The Bihar GazetteThe Bihar GazetteThe Bihar GazetteThe Bihar Gazette EXTRA ORDI PUBLISHED BY AUTHORIT (NO.PATNA 803) PATNA, BIHAR ELECTRICITY REGULATORY MULTI YEAR TRANSMISSION TARIFF No. BERC-SMP-23/2018 section (1) of section 181 and clauses (zd), (ze) and(zf) of section 181, read with sections 32, 61, 62, and 86, of the Electricity Act, 2003 (36 of 2003) and all other powers enabling it in that behalf, the Bihar Electricity Regulatory Commission hereby makes the following Regulations.

1. Short Title, Commencement and Extent.

1.1 These Regulations shall be called the Regulatory Commission (Multi Year Transmission Tariff and SLDC Charges) Regulations, 2018.

1.2 These Regulations shall come into force from the date of notification in the Official Gazette.

Provided that where a project or a part thereof, has been declared under commercial operation before the date of commencement of these regulations and whose tariff has not been finally determined by the Commissi respect of such project or such part thereof for the period ending

31.3.2019 shall be determined in accordance with the Bihar Electricity Regulatory Commission (Terms and Conditions for REGISTERED NO. PT.

The Bihar GazetteThe Bihar GazetteThe Bihar GazetteThe Bihar Gazette XTRA ORDINARY UBLISHED BY AUTHORITY 6 Bhadra 1940(S) PATNA, TUESDAY, 28TH AUGUST BIHAR ELECTRICITY REGULATORY COMMISSION, PATNA MULTI YEAR TRANSMISSION TARIFF AND SLDC CHARGES REGULATIONS, 2018 _________ NOTIFICATION The 27th August, 2018 23/2018-11—In exercise of powers conferred by sub section (1) of section 181 and clauses (zd), (ze) and(zf) of sub section (2) of section 181, read with sections 32, 61, 62, and 86, of the Electricity Act, 2003 (36 of 2003) and all other powers enabling it in that behalf, the Bihar Electricity Regulatory Commission hereby makes the following Regulations.

PART-I PRELIMINARY Short Title, Commencement and Extent.

These Regulations shall be called the Bihar Electricity Regulatory Commission (Multi Year Transmission Tariff and SLDC Charges) Regulations, 2018.

These Regulations shall come into force from the date of notification in the Official Gazette.

Provided that where a project or a part thereof, has been declared under commercial operation before the date of commencement of these regulations and whose tariff has not been finally determined by the Commission till that date, tariff in respect of such project or such part thereof for the period ending

31.3.2019 shall be determined in accordance with the Bihar Electricity Regulatory Commission (Terms and Conditions for REGISTERED NO. PT.-40 The Bihar GazetteThe Bihar GazetteThe Bihar GazetteThe Bihar Gazette AUGUST 2018 COMMISSION, PATNA AND SLDC CHARGES In exercise of powers conferred by sub sub section (2) of section 181, read with sections 32, 61, 62, and 86, of the Electricity Act, 2003 (36 of 2003) and all other powers enabling it in that behalf, the Bihar Electricity Bihar Electricity Regulatory Commission (Multi Year Transmission Tariff and These Regulations shall come into force from the date of their

Provided that where a project or a part thereof, has been declared under commercial operation before the date of commencement of these regulations and whose tariff has not been on till that date, tariff in respect of such project or such part thereof for the period ending

31.3.2019 shall be determined in accordance with the Bihar Electricity Regulatory Commission (Terms and Conditions for 2 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 determination of Tariff) Regulations, 2007 as amended from time to time.

1.3 These Regulations shall extend to the whole of the state of Bihar.

2. Scope of Application

2.1 These Regulations shall apply to all the Transmission Licensees and SLDC in the State of Bihar

2.2 These Regulations shall be applicable for determination of transmission tariff and SLDC charges in all cases covered under these Regulations from 1st April 2019 and onwards up to FY 2022 (i.e. till 31st March 2022) or till these Regulations are amended.

2.3 These Regulations shall be applicable where the cost based/ Aggregate Revenue Requirement (ARR) based tariff is determined by the Commission.

2.4 These Regulations shall not be applicable whose tariff has been discovered through tariff based competitive bidding in accordance with the guidelines issued by the Central Government and adopted by the Commission under Section 63 of the Act.

3. Definitions

3.1 In these regulations, unless the context otherwise requires;- 1) "Act" means the Electricity Act, 2003 (36 of 2003);

2) “Accounting Statement” means for each Year, the following statements, namely :—

(i) balance sheet, prepared in accordance with BERC (Power Regulatory Accounting) Regulations, 2018, with reference to each licensed or regulated business separately, duly certified by the statutory auditors;

(ii) profit and loss account, prepared in accordance with BERC (Power Regulatory Accounting) Regulations, 2018, with reference to each licensed or regulated business separately, duly certified by the statutory auditors;

(iii) cash flow statement, prepared in accordance with BERC (Power Regulatory Accounting) Regulations, 2018, with reference to each licensed or regulated business separately, duly certified by the statutory auditors;

(iv) balance sheet, prepared in accordance with the form contained in the Companies Act, 1956 or Companies Act, 2013, as applicable;

(v) profit and loss account, complying with the requirements contained in the Companies Act, 1956 or Companies Act, 2013, as applicable;

(vi) cash flow statement, prepared in accordance with the applicable Accounting Standards of the Institute of Chartered Accountants of India;

(vii) report of the statutory auditors ;

(viii) reconciliation statement, duly certified by the statutory auditors, showing the reconciliation between the total expenses, revenue, assets and liabilities, of the entity as a Company and the expenses, revenue, assets and liabilities, separately for each business regulated by the Commission and unregulated business operations ;

(ix) cost records prescribed by the Central Government under the Companies Act,1956 or Companies Act, 2013, as applicable;

3 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 together with notes thereto, and such other supporting statements and information as the Commission may direct :

Provided that separate Accounting Statements shall be prepared and submitted to the Commission for each licensed Business in accordance with the Licence conditions, and for each regulated Business :

Provided further that, in case separate Accounting Statements are not submitted for each licensed Business in accordance with the Licence conditions and for each regulated Business for the Financial Year (FY) 2019-20 onwards, the Petitions filed by the Transmission Licensee or SLDC, as the case may be, may be rejected by the Commission after giving the Petitioner a reasonable opportunity of being heard :

Provided also that the Transmission Licensee or SLDC, as the case may be, shall submit the Statutory Auditor’s comments, observations and notes to Accounts, alongwith the Accounting Statements, and a summary of the key issues highlighted by the Statutory Auditor and the steps taken to address them :

Provided also that, in respect of a Local Authority engaged in the business of distribution of electricity, the Accounting Statement shall mean the items mentioned above as prepared and maintained in accordance with the relevant statutes applicable to such Local Authority:

Provided also that till the SLDC remains a part of Bihar State Power Transmission Company Limited (BSPTCL), separate books of accounts for SLDC shall be maintained by the Bihar State Power Transmission Company Limited and shall be audited and certified by the statutory auditor 3) “Audited accounts or Audited Accounting Statements” for the purpose of licensed or regulated business shall mean (Audited) Regulatory Accounts prepared in accordance with BERC (Power Regulatory Accounting) Regulations, 2018.

4) "Additional Capitalisation" means the capital expenditure actually incurred after the date of commercial operation of the transmission system and admitted by the Commission after prudence check subject to Regulation 19 provided herein after.

5) "Aggregate Revenue Requirement" or "ARR" means the costs pertaining to the licensed business which are permitted, in accordance with these Regulations, to be recovered from the tariffs and charges determined by the Commission;

6) “Allocation Statement” means, for each Year, a statement in respect of each of the Other Businesses of the Transmission Licensee undertaken for optimum utilisation of its assets, showing the amounts of any revenue, cost, asset, liability, reserve or provision, etc., which has been charged from or to each such Other Business together with a description of the basis of that charge ; or determined by apportionment or allocation between different Businesses of the Transmission Licensee, together with a description of the basis of the apportionment or allocation :

7) "Allotted Transmission Capacity" means the power transfer in MW between the specified point(s) of injection and point(s) of drawal allowed to a long-term customer or a medium-term customer on the intra-State transmission system under the normal circumstances and the expression "allotment of transmission capacity" shall be construed accordingly:

4 BIHAR GAZETTE (EXTRA) 17TH JULY 2018

Provided that the Allotted Transmission Capacity to a long-term transmission customer or a medium-term transmission customer shall be sum of the generating capacities allocated to the long-term transmission customer or the medium-term transmission customer from the generating stations and the contracted power, if any;

8) "Auditor" means an auditor appointed by transmission licensee or SLDC as the case may be, in accordance with the provisions of sections 224, 233B and 619 of the Companies Act, 1956 (1of1956), as amended from time to time or Chapter X of the Companies Act, 2013 (18 of 2013) or any other law for the time being in force;

9) "Authority" means Central Electricity Authority constituted under section 70 of the Electricity Act, 2003.

10) "Availability" in relation to a transmission system for a given period means the time in hours during which period the transmission system is capable to transmit electricity at its rated voltage expressed in percentage of total hours in the given period and shall be calculated as provided in Appendix-II to these Regulations.

11) "Base Year" means the financial year immediately preceding first year of the control period and used for the purpose of these Regulations;

12) “Balancing and Settlement Code” means such Code as may be stipulated by the Commission, or by the SLDC with the approval of the Commission, for the balancing of energy accounts and settlement of differences among the users of the grid in the State of Bihar 13) "Beneficiary(ies)"

(a) in relation to a Transmission Licensee, the Transmission System Users.

(b) in relation to the SLDC, the Distribution Licensees and Open Access consumers who utilise the Intra-State Transmission system for transmission of electricity and / or utilise the distribution system of a Licensee in the State for wheeling of electricity and/or avail the services of the SLDC relating to scheduling and real-time grid operations, State energy accounting, operation of pool account, etc.

14) "Books of Accounts" for the purpose of licensed or regulated business shall mean Regulatory Books of Accounts drawn up in accordance with BERC (Power Regulatory Accounting) Regulations, 2018 15) “Bulk Power Transmission Agreement” means an executed Agreement that contains the terms and conditions under which a Transmission System User is entitled to access to an intra-State transmission system of a Transmission Licensee 16) "Change in Law" means occurrence of any of the following events:

(a) enactment, bringing into effect or promulgation of any new Indian law; or

(b) adoption, amendment, modification, repeal or re-enactment of any existing Indian law; or

(c) change in interpretation or application of any Indian law by a competent court, Tribunal or Indian Governmental Instrumentality which is the final authority under law for such interpretation or application; or

(d) change by any competent statutory authority in any condition or covenant of any consent or clearances or approval or licence available or obtained for the project; or 5 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018

(e) coming into force or change in any bilateral or multilateral agreement/treaty between the Government of India and any other Sovereign Government having implication for the generating station or the transmission system regulated under these Regulations.

(f) any change in taxes or duties, or introduction of any taxes or duties levied by the Central or any State Government 17) “Charges” means payments to be collected by the Transmission Licensee or SLDC for the services rendered by it.

18) "Commission" means the Bihar Electricity Regulatory Commission;

19) "Conduct of Business Regulations" means the Bihar Electricity Regulatory Commission (Conduct of Business) Regulations, 2005, and its amendments from time to time.

20) "Contracted Capacity" means the capacity in MW contracted by a longterm Transmission System User as part of its long-term power procurement plan through a power purchase agreement or arrangement, and shall be equivalent to the deemed Transmission Capacity Right of a Transmission System User as specified under the Regulations of the Commission governing Transmission Open Access.

21) "Control Period" means a multi year period normally comprising of three financial years or as may be determined by the Commission, for submission of forecast in accordance with these Regulations;

22) "Cut off date" means 31st March of the year closing after two years of the year of commercial operation of the project, and in case the project is declared under commercial operation in the last quarter of a year, the cut-off date shall be 31st March of the year closing after three years of the year of commercial operation:

Provided that the cut-off date may be extended by the Commission if it is proved on the basis of documentary evidence that the capitalisation could not be made within the cut-off date for reasons beyond the control of the project developer;

23) "Date of Commercial operation" or "COD" in case of a transmission system shall mean the date declared by the Transmission Licensee from 00:00 hour of which an element of the transmission system is in regular service after successful trial operation for transmitting electricity and communication signal from sending end to receiving end. Date of commercial operation in relation to a communication system or element thereof shall mean the date declared by the transmission licensee from 00:00 hour of which a communication system or element is put into service after completion of site acceptance test including transfer of voice and data to respective control centre as certified by the respective State Load Dispatch Centre.

