine floor area:- ……………………………………………………...………………...… (E) Deduction showing detail calculation of each floor (Existing + Proposed):- ……………………………………………………………………………………………...………………………………..

(F) Total floor area after deduction (Existing + Proposed):- …………..………………………… ………………………………………………………………………………………………...……………………………..

(G) Total floor area before deduction (Existing + Proposed):- ………..………………………… ……………………………………………………………………………………………………………………………….

(H) Coverage (Existing + Proposed):- ……………………………………………………………………..… (I) Floor Area Ratio (FAR) (Existing + Proposed):- …………..…………………………………….

………………………………………………………….… ………………………………………………………….… Signature of the owners: Signature of registered Architect/Engineer/ supervisor Name of owner(s): Registration no. of the Architect/Engineer/ supervisor:

Address of the owner(s): Address of the Architect/Engineer/ supervisor:

Dated: Dated:

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [99] Annexure- A-1 Statement of the Proposal and Certificate By the Owner and Registered Architect (For above G+2) Classification of the Proposal ………………………………………………………………………………….……….

(To erect/re-erect/demolition) Revenue Village : ………………………………………………………………………………...…………………..

Mouza :

Dag No. : …………………………………Patta No. : ………………………………………… Road facing the plot : ………………………………………………………………………………….……..…….…….

(1) Existing road width Sl. No. Existing road width Proposed road width Remarks

(1) Plot Area

(a) As per site plan : …………………………………………………….……………………

(b) As per land document : …………………………………………………….……………………

(2) Area Statement Description Proposed sq. mt.

Use Permissible (For office use) Remarks Max. ground coverage Basement Ground floor Mezzanine First floor Second floor Third floor Fourth floor Fifth floor Sixth floor Seventh floor Eighth floor Ninth floor Tenth floor Service floor (if any) Total floor area Floor area ratio No. of Dwelling units NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [100]

(3)

(a) Maximum height of building (in meter): ………………………………….

(b) Maximum height of the plinth (in meter): ………………………………...

(4) Set backs Setbacks Proposed Required as per byelaws (For office use) Remarks Clear setback (in meter) Cantilever projection over setback (in meter) Clear setback (in meter Cantilever projection over setback (in meter Front Rear Left Right

(5) Duct No. of duct Area of duct (in sq. mt.) Minimum width of the shaft (in meter)

(6) Distance from the electric line (if any):

Nature of electric line Vertical distance (in meter) Horizontal distance (in meter)

(7) Parking (A) Parking provided as per clause no. 58.10.4 of GMDA’s Building Byelaws:

Open parking Stilt parking or ground floor covered parking Basement parking Total no. of parking (B) Parking required as per Appendix-I of GMDA’s Byelaws (For office use):

Sl. No. Type of use of building CAR parking Scooter parking Remarks (C) Visitor’s car/Scooter parking required as per clause no. 58.10.4 of GMDA’s Byelaws:

Sl. No. Type of use of building Car parking Scooter parking N.B. For Educational building 20% of the total plot area is required to be kept for parking in organised manner with separate entry and exit gate.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [101]

(8) Fee and charges (For office use)

(a) Building permit fee : Rs. ……………

(b) Use of city infrastructure charges : Rs. ……………

(c) Additional floor space charges (provisional) : Rs. ……………

(d) Peripheral charges (if any) : Rs. ……………

(e) Any other charges (if any, please specify) : Rs. …………… Total amount (as per detail above) Rs. …………… Receipt No. ……………………….. Dated ………………………………… We hereby certify that-

(1) The titleship document is to justify the ownership of land and its subdivision was duly approved by the GMDA before registration of the land sale deed.

(2) Plot is lying vacant and no construction shall be started before sanction.

(3) The plot is free from all encumbrances (owner responsibility).

(4) Building will not be occupied before getting occupancy certificate dully issued by Authority.

(5) Supervision in the manner prescribed in CL. 58.17 and Chapter-VI will be conducted with intimation to the Authority.

(6) Mandatory provision of rainwater harvesting is to be provided.

(7) Special earthquake resistance measure (Like shear wall/breeching etc.) has been taken to make stilt parking as an earthquake resistance structure.

…………………………………. ………………………………… Signature of the owners: Signature of registered Architect/Engineer/ supervisor Name of owner(s): Registration no. of the Architect/Engineer/ supervisor:

Address of the owner(s): Address of the Architect/Engineer/ supervisor:

Dated: Dated:

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [102] Annexure A-2 (Clause No. 5.3 (d) of GMDA’s Building Byelaws) (For above G+2) Form for specification of proposed building

(1) The purpose (Residence, Office, Restaurant, Hotel, Dharamshala, School, Hostel, Cinema, Shop, Factory. Others) for which it is intended to be used ……………….…………………………………………………..…………………….… …………………………………………………………………………………………....

(2) Details of Area on respective floor are given below Floor Existing (sq. mt.) Propsed (sq. mt.) Total (sq. mt.)

1 Basement 2 Ground 3 Mezzanine 4 First floor 5 Second floor 6 Third 7 8 9 10 Service floor (if any)

(3)

(a) Approximate number of inhabitants proposed to be accommodated ……...…….

(b) The number of Latrine. Urinals, Kitchens. Baths to be provided ………..………

(c) The source of water to be used in the construction ……………………...………

(d) Distance from public sewer (if any) …………………………………………......

(e) The materials to be used in construction walls/ Columns/ Foundations/ Roof/ Floors ………………………………….

………………………………………..

Signature of registered Architect/Engineer/ supervisor Name ………………………………………………… Registration No. ……………………………………..

Address ………………………………………………

(4) The period of construction valid up to ………………………….. as per the lease condition/further extension of the time for construction granted by the leaser is valid upto …………………. Time construction obtained form the Competent Authority.

(5) Size of dwelling unit is not more than ……………………...

………………………………….. ……………………………………… Signature of the owners: Signature of registered Architect/Engineer/ supervisor Name (in block letters): Registration no. of the Architect/Engineer/ supervisor:

Name (in block letters):

Address of the owner(s): Address of the Architect/Engineer/ supervisor:

Dated: Dated:

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [103] Authority letter I hereby authorise that Mr./Mrs. ………………………………………….. to collect the sanction whose signature is verified below.

Specimen signature of …………………… signature of the owner(s)/Registered architect Mr./Mrs. …………………………………………………………………………….

Dated received ……………………………….. Date ……………………………… (Signature of authorized person/owner/Registered Architect) Dated ………………………………… Remarks, if any ………………………… NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [104] Affidavit-cum Undertaking (For all categories of buildings except residential A.T. building and semi R.C.C. above G+2) (Affidavit of Architect/Registered Technical Personnel (RTP) of GMDA/GMC on Rs.

10/- Non-Judicial Stamp paper of specified amount to be attested by Notary Public/Metropolitan Magistrate) Ref: Proposal work of …………………………………………………………….…… (Title of the project) Dag No. ………………… Patta No. ………………… of Revenue Village ……………….. under …………………… Mouza situated at …………...………..

Road, Guwahati for ……………………………………………………………………… (Name of the owner/Developer/Builder) Address: …………………………………………………………………...………..

Telephone No. …………………… Mobile No. ……………………… I ………………………………… son of ……………..………………… Architect/Registered Technical Personnel of GMDA/GMC by profession having office at ……………………………… do hereby solemnly affirm and declares as under:

1. That I am a Licensed Architect/ Engineer/Group or Agency duly registered with the Authority vide registration no.

……………………………………………..……… Or That I am an Architect by profession and duly registered with the Council of Architecture vide registration no. ………………………………….………………

2. I hereby certify that I am appointed as the Architect/Engineer/Group or Agency on Record to provide Comprehensive Consultancy services for the above mentioned project and that I have prepared and endorsed the same and that the execution of the project shall be carried out under my direction, and supervision by a Construction Engineer on Record, as per the approved design. I am fully conversant with the provisions of the Regulations, which are in force, and about my duties and responsibilities under the same and I undertake to fulfill them in all respects, except under the circumstances of natural calamities.

3. That I or through my authorized representative have visited the site and surveyed the site and the site measurements are found to be in conformity with land area at site and land document provided to me by my client. The plot under proposal forms part of the existing Master Plan for Greater Guwahati with respect to its location, proposed land use in conformity with the existing zoning regulation and Building Byelaws.

4. The appointment of Construction Engineer on record, Building Contractor, Plumbing Contractor, Electrical Contractor, HVAC Contractor if required separately shall be met at an appropriate stage by the owner before the relevant work commences.

5. That in case the owner dispenses with my services and or deviates from the sanctioned design at any stage whatsoever, I will inform the concern authority within 48 (forty eight) hours after it is brought to my notice.

6. That nothing has been concealed and no misinterpretation has been made while designing the project and submitting the same.

NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006 Guwahati Metropolitan Dev. Authority Page No. [105]

7. That mandatory setbacks have been proposed and shall be maintained in accordance with the setbacks marked in the Layout Plan/Building Byelaws.

8. That in case any thing contrary to the above is found or established at any stage, the concern Authority shall be at liberty to lodge a complain with the Council of Architecture, New Delhi or any other competent Authority as per GMDA/GMC Act and Byelaws.

Deponent Verification:

I the above named deponent do hereby verify at …………………………. on this …………………… of ……………… 200………. that contents of the above affidavit are true and correct to my knowledge. No part of it is false and nothing has been concealed there from.

Deponent Conetnts

Where this provision sits

ActGuwahati Building Byelaws
Section60
Marginal note1 Factories
JurisdictionState of Assam
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Guwahati Building Byelaws is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.