Provided that where the transmission line or substation is dedicated for evacuation of power from a particular generating station, the Generating Company and Transmission Licensee shall endeavour to commission the generating station and the transmission system simultaneously as far as practicable and shall ensure the same through appropriate Implementation Agreement:

Provided further that in case a transmission system or an element thereof is prevented from regular service for reasons not attributable to the Transmission Licensee or its supplier or its contractors but is on account of the delay in commissioning of the concerned generating station or in commissioning of the upstream or downstream 6 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 transmission system, the Transmission Licensee shall approach the Commission through an appropriate application for approval of the date of commercial operation of such transmission system or an element thereof.

24) “De-capitalisation” means the reduction in Gross Fixed Assets corresponding to the removal of assets as approved by the Commission.

25) “Detailed Project Report Scheme” (or “DPR Scheme”) means a capital expenditure Scheme with projected capital cost exceeding the limits specified in these Regulations, for which the Transmission Licensee or SLDC, as the case may be, is required to obtain prior in-principle approval by submitting a Detailed Project Report (DPR) in accordance with the Guidelines of the Commission for In-Principle Clearance of proposed Investment Schemes 26) "Existing Project" means transmission project declared under commercial operation from a date prior to notified date of these tariff regulations by the Commission as per Regulation 1.2.

27) "Expenditure” means reasonable and prudently required expenditure incurred on the following:

a) salaries and wages of staff, welfare expenses excluding management remuneration covered below;

b) Directors remuneration, fees, expenses including facilities;

c) salaries and wages of corporate office / registered office;

d) financing cost excluding penal interest / charges;

e) interest charges on loan(s) borrowed for capitalized assets;

f) interest on temporary accommodation to the extent of approved unrealized arrears from the consumers g) interest on working capital h) Return on equity;

i) financing charges applicable to operational account;

j) interest on security deposits (in cash) from consumers;

k) Impact of variation in foreign exchange rate in case of foreign currency loan taken with due approval and is not capitalised;

l) Depreciation m) Rents, rates and taxes, other than all taxes relating to income / profits;

n) Legal charges;

o) Auditor’s expenses, Auditor’s fees; auditor’s expenses; Payment to Auditors in any other capacity or for any work which is necessary to be got done from them in connection with audit;

p) Consultancy charges for work which cannot be done in house or is uneconomical in doing in-house or is essential to be done from outside sources;

q) Bad debts actually written off subject to Commission’s clearance;

r) Other expenses necessary which are ancillary or incidental to the business of electricity except penalty etc levied under the Act or any other law in force;

28) "Extended Life" means the life of a transmission system or element thereof beyond the period of useful life, as may be determined by the Commission on case to case basis;

29) "Financial Year" means a period commencing on 1st April of a calendar year and ending on 31st March of the subsequent calendar year;

7 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 30) "Force Majeure Event" for the purpose of these regulations means the event or circumstance or combination of events or circumstances including those stated below which partly or fully prevents the transmission licensee to complete the project within the time specified in the Capital Investment Approval, and only if such events or circumstances are not within the control of the transmission licensee and could not have been avoided, had the transmission licensee taken reasonable care or complied with prudent utility practices:

(a) Act of God including lightning, drought, fire and explosion, earthquake, volcanic eruption, landslide, flood, cyclone, typhoon, tornado, geological surprises; or

(b) Any act of war, invasion, armed conflict or act of foreign enemy, blockade, embargo, revolution, riot, insurrection, terrorist or military action; or

(c) Industry wide strikes and labour disturbances having a nationwide impact in India and/or state wide impact in Bihar ;

31) “High Tension” (or “HT”) means all voltages defined as “high” or “extra high” voltage under the applicable Rules and Regulations as specified by the Central Electricity Authority 32) “Income” shall include all income from any sources but shall not be limited to the following:

a) Gross receipts from transmission of energy or SLDC fees & charges, as the case may be, excluding late payment surcharge, if any, based on the orders of the Commission;

b) Rental of meters, plant, equipment and other apparatus hired to the consumers;

c) Income from services to consumers by way of repair or any sale or other service other than capital receipts;

d) Interest on investments, bank balances including fixed and call deposits and any other income in the form of interest;

e) Profit on sale of assets;

f) Wheeling of energy;

g) Non tariff income;

h) Income from other business;

i) Any receipt or refund from other sources against any expense or likely expense which has been earlier allowed as expense in the tariff;

j) All other general receipts arising from and ancillary or incidental to the business of electricity supply;

k) Other general receipts in terms of Act / Regulations including use of assets for other business whether actually recovered or not;

33) “Indian Governmental Instrumentality” means the Government of India, State Government and any Ministry or Department or Board or Agency or regulatory or quasi-judicial authority controlled by Government of India or the Government of the State where the Project is located 34) “Intra-State Transmission System” (or “InSTS”) means any system for conveyance of electricity by transmission lines within the area of the State of Bihar, and includes all transmission lines, sub-stations and associated equipment of Transmission Licensees in the State :

Provided that the definition of point of separation between a transmission system and distribution system and between a Generating Station and transmission system shall be guided by the Regulations 8 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 notified by the Central Electricity Authority under clause (b) of Section 73 of the Act 35) "Implementation Agreement" means the agreement, contract or memorandum of understanding, or any such covenant, entered into (i) between transmission licensee and generating station or (ii) between transmission licensee and developer of the associated transmission system for the execution of project in coordinated manner;

36) "License" means a License granted by the Commission under Section 14 of the Act;

37) "Licensed Business" means the functions and activities, which the Licensee is required to undertake in terms of the License granted by the Commission or as a deemed Licensee under the Act;

38) “Market operation function” means the functions of scheduling, despatch, data acquisition, energy accounting and deviation settlement, transmission loss calculation and apportionment, operation of pool account and congestion charge account, administering ancillary services, information dissemination and any other functions assigned to the SLDC by the Act or Regulations or Orders.

39) “Non-DPR Scheme” means a capital expenditure Scheme with projected capital cost within the limits specified in these Regulations, for which the Transmission Licensee or SLDC, as the case may be, is not required to obtain prior in-principle approval of the Commission.

40) “Non-Tariff Income” means the income relating to the regulated Business other than from Tariff, excluding any income from Other Business.

41) "Operation and Maintenance expenses" or "O&M expenses" means the expenditure incurred on operation and maintenance of the transmission system including part thereof, and includes the expenditure on manpower, repairs, maintenance spares, consumables, insurance and overheads.

42) "Original Project Cost" means the actual expenditure incurred by the transmission licensee, as per the original scope of the project up to the cut-off date as admitted by the Commission;

43) "Project" includes transmission system comprising of specified transmission lines, sub - stations and associated equipment.

44) "Rated Voltage" means the manufacturer’s design voltage at which the transmission system is designed to operate or such lower voltage at which the line is charged, for the time being, in consultation with the long – term transmission customer(s).

45) "State Government" means Government of Bihar.

46) “State Grid Code” means the Code specified by the Commission under clause (h) of sub-section (1) of section 86 of the Act 47) “Transmission Capacity Rights” means the right of a Transmission System User to transfer power in MW, under normal circumstances, between such points of injection and drawal as may be set out in the Bulk Power Transmission Agreement.

48) “Transmission System User” for the purpose of these Regulations means the Distribution Licensees and long-term Open Access Users, but excludes partial Open Access Users 49) "Tariff" means schedule of charges for generation, transmission, distribution and trading of electricity as well as various charges for providing open access of electricity, as determined by the commission from time to time.

9 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 50) "Transformer Failure" represents number of transformer failures of a particular capacity within the transmission system as a percentage of the total number of transformers in that capacity.

51) "Trial Run" or "Trial Operation" Trial operation in relation to a transmission system or an element thereof shall mean successful charging of the transmission system or an element thereof for 24 hours at continuous flow of power, and communication signal from sending end to receiving end and with requisite metering system, telemetry and protection system in service enclosing certificate to that effect from State Load Dispatch Centre.

52) "Transmission Licensee" means a person who has been granted licence for intra state transmission of electricity and includes any person deemed to be a transmission licensee for intra – state transmission of electricity.

53) "Transmission Service Agreement" means an agreement, contract, memorandum of understanding or any such covenant, entered into between the transmission licensee and the long – term transmission customer for the operational phase of the project.

54) "Transmission System" means a line with associated sub stations or a group of lines inter – connected together along with associated sub - stations and the term includes equipment associated with transmission lines and sub-stations.

55) "Useful life" in relation to a unit of a Transmission System from the COD shall mean 25 years for sub-station and 35 years for transmission line.

Provided that the useful life for AC and DC substations and GIS for which Notice Inviting Tender is floated on or after

01.04.2019 shall be considered as 35 years.

3.2 The words and expressions used and not defined in these Regulations, but defined in other Regulations or the Act, shall have the meanings assigned to them in the other Regulations or the Act respectively.

3.3 The words “Application” or “Petition” shall be interpreted synonymously.

PART-II GENERAL PRINCIPLES

4. Multi Year Tariff Framework

4.1 The Commission shall determine the tariff for Transmission business or charges of SLDC operations under a Multi-Year Tariff framework with effect from April 1st of each financial year subject to provisions under these Regulations.

4.2 The Multi Year Tariff frameworks shall be based on the following elements, for calculation of Aggregate Revenue Requirement and expected revenue from tariff and charges for Transmission Business and Fees and Charges of SLDC:

i. Control Period, before commencement of which a forecast of the Aggregate Revenue Requirement and expected revenue from existing tariff in case of transmission licensee or Fees and Charges in case of SLDC, as the case may be, shall be submitted by the applicant and approved by the Commission;

Provided that the performance parameters whose trajectories have been specified in these Regulations shall form the basis of projection for the Aggregate Revenue Requirement for the entire Control Period:

ii. A detailed Business Plan based on the Operational Norms and trajectories of performance parameters specified in the MYT Regulations, for each year of the Control Period, shall be 10 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 submitted by the applicant for the Commission's approval subject to provisions under these Regulations;

iii. Based on the Business Plan, the applicant shall submit a petition with the forecast of Aggregate Revenue Requirement and expected revenue from existing tariff and charges for each year of the Control Period, and the Commission shall approve the transmission tariff and Fees and Charges in case of SLDC for each year of the Control Period;

iv. The mechanism for pass-through of approved gains or losses on account of uncontrollable factors as specified under Regulation 9 of these Regulations;

v. The mechanism for sharing of approved gains or losses arising out of controllable factors as specified under Regulation 10 of these Regulations;

5. Business Plan

5.1 The Transmission Licensee or SLDC, as the case may be, shall file a Business Plan, for the Control Period by a Petition in accordance with BERC (Conduct of Business) Regulations, 2005 and its amendments from time to time, by 15th September of the year prior to the commencement of the Control Period and accompanied by such fee payable, as specified in the BERC (Fees, Fines and Charges) Regulations, 2005 as amended from time to time.

Provided that where no separate fee has been specified for filling of a business plan, the applicant shall pay fees as may be determined by the Commission.

5.2 Such Business Plan shall comprise but not be limited to infrastructure requirement commensurate with load growth forecast and demand projections, capital investment plan, financing plan and physical targets.

Provided that the Business Plan shall take into account schemes costing below the threshold limit to be notified separately that are to be developed by the State Transmission Utility on cost plus basis in accordance with the Tariff Policy notified by Govt.

of India.

Provided further that the Commission may permit SLDC to create and maintain a separate development fund for such purposes and from such sources of income, as the Commission may consider appropriate, on a Petition filed by SLDC.

Provided also that in case the Commission issues guidelines and formats, from time to time, the same shall be adhered to by the Transmission Licensee.

5.3 (a) The Transmission Licensee or SLDC, as the case may be, shall make assessment of infrastructure requirement and prepare capital investment plan in accordance with BERC (Procedure for Filing Capital Investment and Capitalization Plan) Regulations, 2018 that will spill into the year(s) under review and new projects that will commence and may be completed within or beyond the tariff period.

Provided that all the new intra-state transmission projects costing above a threshold limit to be notified separately, shall be developed through Tariff Based Competitive Bidding.

11 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018

(b) The Commission shall approve the infrastructure requirement and preparation of capital investment plan in accordance with BERC (Procedure for Filing Capital Investment and Capitalization Plan) Regulations, 2018. The same would be considered for computation of ARR, wherein the amount of electricity transmitted by the Transmission System shall be projected considering the estimated growth plan of its Beneficiaries and any plans of new transmission system, based on network expansion plans within the State.

(c) The Commission may also undertake a detailed review of the actual works compared with the works approved in the previous Tariff Order while approving the capital expenditure for the ensuing year.

(d) Capital expenditure shall be incurred by the Licensee after the approval of the Business Plan Order. In case the capital expenditure is required for emergency work, the Licensee may take up the work upto Rs.20 Crore prior to receiving the approval from the Commission provided the emergent nature of the scheme has been certified by its Board of Directors.

(e) The Licensee shall submit an application within 15 days of occurrence of cause for such emergent work, containing all relevant information along with reasons justifying the emergent nature of the proposed work, seeking post facto approval by the Commission.

(f) Beneficiaries contribution towards cost of capital asset shall be treated as capital receipt and credited in current liabilities until transferred to a separate account on Commissioning of the assets.

(g) An amount equivalent to the depreciation charge on such assets for the year shall be appropriated from this account as income to the statement of profit and loss over the useful life of the asset.

6. Specific trajectory for certain variables

6.1 The Commission shall stipulate a trajectory while approving the Business Plan, for certain variables having regard to the reorganization, restructuring and development of the electricity industry in the State:

Provided that the variables for which a trajectory may be stipulated shall include, but are not limited to, Capitalization Schedule (Timely completion of Project as per original award without cost overrun and Time overrun), Operation & Maintenance expense norms, transmission system availability, and transmission losses.

6.2 In case the Commission has approved the business plan by 31st October of current year, the trajectory stipulated by the Commission in the order approving the Business Plan submitted by the applicant, shall be incorporated by the applicant, in its forecast of Aggregate Revenue Requirement and/or expected revenue from tariff and charges under these Regulations.

7. Annual Review of Performance and True-up

7.1 Where the Aggregate Revenue Requirement and expected revenue from tariff and charges of a Transmission Licensee or SLDC, as the case may be, are covered under a Multi-Year Tariff framework, 12 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 such Transmission Licensee or SLDC shall be subject to an annual review of performance and True-up during the Control Period in accordance with these Regulations.

8. Controllable and uncontrollable factors:

8.1 The “uncontrollable factors” shall comprise but not limited to the following factors which are beyond the control of, and could not be mitigated by the applicant:

(a) Force Majeure events, such act of God, war, fire and natural calamities, etc.

(b) Change in law;

(c) Taxes and Duties;

(d) Variations in interest rates for long-term loan

8.2 The “controllable factors” shall comprise but not limited to the following factors which are within the control of, and are attributable to the applicant:

(a) Variations in Transmission System availability;

(b) Variations in capital expenditure and Capitalization on account of time and/or cost overruns/ efficiencies in the implementation of a capital expenditure project not attributable to an approved change in scope of such project, change in statutory levies or force majeure events;

(c) Variation in Interest and Finance Charges, Return on Equity, and Depreciation on account of variation in capitalisation as specified in clause (b) above ;

(d) Variations in transformation and transmission losses;

(e) Variation in performance parameters;

(f) Variations in Return on Equity (RoE), depreciation and working capital requirements. However, if the Commission is satisfied that the variation in the working capital requirement is attributable to any uncontrollable factors, the same may be considered as uncontrollable factor.

(g) Variation in operation & maintenance expenses, except those attributable to directions of the Commission or to change in Government policy/law.

(h) Failure to meet the standards specified in the Standards of Performance Regulations, except where exempted;

9. Mechanism for pass-through of gains or losses on account of uncontrollable factors

9.1 The approved aggregate gain or loss to the Licensee or SLDC, as the case may be, on account of uncontrollable factors shall be a pass through, as an adjustment in the tariff of the Licensee or SLDC, as the case may be, as specified in these Regulations and as may be determined in the Order of the Commission passed under these Regulations..

9.2 The Licensee or SLDC, as the case may be, shall submit such details of the variations between actual and the figures approved by the Commission along with the detailed computations and supporting documents as may be required by the Commission.

10. Mechanism for sharing of gains or losses on account of controllable factors

10.1 The approved aggregate gain or loss to the Licensee or SLDC, as the case may be, on account of controllable factors shall be dealt 13 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 with separately for aggregate gain and aggregate loss in the following manner:

(a) Aggregate gain:

(i) Two-third of the amount of such gain shall be a pass through as an adjustment in the tariff of the Licensee or SLDC, as the case may be,, as specified in these Regulations and as may be determined in the Order of the Commission passed under these Regulations;

(ii) The balance one-third of the amount of such gain shall be on account of Licensee or SLDC, as the case may be, and such amount shall be utilized at the discretion of Licensee or SLDC, as the case may be.

(b) Aggregate Loss:

(i) One-third of the amount of such loss shall normally be a pass through as an adjustment in the tariff of the Licensee or SLDC, as the case may be, as specified in these Regulations and as may be determined in the Order of the Commission passed under these Regulations, provided the Commission is satisfied that such loss is not on account of deliberate action of the Licensee or SLDC, as the case may be;

(ii) The balance two-third of the amount of such loss shall be on account of Licensee or SLDC and shall be absorbed by the Licensee or SLDC, as the case may be.

Explanation:- If the State Government is providing resource gap grant, Aggregate Loss shall be reduced by that amount for the purpose of computation of Aggregate Loss to be qualified for a pass through.

10.2 The Licensee and SLDC, as the case may be, shall submit such details of variation for sharing of approved aggregate gain or loss on account of controllable factors along with the detailed computations and supporting documents as may be required for verification by the Commission.

PART-III PROCEDURE

11. Procedures relating to making of an application for approval of Business plan and for determination of Tariff

11.1 An application (alongwith soft copy) for approval of the Business Plan shall be made by 15th September of the year prior to the commencement of the Control Period, in accordance with the BERC (Conduct of Business) Regulations, 2005 and its amendments from time to time, and accompanied by such fee payable, as specified in the BERC (Fees, Fines and Charges) Regulations, 2005 as amended from time to time.

Provided that where no separate fee has been specified for filing of a Business Plan, the applicant shall pay fees as may be determined by the Commission.

Provided also that the Commission may conduct a Technical Validation Session prior to admission of the Petition

11.2 The Transmission Licensee in its Business Plan filings shall submit and propose the trajectory for the achievement of quality targets. The Commission shall specify the targets for each parameter. The Transmission Licensee shall submit its performance on each parameter in the form and manner specified by the Commission.

14 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 The Business Plan shall be for the entire control period and shall interalia, contain:

(a) Capital Investment Plan

(b) The appropriate capital structure and cost of financing (interest on debt) and return on equity, terms of the existing loan agreements, etc;

(c) Operation and Maintenance (O&M) expenses: This shall include the costs estimated for the Base Year, the actual expenses incurred in the previous control period and the projected values for each year of the Control Period based on the proposed norms for O&M cost, including indexation and other appropriate mechanisms;

(d) Depreciation: Based on the original cost of the fixed assets of the corresponding year, capitalisation schedules for each year of the Control Period and at the rate not exceeding the rate specified by the Central Electricity Regulatory Commission;

(e) Performance Targets: A set of targets proposed for controllable items such as availability of transmission system, transmission losses, transformer failure rate, and any other parameters for quality of supply. The targets shall be consistent with the Capital Investment Plan proposed by the Transmission Licensee;

(f) Proposals for Non-Tariff Income with item-wise description and details;

(g) Proposals in respect of income from Other Business;

(h) Other Information: This shall include any other details considered appropriate by the Transmission Licensee for consideration during determination of tariff; and

11.3 An application (alongwith soft copy) for determination of tariff and charges shall be made by 15th November every year, for Truing up of expenses of previous years, for Annual Performance Review (APR) of the Aggregate Revenue Requirement (ARR) for the current year and determination of ARR and transmission tariff or SLDC charges for the ensuing years of the control period. The application should contain the data relating to each item of the ARR supported with the information/data in the formats Form no- SI to Form no-P12 appended to these Regulations, and accompanied by such fees as may be specified under the BERC (Fees, Fines and Charges) Regulations, 2005 as amended from time to time. All the information as required in the formats appended to these Regulations along with justification shall be provided in the main petition.

Provided that the Commission may require submission of additional information/data required for determination of ARR and tariff.

11.4 The filings for Transmission Tariff shall inter-alia contain but are not limited to the following:

(a) The Transmission System or network usage forecast for each year of the Control Period, consistent with the Business Plan;

(b) Proposals for transmission tariff design for each year of the Control Period, including the losses to be charged and the procedure thereof;

(c) Proposal for reactive energy charges;

15 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018

(d) Expected Revenue from the Licensed Business, Non-Tariff Income and income from Other Business and other matters considered appropriate by the Transmission Licensee.

11.5 The petition for determination of tariff or SLDC charges shall be accompanied by information for the previous year, current year (RE) and the ensuing years of the entire control period.

Provided that the application shall be accompanied where relevant, by a detailed tariff revision proposal and how such revision would meet the gap, if any, in Aggregate Revenue Requirement for each year of the Control Period.

Provided further that the information for the previous year shall be based on audited accounts and in case audited accounts for previous year are not available, audited accounts for the immediately preceding year should be filed along with provisional books of annual (regulatory) accounts for the previous year adopted by the Board of Directors of the licensee company or SLDC, as the case may be.

11.6 The Transmission Licensee or SLDC as the case may be shall along with the aforesaid petition submit a statement on the status of compliance of directives, if any, issued by the Commission in its last tariff order.

11.7 The Commission may seek clarification and additional information on inadequacies in the application, if any, within 14 days or as may be practicable, of filing of the application for approval of the Business Plan and application for determination of tariff, as the case may be.

11.8 The Transmission Licensee shall respond within the next 10 days to the Commission with all clarification and information as required.

11.9 Upon receipt of a complete application accompanied by all requisite information, particulars and documents in compliance with all the requirements specified in these Regulations, the application for approval of the Business Plan and application for determination of tariff, as the case may be, shall be deemed to be received and The Commission shall admit the application for approval of the Business Plan and application for determination of tariff, as the case may be, within seven days or as may be required, of submission of response to the clarifications, if any, by the Transmission Licensee or SLDC, as the case may be.

11.10 The Commission or the Secretary or the designated Officer shall intimate to the applicant with the abridged form of application for publication of public notice in the daily newspapers. In case of non-submission or delay in submission of additional information, the Commission may take suo-motu decision to formulate this abridged form of application as it deem appropriate.

11.11 The applicant shall, within three (3) days of the intimation given to him in accordance with Regulation 11.10, publish a notice inviting suggestions and objections from the public, in at least two (2) English and two (2) Hindi language daily newspapers widely circulated in the area to which the application pertains, outlining the proposed Business Plan or the proposed ARR and tariff, as the case may be, and such other matters as may be stipulated by the Commission.

16 BIHAR GAZETTE (EXTRA) 17TH JULY 2018

Provided that the applicant shall make available a hard copy of the complete application, to any interested party, at such locations and at such rates as may be stipulated by the Commission:

Provided further that the applicant shall also put up on its internet website, in downloadable spreadsheet format showing detailed computations, the application made to the Commission along with all regulatory filings, information, particulars and documents in the manner so stipulated by the Commission:

Provided further that the web-link to the information mentioned in the second proviso above shall be easily accessible, archived for downloading and shall be prominently displayed on the applicant's internet website:

Provided also that the applicant may not provide or put up any such information, particulars or documents, which are confidential in nature, with the prior approval of the Commission.

Explanation– for the purpose of this Regulation, the term “downloadable spreadsheet format” shall mean one (or multiple, linked) spreadsheet software files containing all assumptions, formulae, calculations, software macros and outputs forming the basis of the application.

11.12 The procedural aspects pertaining to the Petition contained in this Regulation shall apply only to such an extent as may be required by the Commission having regard to the circumstances of an individual case, to,-

(a) a Petition filed by a Transmission Licensee under Section 36 of the Act;

(b) a Petition filed by the SLDC under section 32 of the Act

11.13 Notwithstanding anything contained in these Regulations, in case of delay/ non-submission of the application for approval of the Business Plan and application for determination of tariff, as the case may be, the Commission may initiate suo-motu proceedings mandating the filing of the said applications.

Provided that in the event of the licensee not filing the application despite the aforesaid proceeding, the Commission may on its own, decide the tariff based on previous year’s tariff details and after incorporating suitable adjustments. However before issuing tariff order under such circumstances, comments/ suggestions/ objections from the public and stake holders including the licensee will be invited and same will be considered for the tariff order.

Provided further that the Commission may also pass directions under Section 129 and/or Section 142 of the Act, if required.

12. Order approving the Business Plan and Tariff Order

12.1 An Order approving with such modifications or such conditions as may be specified in that order or rejecting the Business Plan shall, as far as practicable, be issued before the filing of tariff petition separately or with the tariff order as the Commission may deem fit and practicable.

12.2 The Commission shall, within one hundred and twenty (120) days from receipt of a complete application for determination of ARR and tariff and after considering all suggestions and objections 17 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 received from the public and after hearing all stakeholders and general public:-

(a) issue a Tariff Order accepting the application with such modifications or such conditions as may be specified in that Order;

(b) reject the application for reasons to be recorded in writing, if such application is not in accordance with the provisions of the Act and the Rules and Regulations made there under or the provisions of any other law for the time being in force:

12.3 An applicant shall be given a reasonable opportunity of being heard before rejecting its application referred to under regulation

12.1 and 12.2 above.

12.4 The applicant shall publish the tariff approved by the Commission within seven days of issue of tariff order in at least two (2) English and two (2) Hindi daily newspapers having wide circulation in the area of supply of the applicant and shall put up the approved tariff or charges on its internet website.

12.5 The tariff so published shall be in force from the date specified in the said Order and shall, unless amended or revised, continue to be in force for such period as may be stipulated therein.

13. True-Up and Annual Performance Review The Commission shall True-Up expenses of the previous year either as part of the Tariff order or issue Order/s for True-Up of expenses preceding the Tariff order of ensuing year.

(a) An order for True-Up of expenses shall be issued on annual basis.

(b) An order for True-Up of expenses shall be on the basis of expense estimates made in the beginning of the year under consideration, actual expenses booked in the audited books of accounts of the Transmission Licensee or SLDC, as the case may be, for the year, and after prudence check of data by the Commission.

(c) Where audited books of account are not available at the time of true-up, provisional books of annual (regulatory) accounts duly approved by the Board of Directors of the applicant company shall be used for the provisional True-up process.

(d) The Commission shall undertake review of estimates of expenses for the current year as a part of the tariff order on the basis of the actual expenses incurred during the period April – September of the current year and corresponding figures in the order for Annual Revenue Requirement (ARR) of the current year approved by the Commission.

(e) Estimates of expenses for the ensuing year shall be on the basis of corresponding figures in the order for True-up of expenses of the previous year and Annual Performance Review or Tariff Order of the current year, as the Commission may consider reasonable and deem fit.

(f) Notwithstanding anything contained in regulation 4 of these Regulations, the Revenue gap/surplus arising out of Truing up shall be considered by the Commission while determining the ARR of ensuing year(s).While approving adjustments towards revenue/expenses in future years, arising out of Truing up exercises, the Commission may allow the carrying costs as 18 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 determined by the Commission of such expenses/revenues.

However the revised estimated gap/surplus as a result of APR may or may not be passed in the ARR of ensuing year.

14. Adherence to Tariff Order

14.1 If a Transmission Licensee recovers a price or charge exceeding the tariff determined under Section 62 of the Act and in accordance with these Regulations, the excess amount shall be payable to the person who has paid such price or charge, along with interest equivalent to the Bank Rate of the Reserve Bank of India without prejudice to any other liability that may be incurred by such Transmission Licensee.

14.2 The Transmission Licensee shall submit periodic returns as may be required by the Commission, containing operational and cost data to enable the Commission to monitor the implementation of its Order.

PART-IV NORMS OF OPERATION

15. Charges for Auxiliary Energy Consumption in the Sub – Station The charges for auxiliary energy consumption in the Sub Stations for the purpose of air – conditioning, lighting, technical consumption etc shall be borne by the transmission licensee as part of normative operation and maintenance expenses.

Provided that for consumption in the Sub Stations for the purpose of air–conditioning, lighting, technical consumption etc., transmission licensee shall get an electric connection from the concerned distribution licensee and pay charges to the distribution licensee as per the applicable retail tariff.

16. Normative Annual Transmission System Availability Factor (NATAF):

16.1 The Normative Annual Transmission System Availability Factor for recovery of full transmission charges shall be as under:

(a) For full recovery of Annual Transmission Charges-

(i) AC System 98%

(ii) HVDC System 95%

(b) For Incentive consideration-

(iii) AC System 99%

(iv) HVDC System 96%

Provided that recovery of full annual transmission charges below the target availability shall be on a pro rata basis. At zero availability, no transmission charges shall be payable

16.2 The actual availability shall be calculated in accordance with the procedure provided in Appendix-II to these Regulations and shall be certified by the State Load Despatch Centre (SLDC) as per the format specified in Appendix I of these Regulations.

16.3 The Transmission Licensee shall be entitled to incentive on achieving annual availability beyond the target availability, in accordance with the following formula :- Incentive = Annual Transmission Charges x (Annual availability achieved – Target Availability) / Target Availability;

Where, 19 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Annual transmission Charges shall correspond to Aggregate Revenue Requirement for each year of the Control Period for the particular Transmission Licensee within the State:

Provided that no incentive shall be payable above the availability of 99.75 % for AC system and 98.5 % for HVDC system:

17. Quality of Supply

17.1 The Commission shall monitor the following Quality of Supply parameters during the Control Period:

(a) Transmission System Availability

(b) Transformer Failure,

18. Safety Standards

18.1 The Transmission Licensee shall develop a Safety Manual and follow procedures to maintain at least minimum safety standards during construction, operation, etc. in line with the provisions of Section 53 of the Act

19. Additional Capitalisation:

(1) The following capital expenditure which is within the original scope of work and actually incurred after the date of commercial operation and upto the cut-off date may be admitted by the Commission, subject to prudence check:

(i) deferred liabilities

(ii) works deferred for execution

(iii) Initial spares shall be capitalised as a percentage of the Plant and Machinery cost upto cut-off date, subject to following ceiling norms:

a) Transmission line - 1.00% b) Transmission Sub-station (Green Field) - 4.00% c) Transmission Sub-station (Brown Field) - 6.00% d) Series Compensation devices and HVDC Station - 4.00% e) Gas Insulated Sub-station (GIS) - 5.00% f) Communication system- 3.50%

Provided that once the project is commissioned, the cost of initial spares shall be restricted on the basis of plant and machinery cost corresponding to the project at the time of truing up.

(iv) liabilities in connection with implementation of award of arbitration or compliance of the order or decree of a court, and

(v) on account of change in law Note: (a) original scope of work along with estimates of expenditure shall be submitted to the Commission along with application for provisional tariff.

(b) a list of the deferred liabilities and works deferred for execution shall be submitted along with the application for determination of final tariff after the date of commercial operation of the transmission system.

(2) Subject to clause (3) of this regulation, the capital expenditure of the following nature actually incurred after the cut-off date may be admitted by the Commission, subject to prudent check.

(i) deferred liabilities relating to work / services within the original scope of work

(ii) liabilities in connection with implementation of award of arbitration or compliance of an order or decree of a court

(iii) on account of a change in law, and

(iv) any additional works / services which have become necessary for efficient and successful operation of the project, but not included in the original project cost.

20 BIHAR GAZETTE (EXTRA) 17TH JULY 2018

(3) Any expenditure incurred on minor items / assets bought after the cut off date like tools and tackles, personal computers, furniture, airconditioners, voltage stabilizers, refrigerators, coolers, fans, TV, washing machine, heat convectors, mattresses, carpets etc. shall not be considered for additional capitalisation for determination of tariff with effect from notified date of the tariff regulations by the Commission as per Regulation 1.2 The list of items is illustrative but not exhaustive.

Note:

(1) Any expenditure admitted on account of committed liabilities within the original scope of work and the expenditure deferred on technoeconomic grounds but falling within the original scope of work shall be serviced in the normative debt equity ratio specified in these Regulations.

(2) Any expenditure on replacement of old asset shall be considered after writing off the entire value of the original asset from the original capital cost.

(3) Any expenditure admitted by the Commission for determination of tariff on account of new works not in the original scope of work shall be serviced on normative debt – equity ratio specified in these Regulations.

(4) Any expenditure admitted by the Commission for determination of tariff on renovation and modernisation or life extension shall be serviced on normative debt –equity ratio specified in these Regulations after writing off the original amount of the replaced asset from the original capital cost.

PART-V FINANCIAL PRINCIPLES

20. ARR for Transmission Business

20.1 Financial Prudence- The Transmission Licensee or SLDC, as the case may be, shall manage its finances in an optimum and prudent manner

Provided that the Commission may disallow a part of the Aggregate Revenue Requirement, as an efficiency measure, if it finds the exercise of such prudence to have been deficient

Provided also that, in case its payment obligations to other entities are not regularly met, the Transmission Licensee or SLDC, as the case may be, shall provide justification for such shortfall with reference to its cash flow statement.

20.2 The financial prudence with respect to capital expenditure shall be assessed in terms of the following parameters:—

(a) mechanism put in place for monitoring the physical progress of projects with respect to their original schedule;

(b) optimum drawal of loans in accordance with the physical progress of the capital expenditure schemes, and efficient utilisation of such loans;

(c ) in case the actual capital expenditure or capitalisation exceeds 10% of that approved by the Commission, the Transmission Licensee or SLDC, as the case may be, shall submit detailed justification for such excess along with its Petition for True-up ;

(d) in case any scheme has not been commenced during the year despite the Commission’s approval, detailed justification shall be submitted along with the Petition for True-up.

21 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018

20.3 The Aggregate Revenue Requirement for the Transmission Licensee or SLDC business, as the case may be, for each year of the Control Period shall contain but not limited to the following items:

(a) Operation and Maintenance expenses;

(b) Return on Equity;

(c) Depreciation

(d) Interest and finance charges on loan capital

(e) Interest on working capital

(f) Contingency Reserve;

(g) Bad debts, if any

(h) Non-Tariff Income

(i) Income from Other Business.

(j) Revenue from short-term transmission charges

21. Operation and Maintenance Expenses

(a) The Commission shall stipulate a separate trajectory of norms for each of the components of O&M expenses viz., Employee cost, Repair and Maintenance (R&M) expense and Administrative and General (A&G) expense.

Provided that such norms may be specified for a specific Transmission Licensee or a class of Transmission Licensees.

(b) Norms shall be defined in terms of number of personnel per ckt/km (for different categories of transmission lines for e.g.

400 KV, 220 KV, 132 KV etc. Lines) and number of personal per bay (for different categories of bay for e.g. 400 KV, 220 KV, 132 KV etc. Bays) along with annual expenses per personnel for Employee expenses; combination of A&G expense per personnel and A&G expense per substation for A&G expenses and R&M expense as percentage of gross fixed assets for estimation of R&M expenses.

(c) One-time expenses such as expense due to change in accounting policy and arrears paid due to pay commission recommendation shall be excluded from the norms in the trajectory.

(d) The unforeseen expenses beyond the control of the Transmission Licensee such as pay revision, shall be excluded from the norms in the trajectory.

(e) The One-time expenses and the expenses beyond the control of the Transmission Licensee shall be allowed by the Commission over and above normative Operation & Maintenance Expenses after prudence check.

(f) The norms in the trajectory shall be specified over the control period with due consideration to productivity improvements.

(g) The norms shall be determined at constant prices of base year and escalation on account of inflation shall be over and above the baseline.

(h) The Transmission Licensee specific trajectory of norms shall be identified by the Commission on the basis of absolute and relative analysis.

(i) In absolute analysis, Transmission Licensee’s audited accounts of operations for last three years, expenses claimed for control period, historically approved cost, and prudence check shall be used by the Commission to estimate values of norms.

22 BIHAR GAZETTE (EXTRA) 17TH JULY 2018

(j) In relative analysis, performance parameters of other Transmission Licensees within the same state or in other states, shall be considered by the Commission to estimate norms.

Provided that other Transmission Licensees so chosen shall have similar profile as that of the Transmission Licensee under consideration in terms of consumer mix, type of license area (city, state, etc.) type of substation, transmission networks, etc.

(k) Suitable average of outcomes of absolute and relative analysis shall be taken by the Commission to fix the norms over the control period for the Transmission Licensee.

21.1 Employee Cost Employee cost shall be computed as per the approved norm escalated by consumer price index (CPI), adjusted by provisions for expenses beyond the control of the Transmission Licensee and one time expected expenses, such as recovery/adjustment of terminal benefits, implications of pay commission, arrears and Interim Relief, governed by the following formula:

EMPn = (EMPb * CPI inflation) + Provision Where:

EMPn : Employee expense for the year n EMPb : Employee expense as per the norm CPI inflation : is the average increase in the Consumer Price Index (CPI) for immediately preceding three years Provision : Provision for expenses beyond control of the Transmission Licensee and expected one-time expenses as specified above.

Till the norms are specified by the Commission the employee cost shall be determined on the basis of actual historical cost.

21.2 Repairs and Maintenance (R&M) Expense Repairs and Maintenance expense shall be calculated as percentage (as per the norm determined) of Opening Gross Fixed Assets excluding land cost for the year governed by following formula:

R&Mn = Kb * GFAn Where:

R&Mn : Repairs & Maintenance expense for nth year GFAn : Opening Gross Fixed Assets for nth year Kb : Percentage point as per the norm

21.3 Administrative and General (A&G) Expense A&G expense shall be computed as per the norm escalated by wholesale price index (WPI) and Consumer Price Index (CPI) in the ratio 60:40 and adjusted by provisions for confirmed initiatives (IT etc. initiatives as proposed by the Transmission Licensee and validated by the Commission) or other expected one-time expenses, and shall be governed by following formula:

A&Gn = (A&Gb * WPI inflation) + Provision Where:

A&Gn: A&G expense for the year n A&Gb: A&G expense as per the norm WPI inflation: is the average increase in the Wholesale Price Index (WPI) for immediately preceding three years Provision: Cost for initiatives or other one-time expenses as proposed by the Transmission Licensee and validated by the Commission. Till the norms of A&G expenses is specified by the Commission, the actual historical cost will be considered for determination of A&G expenses.

23 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018

22. Return on Equity

(a) Return on equity shall be computed on 30% of the capital cost or actual equity, whichever is lower:

Provided that assets funded by beneficiary contribution, capital subsidies/ grants and corresponding depreciation shall not form part of the capital cost. Actual equity invested in the Transmission Licensee or SLDC, as the case may be, as per book value shall be considered as perpetual and shall be used for computation in this Regulation:

Provided further that the premium if any raised by the Licensee while issuing share capital and investment of internal resources created out of its free reserves, for the funding of the Scheme, shall be reckoned as paid up capital for the purpose of computing return on equity, provided such premium amount and internal resources are actually utilized for meeting the capital expenditure of the distribution system, and are within the ceiling of 30% of capital cost approved by the Commission.

(b) The return on the equity invested shall be allowed from the date of start of commercial operation and after put to use:

(c) Return on equity shall be computed at the rate of 15.5% for the project which is commissioned w.e.f. 01.04.2015 and further incentive equivalent to 0.5% will be allowed in the form of RoE, if the project is completed within schedule as per the Annexure A or original schedule period as the case may be. However, Return on Equity for the project commissioned prior to 01.04.2015 shall be allowed at the rate of 14%.

23. Depreciation

(i) Depreciation shall be calculated for each year of the control period on the original cost of the fixed assets of the corresponding year.

No advance shall be granted against depreciation.

(ii) Depreciation shall not be allowed on assets funded by capital subsidies, beneficiary contributions or grants.

(iii) Depreciation shall be calculated annually on the basis of assets capitalised and put to use based on the straight line method over the useful life of the asset and at the rate not exceeding the rate specified by the Central Electricity Regulatory Commission from time to time as provided in Appendix-III of these Regulations.

The residual value of assets shall be considered as 10% and depreciation shall be allowed to a maximum of 90% of the original cost of the asset. The Transmission Licensee or SLDC, as the case may be, shall submit separate detail of fully depreciated asset along with year of commissioning and year of attaining ninety percent depreciation with the tariff petition.

Provided that freehold land shall not be treated as a depreciable asset and its cost shall be excluded while computing 90% of the original cost of the asset.

Provided further that the cost of lease hold land shall be amortised evenly within the leased period.

(iv) The original capital cost of the asset shall include Additional Capitalisation on account of Foreign Exchange Rate Variation as allowed by the Government / Bihar Electricity Regulatory Commission.

(v) Depreciation shall be chargeable from the first year of operation of the asset. For part of the year, depreciation shall be charged on pro rata basis.

24 BIHAR GAZETTE (EXTRA) 17TH JULY 2018

(vi) A provision of replacement of assets shall be made in the capital investment plan.

24. Interest and finance charges on loan capital

(a) The Transmission Licensee or SLDC, as the case may be, shall provide detailed loan-wise, project wise and utilization-wise details of all the loans.

(b) If the equity actually deployed is more than 30 % of the capital cost, equity in excess of 30 % shall be treated as normative loan:

Provided that where equity actually deployed is less than 30% of the capital cost, the actual loan shall be considered for determination of interest on loan:

(c) Actual loan or normative loan, if any, shall be referred as gross normative loan in this Regulation.

(d) The normative loan outstanding as of 1st April of control period shall be computed by deducting the cumulative repayment as approved by the Commission (basis as mentioned below) up to 31st March of current period (a year before control period) from the gross normative loan.

(e) The repayment for the control period shall be deemed to be equal to the depreciation allowed for the year.

(f) Notwithstanding any moratorium period availed by the Transmission Licensee or SLDC, as the case may be, the repayment of the loan shall be considered from the first year of the control period as per annual depreciation allowed.

(g) The rate of interest shall be the weighted average rate of interest calculated on the basis of actual loan portfolio at the beginning of each year of the control period, in accordance with terms and conditions of relevant loan agreements, or bonds or nonconvertible debentures:

Provided that if no actual loan is outstanding but normative loan is still outstanding, the last available weighted average rate of interest shall be applicable.

Provided further that if no actual loan is outstanding but normative loan is still outstanding and the last available weighted average rate of interest is also not available, rate of interest equal to the State Bank one-year Marginal Cost of Funds-based Lending Rate (‘MCLR’) shall be applicable.

Provided further that the interest on loan shall be calculated on the normative average loan of the year by applying the weighted average rate of interest:

Provided also that exception shall be made for the existing loans which may have different terms as per the agreements already executed if the Commission is satisfied that the loan has been contracted for and applied to identifiable and approved projects:

(h) The Transmission Licensee or SLDC, as the case may be, shall make every effort to refinance the loan as long as it results in net benefit to the beneficiaries.

Provided that the cost associated with such refinancing shall be eligible to be passed through in tariffs and the benefit on account of refinancing of loan and interest on loan shall be shared in the ratio of 50:50 between the Transmission Licensee or SLDC and the beneficiaries.

25 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018

Provided further that the Transmission Licensee shall submit the calculation of such benefit to the Commission for its approval.

(i) The Transmission Licensee shall enable tracking of the loans converted into grants under schemes like BRGF, PSDF, APDRP, R- APDRP, RGGVY, DDUGVY, RSVP, etc or any other loan from the Central or State Government by providing information and data regularly to the Commission, for enabling the Commission to recover from Transmission Licensee or SLDC, as the case may be, the amount of interest on loans which have been passed on to the beneficiaries in the earlier years and have been converted into grant subsequently so that the recovered amount is passed on to the beneficiaries.

(j) Addition to loan during the year for interest purpose will be restricted to the quantum of assets capitalized and put to use.

(k) The excess interest during construction on account of time and/or cost overrun as compared to the approved completion schedule and capital cost or on account of excess drawal of the debt funds disproportionate to the actual requirement based on Scheme completion status, shall be allowed or disallowed partly or fully on a case to case basis, after prudence check by the Commission. The transmission licensee shall endeavour to adhere the time schedule for various transmission system in accordance with Annexure-A appended for these regulations.

Provided that where the excess interest during construction is on account of delay attributable to an agency or contractor or supplier engaged by the Transmission Licensee, any liquidated damages recovered from such agency or contractor or supplier shall be taken into account for computation of capital cost:

Provided further that the extent of liquidated damages to be considered shall depend on the amount of excess interest during construction that has been allowed by the Commission.

(l) The above interest computation shall exclude interest on loan amount, normative or otherwise, to the extent of capital cost funded by Consumer Contribution, Deposit Works, Grants or Capital Subsidy.

25. Interest during Construction (IDC), Incidental Expenditure during Construction (IEDC):

(A) Interest during Construction (IDC)

(i) Interest during construction shall be computed corresponding to the loan from the date of infusion of debt fund, and after taking into account the prudent phasing of funds upto Scheduled Date of Commercial operation (SCOD).

(ii) In case of additional costs on account of IDC due to delay in achieving the SCOD, the SLDC or the transmission licensee as the case may be, shall be required to furnish detailed justifications with supporting documents for such delay including prudent phasing of funds.

Provided that if the delay is not attributable to the SLDC or the transmission licensee as the case may be, and is due to uncontrollable factors as specified in Regulation 8 of these regulations, IDC may be allowed after due prudence check.

26 BIHAR GAZETTE (EXTRA) 17TH JULY 2018

Provided further that only IDC on actual loan may be allowed beyond the SCOD to the extent, the delay is found beyond the control of SLDC or the transmission licensee, as the case may be, after due prudence and taking into account prudent phasing of funds.

(B) Incidental Expenditure during Construction (IEDC)

(i) Incidental expenditure during construction shall be computed from the zero date and after taking into account pre-operative expenses up to Scheduled Date of Commercial operation (SCOD).

Provided that any revenue earned during construction period up to SCOD on account of interest on deposits or advances, or any other receipts may be taken into account for reduction in incidental expenditure during construction.

(ii) In case of additional costs on account of IEDC due to delay in achieving the SCOD, the transmission licensee or SLDC as the case may be, shall be required to furnish detailed justification with supporting documents for such delay including the details of incidental expenditure during the period of delay and liquidated damages recovered or recoverable corresponding to the delay.

Provided that if the delay is not attributable to the transmission licensee or SLDC as the case may be, and is due to uncontrollable factors as specified in Regulation 8, IEDC may be allowed after due prudence check.

Provided further that where the delay is attributable to an agency or contactor or supplier engaged by the transmission licensee or SLDC, the liquidated damages recovered from such agency or contractor supplier shall be taken into account for computation of capital cost.

(iii) In case the time over-run beyond SCOD is not admissible after due prudence, the increase of capital cost on account of cost variation corresponding to the period of time over run may be excluded from capitalization irrespective of price variation provisions in the contracts with supplier or contractor of the transmission licensee or SLDC.

26. Interest on working capital

(a) The Transmission Licensee shall be allowed interest on the estimated level of working capital for the financial year, computed as follows:

(i) Receivables equivalent to two (2) month of transmission charges calculated on target availability level.

(ii) O&M Expenses of one (01) month.

(iii) Maintenance spares @ 15% of O&M expenses for one month.

Less:

(iv) Depreciation, return on equity and contribution to contingency reserves equivalent to two months.

(v) Amount of security deposits from Transmission System users, if any, held during the year except the security deposits held in the form of Bank Guarantee from Transmission System Users.

(b) Interest on working capital shall be on normative basis and rate of interest shall be equal to the State Bank one-year Marginal Cost of Funds-based Lending Rate (‘MCLR’) as of the date on which petition for determination of tariff is filed plus 150 basis points.

The rate of interest for the purpose of Truing-up shall be the 27 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 weighted average MCLR of the concern Financial Year plus 150 basis points.

(c) Interest shall be allowed on the amount held as security deposit from Transmission System Users at the Bank Rate as at the date on which the application for determination of tariff is filed. The interest allowed shall be subject to true up at weighted average Bank Rate of the concern Financial Year.

(d) If the State Government is providing resource gap grant and/or subsidy, the working capital shall be reduced by two months equivalent of that amount.

27. Tax on Return on Equity 1) The base rate of return on equity as allowed by the Commission under Regulation 22 shall be grossed up with the effective tax rate of the respective financial year. For this purpose, the effective tax rate shall be considered on the basis of actual tax paid in the respect of the financial year in line with the provisions of the relevant Finance Acts by the concerned the transmission licensee or SLDC, as the case may be. The actual tax on income from other business including deferred tax liability (i.e. income on business other than business of transmission or SLDC, as the case may be) shall not be considered for the calculation of effective tax rate.

2) Rate of return on equity shall be rounded off to two decimal places and shall be computed as per the formula given below:

Rate of pre-tax return on equity = Base rate / (1-t) Where “t” is the effective tax rate in accordance with Clause

(1) of this regulation and shall be calculated at the beginning of every financial year based on the estimated profit and tax to be paid estimated in line with the provisions of the relevant Finance Act applicable for that financial year to the company on pro-rata basis by excluding the income of non-generation or nontransmission business, as the case may be, and the corresponding tax thereon. In case of licensee/SLDC paying Minimum Alternate Tax (MAT), “t” shall be considered as MAT rate including surcharge and cess.

Illustration:-

(i) In case of the licensee paying Minimum Alternate Tax (MAT) @

20.96% including surcharge and cess:

Rate of return on equity = 15.50/(1-0.2096) = 19.61%

(ii) In case of licensee paying normal corporate tax including surcharge and cess:

(a) Estimated Gross Income from the licensee business for FY 2017-18 is Rs 1000 crore.

(b) Estimated Advance Tax for the year on above is Rs 240 crore.

(c) Effective Tax Rate for the year 2017-18 = Rs 240 Crore/Rs 1000 Crore = 24%

(d) Rate of return on equity = 15.50/ (1-0.24) = 20.39%

(3) The Licensee or SLDC, as the case may be, shall true up the grossed up rate of return on equity at the end of every financial year based on actual tax paid together with any additional tax demand including interest thereon, duly adjusted for any refund of tax including interest received from the income tax authorities pertaining to the tariff period 2019-20 to 2021-22 on actual gross income of any financial year. However, penalty, if any, arising on account of delay in deposit or short deposit of tax amount shall not be claimed by the 28 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Licensee or SLDC as the case may be. Any under-recovery or over-recovery of grossed up rate on return on equity after truing up, shall be recovered or refunded to beneficiaries on year to year basis.

28. Contribution to Contingency Reserve

(a) If the Transmission Licensee or SLDC, as the case may be, has made an appropriation to the Contingency Reserve, a sum not less than 0.25 per cent and not more than 0.5 per cent of the original cost of fixed assets shall be allowed annually towards such appropriation in the calculation of ARR.

Provided that where the amount of such Contingency Reserves exceeds five (5) per cent of the original cost of fixed assets, no further contribution shall be allowed.

Provided further that such contribution shall be invested in securities authorised under the Indian Trusts Act, 1882 within a period of six months of the close of the Year.

(b) The Contingency Reserve shall not be drawn upon during the term of the license except to meet such charges as may be approved by the Commission, such as following:

(i) Expenses or loss of profits arising out of accidents, strikes or circumstances which the management could not have prevented;

(ii) Expenses on replacement or removal of plant or works other than expenses required for normal maintenance or renewal;

(iii) Compensation payable under any law for the time being in force and for which no other provision is made:

Provided that such drawal from contingency reserve shall be computed after making due adjustment for any other compensation that may have been received by the Licensee as part of an insurance cover:

(c) No diminution in the value of contingency reserve as mentioned above shall be allowed to be adjusted as a part of tariff.

29. Bad and Doubtful Debts :

Bad and Doubtful Debts shall be allowed as a legitimate business expense provided the transmission licensee actually identifies and writes off bad debts as per the transparent policy approved by the Commission.

In case there is any recovery of bad debts already written off, the recovered bad debt will be treated as other income.

30. Delayed Payment Charge and Interest on Delayed Payment:

In case the payment of bills of transmission charges or SLDC Fees and Charges by the Beneficiary, as the case may be, is delayed beyond a period of 60 days from the date of billing, Delayed Payment Charge at the rate of 1.25% per month on the billed amount shall be levied for the period of delay by the Transmission Licensee or SLDC, as the case may be, notwithstanding anything to the contrary as may have been stipulated in the Agreement or Arrangement with the Beneficiaries

31. Non-Tariff Income

(i) All incomes being incidental to electricity business and derived by the Licensee from sources, including but not limited to profit derived from disposal of assets, rents, delayed payment surcharge, income from investments other than contingency reserves, miscellaneous receipts from the Beneficiaries, income to Licensed business from the Other Business of the Transmission Licensee or SLDC, as the case may be, shall constitute Non-Tariff Income of the Licensee.

29 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018

Provided that the interest earned from investments made out of Return on Equity corresponding to the regulated Business shall not be included in Non-Tariff Income.

(ii) The amount received by the Licensee on account of Non-Tariff Income shall be deducted from the Aggregate Revenue Requirement in calculating the net revenue requirement of such Licensee.

32. Income from Other Business Where the Transmission Licensee is engaged in any other business under Section 41, the income from such business will be deducted from the Aggregate Revenue Requirement in calculating the revenue requirement of the Licensee in the manner and in proportion as may be specified by the Commission in BERC (Treatment of Income of Other Businesses of Transmission Licensees and Distribution Licensees) Regulations, 2013 and its amendments from time to time.

Provided that the Licensee shall follow a reasonable basis for allocation of all joint and common costs between the Transmission Business and the Other Business and shall submit the Allocation Statement as approved by the Board of Directors to the Commission along with the application for determination of tariff;

Provided further that where the sum total of the direct and indirect costs of such Other Business exceed the revenues from such Other Business or for any other reason, no amount shall be allowed to be added to the Aggregate Revenue Requirement of the Transmission Licensee on account of such Other Business.

33. Annual Transmission Charges (ATC)

33.1 The annual Transmission charges of the transmission system shall be computed on annual basis, in accordance with norms contained in these regulations, aggregated as appropriate, and recovered on monthly basis as transmission charge from the users.

33.2 The Transmission charge (inclusive of incentive/29disincentive) for AC system payable for a calendar month shall be:

ARR X (NDM/NDY) x (TAFM/NATAF) Where;

NATAF= 98% NDM = Number of days in the month NDY = Number of days in the year TAFM = Transmission System availability factor for the month, in percent computed in accordance with Appendix-II.

34. Sharing of charges for Intra-State Transmission Network

34.1 The Aggregate Revenue Requirement of the Transmission Licensee, as approved by the Commission, shall be shared by all long-term users and medium-term users of the transmission system on monthly basis in the ratio of their respective contracted transmission capacities to the total contracted transmission capacity, in accordance with the following formula:

TCn= (Transmission ARR net of incentive/disincentive) x (NDM/NDY) x CCn/SCC Where, TCn = transmission charges for the month payable by the nth long-term user or medium-term user of the transmission system;

30 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Transmission ARR = Aggregate Revenue Requirement of the Transmission Licensee, determined in accordance with Regulation 16 of these Regulations;

CCn = capacity contracted in MW by the nth long-term user or mediumterm user of the transmission system during the month;

SCC = sum of capacities contracted in MW by all long-term users and medium-term users of the transmission system during the month:

NDM= Number of days in the month NDY= Number of days in the year

Provided that the TCn shall be payable on monthly basis by each long-term user or medium-term user of the transmission system and shall be collected by the State Transmission Utility (STU).

35. Sharing of SLDC Charges

35.1 The SLDC Charges payable by the Transmission System Users shall be computed in accordance with the following formula:- SLDC Charges payable for a month SCn =(SC/12)*(ACn/SAC) Where, SCn= SLDC charge payable by Transmission System user SC= Approved SLDC Aggregate Revenue Requirement for the year ACn= Actual installed capacity of nth Transmission System user in case of generating stations/long term and medium term contracted capacities in case of sellers/aggregated allocated capacity and contracted capacity in case of distribution licensee/long term contracted capacity in case of buyer.

SAC= Sum of actual installed capacity of Transmission System users in case of generating stations (within Bihar), long term and medium term contracted capacities in case of sellers, aggregated allocated capacity and contracted capacity in case of distribution licensee and long term contracted capacity in case of buyer.”

35.2 The SLDC Charges approved for the Year shall be equally spread over the 12 months of the Year and SLDC Charges per MW per month shall be computed by SLDC accordingly.

35.3 Notwithstanding anything contained in these regulations, the Commission after conducting study and due regulatory process may notify the revised sharing and recovery of annual transmission charges of the transmission licensee.

36. Short-term bilateral transactions and short-term collective transactions

36.1 For short-term bilateral transactions and short-term collective transactions through power exchanges, the transmission tariff shall be denominated in Rs/kWh and shall be:

Tc= ARR/Ei Where Ei=total energy input into the intra-State transmission system during the financial year.

36.2 The revenue from short-term open access charges for each yearly period (t) of Control Period shall be taken to be same as that prevalent during the yearly period one year before the commencement of the Control Period. However, the adjustments due to variation in actual revenue from short-term open access charges shall be undertaken during annual truing up.

37. Separation of Transmission and SLDC functions

37.1 The Transmission Licensee shall separate its business into transmission and SLDC functions, and segregate its accounts 31 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 between these two businesses, once the accounts of these two businesses are segregated SLDC shall file a separate application for determination of its fee and charges in accordance with these regulations.

Till the segregation of the accounts is completed, the Transmission Licensee shall submit an Allocation Statement that contains the apportionment of costs and revenues to that business. The Allocation Statement, approved by the Board of Directors of the Licensee, shall be accompanied with an explanation of the methodology for apportionment which should be consistent over the Control Period.

37.2 SLDC charges shall be payable by various utilities as may be determined by the Commission in accordance with these Regulations.

Provided that the RLDC Fees and Charges payable by the SLDC in accordance with the relevant Orders issued by the Central Electricity Regulatory Commission from time to time shall be allowed to be recovered by the SLDC through the Fees and Charges as approved by the Commission.

Provided further that, the ERPC Charges payable to the ERPC’s Secretariat shall be allowed to be recovered by the SLDC through the Fees and Charges as approved by the Commission.

37.3 The SLDC shall have to produce documentary proof towards payment of such Charges at the time of Truing up.

Provided that any variation between the approved RLDC Fees and Charges and ERPC Charges and that actually paid by the SLDC shall be considered during the true-up as per audited accounts, subject to prudence check and any other factor considered appropriate by the Commission.

38. Incentive/Disincentive

38.1 The Transmission Licensee shall be entitled to incentive/disincentive on account of deviation from target availability as well as transmission Loss target set by commission.

However, the incentive/disincentive on account of deviation from transmission loss target shall be +/- 0.01% of ARR for deviation of

0.01% of transmission loss limited to +/- 2% of the ARR.

The transmission charges referred to in Regulation 33 of these Regulations are inclusive of such incentives and disincentives on account of availability of system.

38.2 Incentive shall be shared by the long-term and medium term customers in the ratio of their respective contracted transmission capacities to the total contracted transmission capacity.

39. Rebate

(1) For payment of bills of the transmission licensee through letter of credit on presentation or through NEFT/RTGS within a period of 2 days of presentation of bills by the transmission licensee, a rebate of 2% shall be allowed.

(2) Where payments are made on any day after 2 days and within a period of 30 days of presentation of bills by the transmission licensee, a rebate of 1% shall be allowed.

40. Late Payment Surcharge In case the payment of any bills for charges payable under these Regulations is delayed by a beneficiary(ies) beyond a period of 60 days 32 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 from the date of billing a late payment surcharge at the rate of 1.25% per month on billed amount shall be levied for the period of delay by the Transmission Licensee.

PART-VI MISCELLANEOUS

41. Power to amend The Commission may, at anytime, amend, alter or modify any provision of these Regulations.

42. Power to remove difficulties If any difficulty arises in giving effect to the provisions of these Regulations, the Commission may, by general or specific order, make such provisions not inconsistent with the provisions of the Act, as may appear to be necessary for removing the difficulty.

43. Right to vary terms and conditions The terms and conditions for determination of tariff specified in these regulations are in the nature of general framework on the basis of which the tariff shall be determined. The Commission reserves its right to vary these terms and conditions, as and when deems fit.

44. Limitation of Power of Commission Nothing in these regulations shall be deemed to limit the powers of the Commission to deal with any matter or exercise any power under the relevant Acts for which no regulations have been made / framed and to make such orders as it may consider appropriate to meet the ends of justice in any case.

45. Repeal and savings

(a) Save as otherwise provided in these regulations, regulations 66 to 78 under Chapter-4 and Appendix-C under same chapter of the BERC (Terms and Conditions for Determination of Tariff) Regulations, 2007 and BERC (Levy and Collection of fees and charges by SLDC) Regulation 2006 and its amendments from time to time are hereby repealed.

(b) The other part of BERC (Terms and Conditions for Determination of Tariff) Regulations, 2007 and its amendments shall remain applicable and where a difference is found in the Regulation relating to MYT of transmission licensee the provision of these Regulations shall prevail.

(c) Notwithstanding such repeal, any proceedings before the Commission pertaining to the period prior to the commencement of the Control Period, including Petitions for True up of exercises, annual performance review, etc. shall be governed by BERC (Terms and Conditions for Determination of Tariff) Regulations, 2007 and its amendments from time to time.

By order of the Commission, (Sd) Illegible, Secretary.

33 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Appendix-I (See Reg. 16.2) FORMAT FOR ISSUANCE OF AVAILABILITY CERTIFICATE BY SLDC On the letterhead of SLDC Ref:

To .......... Date: ..........

Sub: Transmission System Availability Certificate for......................... (Name of Transmission Licensee) for the month…… Ref: ...

With reference to the above, SLDC has received the computation of transmission system availability with interruption details of Transmission network for the month__________, computed in accordance with the BERC (Multi Year Transmission Tariff) Regulations,2018.

The overall Transmission System Availability of the Transmission network for the month _________, computed in accordance with Appendix-II of the BERC (MYT) Regulations, 2018, and after considering the provisions of BERC (MYT) Regulations, 2018, is ________________ %.

Authorised Signatory Copy to ___________ 34 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Appendix-II (See Reg. 16.2)

1. Transmission system availability factor for a calendar month (TAFM) shall be calculated by the respective Transmission Licensee certified by the SLDC, separately for each AC and HVDC transmission system and grouped according to sharing of transmission charges.

2. NAFM for A.C. and HVDC system / sub-systems shall be calculated as follows:

% TAFM for AC system o X AVo + p X AVp + q X AVq + r X AVr = ----------------------------------------------------------X 100 o + p + q + r % TAFM for HVDC system s X AVs + t X AVt = ----------------------------------X 100 S + t Where o = Total number of AC lines.

AVo = Availability of o number of AC lines.

p = Total number of bus reactors/switchable line reactors AVp = Availability of p number of bus reactors/switchable line reactors q = Total number of ICTs.

AVq = Availability of q number of ICTs.

r = Total number of SVCs.

AVr = Availability of r number of SVCs.

s = Total number of HVDC poles AVs = Availability of s number of HVDC poles t = Total number of HVDC back-to-back station blocks AVt = Availability of t number of HVDC back-to-back station blocks The weightage factor for each category of transmission elements shall be as under:

(a) For each circuit of AC line – Surge Impedance Loading for Uncompensated line (SIL) multiplied by ckt-km. As specified in Annexure-B.

However, for the voltage levels and/or conductor configurations not listed in Annexure-B, appropriate SIL based on technical considerations may be used for availability calculation under intimation to long-term transmission customers.

For compensated AC line, Surge Impedance Loading (SIL) shall be as certified by the SLDC considering the compensation on the line.

For shunt compensated line the reduced value of SIL shall be taken in accordance with the location of the reactor. Similarly in case of the lines with series compensation the higher SIL shall be taken as per the percentage of compensation.

(b) For each HVDC pole- The rated MW capacity x ckt-km.

(c) For each ICT bank – The rated MVA capacity.

(d) For SVC- The rated MVAR capacity (inductive and capacitive).

(e) For Bus Reactor/switchable line reactors – The rated MVAR capacity.

35 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018

(f) For HVDC back-to-back station connecting two Regional grids/Intra State Sub-Stations- Rated MW capacity of each block.

The availability for each category of transmission elements shall be calculated based on the weightage factor, total hours under consideration and non-available hours for each element of that category.

FORMULAE FOR CALCULATION OF AVAILABILITY OF EACH CATEGORY OF TRANSMISSION ELEMENTS AVo(Availability of o no. of AC lines)= ∑ �������� � ����� ∑ ����� � AVs(Availability of s no. of HVDC pole)= ∑ �������� � �� ∑ ����� ���� AVq(Availability of q no. of ICTs)= ∑ �������� � ����� ∑ ����� � AVr(Availability of r no. of SVCs)= ∑ 0.5������� − � !�� ���"#� + ∑ 0.5 �%���%� − !&� �%�"#� ∑ 0.5���"�� + ∑ 0.5 �%�"�� � AVp(Availability of p no. of Switched Bus Reactor)= ∑ �'��' − � !'

�'()� ∑ �'()� � AVt (Availability of t no. of HVDC Back-to back Blocks= ∑ �*��* − � !* �*+,� ∑ �*+,� � Where Wi = Weightage factor for ithtransmission line Wj = Weightage factor for jth HVDC pole Wk = Weightage factor for kth ICT WIl&WCl = Weightage factors for inductive & capacitive operation of lth SVC Wm = Weightage factor for mth bus reactor Wn = Weightage factor for nth HVDC back to back block Ti, Tj, Tk, TIl, TCl, - The total hours of ith AC line,jth HVDC pole, kth ICT, lth SVC Tm&Tn (Inductive Operation), lth SVC (Capacitive Operation),mth Switched Bus Reactor &nth HVDC back-to-back block during the period under consideration (excluding time period for outages not attributable to transmission licensee .

TNAi ,TNAj , TNAk - The non-availability hours (excluding the time period for outages not attributable to transmission licensee taken as deemed availability) for ith AC line, jth HVDC 36 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 pole, KthICT, lth SVC (Inductive Operartion), ith SVC (Capacitive Operation), mth Switched Bus Reactor and nth HVDC back-to-back block.

TNAIl, TNACl, TNAm, TNAn Note :- "Factors have been applied in the above formula of NAFM such that a 315 MVA transformer would have the same weightage as a 200 km long D/C line with twin conductors, and a 50 MVAR switched reactor would have one-fourth the weightage of a 315 MVA transformer. The transmission lines shall have a weightage proportional to their circuit – km and number of sub-conductors (to which the current carrying capacity is directly proportional). Voltage has been omitted by design for the present, to deliberately enhance the weightage for 220 kV and 132 kV lines (as they are critical for supply to beneficiaries), and to suppress the weightage for 765 kV lines (since they presently carry power much below their capability). The Commission may review and modify the formula when the situation changes in future".

4. The transmission elements under outage due to following reasons shall be deemed to be available:

i. Shut down availed for maintenance or construction of elements of another transmission scheme. If the other transmission scheme belongs to the Transmission Licensee, SLDC may restrict the deemed availability period to that considered reasonable for the work involved.

ii. Switching off of a transmission Iine to restrict over voltage and manual tripping of switched reactors as per the directions of SLDC.

5. Outage time of transmission elements for the following contingencies shall be excluded from the total time of the element under period of consideration.

i. Outage of elements due to acts of God and force majeure events beyond the control of the Transmission Licensee. However, onus of satisfying the SLDC that element outage was due to aforesaid events and not due to design failure shall rest with the Transmission Licensee. A reasonable restoration time for the element shall be considered by SLDC and any additional time taken by the Transmission Licensee for restoration of the element beyond the reasonable time shall be treated as outage time attributable to the Transmission Licensee. SLDC may consult the Transmission Licensee or any expert for estimation of reasonable restoration time. Circuits restored through ERS (Emergency Restoration System) shall be considered as available.

ii Outage caused by grid incident/disturbance not attributable to the Transmission Licensee, e.g. faults in substation or bays owned by other agency causing outage of the transmission licensee's elements, and tripping of lines, ICTs, HVDC, etc. due to grid disturbance. However, if the element is not restored on receipt of direction from SLDC while normalizing the system following grid incident/disturbance within reasonable time, the element shall be considered not available for the period of outage after issuance of SLDC's direction for restoration.

6. The format for issuance of Availability Certificate by SLDC is given in Appendix-I.

37 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Appendix – III (See Reg. 23) DEPRECIATION SCHEDULE Description of Assets

(1) Depreciation Rate(Straight line method)

(2) A. Land owned under full title: - B. Land held under lease:

(a) for investment in the land 3.34%

(b) for cost of clearing the site 3.34%

(c) Land for reservoir in case of Hydro Generating Station

3.34% C. Assets Purchased New:

(a) Building and civil engineering works of permanent character

(i) Offices and showrooms 3.34%

(ii) Containing thermo-electric generating plant 3.34%

(iii) Containing hydro-electric generating plant 3.34%

(iv) Temporary erection such as wooden structures 100%

(v) Roads other than kutcha roads 3.34%

(vi) Others 3.34%

(b) Transformers, transformer (Kiosk) sub-Station equipment and other fixed apparatus (including foundations):

(i) Transformers (including foundations) having a rating of 100 kilo volt amperes and over

5.28%

(ii) Others 5.28%

(c) Switchgear including cable connections

5.28%

(d) Lightning arrestors 5.28%

(i) Station type 5.28%

(ii) Pole type 5.28%

(iii) Synchronous condensor 5.28%

(e) Batteries 5.28% i Underground Cable including joint boxes and disconnected boxes

5.28% 38 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Description of Assets

(1) Depreciation Rate(Straight line method)

(2) ii Cable duct system 5.28%

(f) Overhead lines including supports 5.28%

(g) Meters 5.28%

(h) Self propelled vehicles 9.50%

(i) Air conditioning plants

(i) Static 5.28%

(ii) Portable 9.50%

(j)

(i) Office furniture and fittings 6.33%

(ii) Office equipments 6.33%

(iii) Internal wiring including fittings and apparatus

6.33% Street light fittings 6.33%

(k) Apparatus let on hire

(i) Other than motors 9.50%

(ii) Motors 6.33%

(l) Communication equipment

(i) Radio and high frequency carrier system

6.33%

(ii) Telephone lines and telephones 6.33%

(iii) Fibre Optic 6.33%

(m) I.T. equipments 15.00%

(n) Software 30.00%

(o) Any other assets not covered above 5.28% 39 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Annexure – A (See Regulation 24) Time schedule for completion of various transmission system Sl.

No.

Transmission Work Plain Area (months) Difficult Hilly Terrain / Forest Area (months) a 765 kV S/C Transmission line 36 42 b +/-500 KV HVDC Transmission line 30 36 c 400 KV D/C Quad Transmission line 38 44 d 400 KV D/C Triple Transmission line 36 42 e 400 KV D/C Twin Transmission line 34 40 f 400 KV S/C Twin Transmission line 30 36 g 220KV D/C Twin Transmission line 34 40 h 220 KV D/C Transmission line 30 36 i 220 KV S/C Transmission line 26 32 j 132 KV D/C Transmission line 20 26 k 132 KV S/C Transmission line 16 22 l 132 KV/33 KV AC Sub-Station 12 15 m New 220 KV AC Sub-Station 24 27 n New 400 KV AC Sub-Station 30 33 o New 765 kV AC Sub-Station 36 40 p HVDC bi-pole terminal 42 44 q HVDC back-to-back 32 34 40 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Annexure – B (see Appendix-II) SURGE IMPEDANCE LOADING (SIL) OF AC LINES Sr. No. Line voltage(kV) Conductor Configuration SIL (MW)

1. 765 Quad Bersimis 2250

2. 400 Quad Bersimis 691

3. 400 Twin Moose 515

4. 400 Twin AAAC 425

5. 400 Quad Zebra 647

6. 400 Quad AAAC 646

7. 400 Triple Snowbird 605

8. 400 ACKC(500/26) 556

9. 400 Twin ACAR 557

10. 220 Twin Zebra 175

11. 220 Single Zebra 132

12. 132 Single Panther 50

13. 66 Single Dog 10 41 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 INDEX OF FORMATS S1 TO P12 FOR ARR & TARIFF FILING BY TRANSMISSION LICENSEES AND THE SAME SHALL BE USED BY SLDC Summary Formats 1 S1 Profit & Loss Account 2 S2 Balance Sheet 3 S3 Cash flow statement Financial Formats 4 F1 Annual Revenue Requirement 5 F2 Allotted Transmission Capacity and Charges to be paid by Long Term Transmission Customers 6 F3 Projection of Sales, Connected Load and Demand 7 F4 Revenue at current tariff rates and at proposed tariff rates 8 F5 Details of Transmission Lines and Substations including Investment plan 9 F6 Normative Parameters Considered for Tariff Computations 10 F7 Gross Fixed Assets(GFA) and Depreciation 11 F8 User contributions and grants towards cost of capital assets 12 F9 Details of Loans 13 F10 Details of Equity 14 F11 Interest, IDC & Financing Charges 15 F12 Details of Lease 16 F13 Operations & Maintenance Cost 17 F14 Employee expenses 18 F15 R&M Expenses 19 F16 Administrative & General Expenses 20 F17 Short Term Open access consumers 21 F18 Details of Non-tariff Income 22 F19 Working Capital Interest 23 F20 Details of Income from Other Business 24 F21 Details of Expenses Capitalised 42 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 25 F22 Net Prior Period Expenses/Income & Extraordinary Items 26 F23 Contribution to Contingency Reserve, details of grant 27 F24 Allocation Statement of Expenses of SLDC Performance Formats 28 P1 Transmission Losses (For Transmission Licensee) 29 P2 Energy Delivered by Transmission licensee to the Distribution Licensees/ Bulk consumers at interface points 30 P3 Details of Electrical Accidents 31 P4 Abstract of Outages due to feeder tripping 32 P5 Major System Disturbances 33 P6 Frequency Variation 34 P7 Voltage Fluctuation 35 P8 Licensee wise Load shedding carried out during the year 36 P9 Details of Overloaded Feeders 37 P10 Details of over loaded Transformers 38 P11 Failure of Transformers 39 P12 Key Ratios 43 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Statement of Projected Profit and Loss Form No: S1 Rs Crores Particulars Current Year (i. e. RE) Ensuing years (Projection) FY (n+1) FY (n+2) FY (n+3) A Revenue/Income 1 Revenue from operations a)Revenue from Transmission/Wheeling charges -NBPDCL -SBPDCL -Others (Pl, specify) 2 Non-tariff income 3 Revenues through subsidies & grants (If any) 4 Any other Income Total Revenue* B Expenditure 1 Repair and Maintenance Cost 2 Employee costs 3 Administration expenses 4 Other Expenses 5 Extraordinary items (specify items) Less: Expenses Capitalized C Depreciation and Related debits D Interest & Finance Charges Less: Interest Capitalized G TOTAL EXPENDITURE (B+C+D)* H Profit/Loss (A-G) * Pertaining to Transmission Business Only, SLDC shall file separately Signature of Petitioner 44 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Projected Balance Sheet Form No: S2 Rs Crores Particulars Current Year (i. e. RE) Ensuing years (Projection) FY (n+1) FY (n+2) FY (n+3) Assets Non-current assets ------- ------- ------- Current assets ------- ------- ------- Total Assets EQUITY AND LIABILITIES Equity ------- ------- ------- LIABILITIES ------- ------- Total Equity and Liabilities Signature of Petitioner 45 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Projected Cash Flow Statement Form No: S3 Rs Crores Particulars Current Year (i. e. RE) Ensuing years (Projection) FY (n+1) FY (n+2) FY (n+3) A Cash flows from operating activities i Net (loss) / Profit Adjustments For ii ---------- iii ---------- iv ---------- B Net Cash flows from operating activities Cash Flow from Investing Activities i ---------- ii ---------- iii ---------- C Net Cash used in Investing Activities Cash Flow from Financing Activities i ---------- ii ---------- iii ---------- Net Cash generated from Financing Activities D Total Cash generated/(lost) E Cash & Cash Equivalents as at beginning of the Financial Year F Cash & Cash Equivalents as at end of the Financial Year Signature of Petitioner 46 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Annual Revenue Requirement Form No: F1 (Rs. Crores) Particulars Previous Year Curren t Year (i. e.

RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) I. Energy Available (MU) 78700 II. Energy Transmitted/Wheeled (MU) 75812 III. Loss % 3.67% IV. Transmission Cost per unit (Rs/U) #REF!

V Total Transmission System Capacity (in MW) VI. Transmission Cost per MW VII .

Max Demand handled by the transmission system (in MW) A. Income from Transmission Function 1 Receipts a Transmission/Wheeling Charges at current tariff rates b Subsidy from Govt. (If any) Total Receipts ( A) B Expenditure 1 O&M Expenses i Employee Expenses ii R&M Expense iii A&G Expense iv. Share of Holding Company 47 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Expenses Total O&M expenses ( i+ii+iii+iv) 0 0 0 0 0 2 Return on Equity 3 Depreciation 4 Interest and finance charges on Loan Capital Less: IDC, if any 5 Interest on Working Capital 6 Contribution towards Contingency Reserve 7 Bad Debts Total Expenditure ( B) C Other Deductions 1 Income from other Business 2 Non tariff income 3 Revenue from Short Term transmission charges Total Other Deductions ( C) D Net ARR for Transmission Function ( B-C) E Shortfall/Excess before tariff revision impact (A-D) F Tariff Revision Impact G Shortfall/Excess after tariff revision impact (E-F) Note: The ARR of SLDC shall be filed separately by SLDC. Expenses will be net of Expenditure capitalized.

Signature of Petitioner 48 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Form No: F2 Allotted Transmission Capacity and Charges to be paid by Long Term Transmission Customers Allotted Transmission Capacity of Long Term Transmission Customers ( CL) (In MW) Particulars Previous Year Current Year (i. e. RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) A Distribution Licensees 1 North Bihar Power Distribution Company Limited 2 South Bihar Power Distribution Company Limited 3 Others i.

ii.

B Bulk Consumers/Long Term Open Access Customers (If any) 1 2 Sum of Total Alloted Transmission Capacity to all the long term Transmission system customers (SCL) Charges to be paid by Long Term Transmission Customers/month Rs. Crore A Distribution Licensees 1 North Bihar Power Distribution Company Limited #REF!

2 South Bihar Power Distribution Company Limited #REF!

3 Others #REF!

i.

ii.

B Bulk Consumers/Long Term Open Access Consumers (If any) 1 2 Total 49 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Projection of Sales, Connected Load and Demand Form No: F3 A) Projection of sales (MU) Particulars Previous Year Curre nt Year (i. e.

RE) Ensuing years (Projection) Approve d in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) A Distribution Licensees 1 North Bihar Power Distribution Company Limited 2 South Bihar Power Distribution Company Limited 3 Others `------- B Bulk Consumers/Long Term Open Access Consumers (If any) 1 2 TOTAL - - - - - - B) Projection of Connected Load (in KW) A Distribution Licensees 1 North Bihar Power Distribution Company Limited 2 South Bihar Power Distribution Company Limited 3 Others `----- B Bulk Consumers/Long Term Open Access Consumers (If any) 1 TOTAL - - - - - - C) Projection of Maximum or Peak Demand (in MW) (Unrestricted) A Distribution Licensees 1 North Bihar Power Distribution Company Limited 2 South Bihar Power Distribution Company Limited 3 Others `-- B Bulk Consumers/Long Term Open Access Consumers (If any) 1 2 TOTAL - - - - - - 50 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 D) Projection of Minimum Demand (in MW) A Distribution Licensees 1 North Bihar Power Distribution Company Limited 2 South Bihar Power Distribution Company Limited 3 Others `--- B Bulk Consumers/Long Term Open Access Consumers (If any) 1 2 TOTAL - - - - - - E) Projection of Average Demand (in MW) A Distribution Licensees 1 North Bihar Power Distribution Company Limited 2 South Bihar Power Distribution Company Limited 3 Others `-- B Bulk Consumers/Long Term Open Access Consumers (If any) 1 2 TOTAL - - - - - - Signature of Petitioner 51 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Revenue Form No: F4 At Current Tariff Rates Rs. Crores Particulars Previous Year Current Year (i. e.

RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) A Distribution Licensees 1 North Bihar Power Distribution Company Limited 2 South Bihar Power Distribution Company Limited 3 Others i.

ii.

TOTAL - - - - - - B Bulk Consumers/Long Term Open Access Consumers (If any) 1 2 TOTAL - - - - - - Grand Total - - - - - - At Proposed Tariff Rates Ensuing years (Projection) FY (n+1) FY (n+2) FY (n+3) A Distribution Licensees 1 North Bihar Power Distribution Company Limited South Bihar Power Distribution Company Limited 3 Others i.

ii.

TOTAL B Bulk Consumers/Long Term Open Access Consumers (If any) 1 2 TOTAL Grand Total Less Tariff at Current Rates - Impact of Tariff Revision 52 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee

(a) Details of Transmission Lines and Substations Form No: F5 Transmission Lines No Name of line Type of line AC/ HVDC S/C or D/C No. of Subconductors Voltage level kV Line length Ckt.-Km.

Date of Commercial operation /Put in use 1 2 - -

(b) Substations No Name of Substation Type of Substation Convention al / GIS Voltag e level kV No. of transform ers / Reactors/ SVC etc (with capacity) No. of Bays Date of Commer cial operatio n /Put in use Covered in this petition (Yes/No) 1 2 - *Note:- Information to be provided for Previous Year, Current Year & Ensuing Control Period

(c) Details of Installed Transformer at Substation Sl.No Voltage Ratio of Transformer (kV/kV) Details of Transformers Total number Total Capacity (MVA) 1 400/220 2 400/132 3 220/132 4 220/33 132/33 Note: Information required for Previous years, current year and Ensuing years 53 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Form No: F5

(d) Investment Plan (Scheme-wise) (Rs. in Cr.)

N a m e o f s c h e m e / P ro je c t N a m e o f lin e / S u b -s ta ti o n e tc Approved Outlay Progressiv e upto the beginning of previous year Previous year Current year (RE) Ensuing Years (Projectio n) Progressiv e Capital expenditur e upto the end of ensuing year (s) A p p ro v e d i n M Y T /R E A c tu a l* C a p it a liz a ti o n C a p it a l E x p e n d it u re (C W IP ) Approved in MYT/RE C a p it a liz a ti o n C a p it a l E x p e n d it u re (C W IP ) C a p it a liz a ti o n C a p it a l E x p e n d it u re (C W IP ) C a p it a liz a ti o n C a p it a l E x p e n d it u re (C W IP ) C a p it a liz a ti o n C a p it a l E x p e n d it u re (C W IP ) C a p it a liz a ti o n C a p it a l E x p e n d it u re (C W IP ) Total ** ** ** **Must be in agreement with the figures shown in audited account, otherwise a reconciliation statement must be accompanied.

* Please furnish seperately details regarding approval of Capital Investment under BERC (Procedure for Filing Capital Investment and Capitalization Plan) Regulations, 2018 and indiacte the portion which is not approved under BERC (Procedure for Filing Capital Investment and Capitalization Plan) Regulations, 2018.

Note:

• The amount of grants and loans shall be furnished separately scheme wise and funding agency wise.

• Additional column may be inserted(if required) for Ensuing Years (Projection).

• All Information for previous year, current year (RE), Ensuing year must be in line with information approved in MYT/Business Plan (if any), other-wise a statement showing complete details of variation must be accompanied.

• CWIP shall mean Capital Work in Progress

(e) Investment Plan (Year-wise) S.N Year Originally proposed Approved by the Commission Revised Revised approval by the Commission in review Actual expenditure ii) Information for the current year to be given in columns 1 to 5 co-relating the information given in MYT/Business Plan (if any) iii) Amount of grants and loans shall be furnished separately funding Agencywise and yearwise.

54 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee

(f) Abstract of Capital Cost for the existing Project, Capital Cost Estimates and Schedule of Commissioning for the New projects Form No:F5 Rs Crores Particulars Previous Year Current Year (i. e. RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) 1 Capital Cost Foreign Component Foreign Exchange rate considered for the admitted cost Domestic Component IDC including Financing Charges Capital cost admitted as on------- (Give reference of the BERC relevant Order with Petition No.

& Date ) 2 Less : Capital Expenditure(CWIP) 3 Less : User contributions and Grants - - - 4 Total Capital Cost admitted 5 Increase /Decrease due to FERV 6 Capital Cost for Purposes of ARR* *Must be in agreement with the figures shown in Form No: F5 (page-2), otherwise a reconciliation statement must be accompanied.

Note

1. Copy of approval letter should be enclosed. Deviation in capital cost and scope of work if any, must be submitted in detailed.

2. Details of IDC & Financing Charges are to be furnished as per FORM- .

(g) Financial Package of Capital cost Admitted Rs. Crores Particulars Capital Cost as Approved Capital Cost Incurred Capital cost Admitted Currency Amount Currency Amount Currency Amount Loans Loan-I Loan-II and so on Total Loan Equity Foreign Domestic Total Equity Total Capital cost Debt : Equity Ratio Provide details for True-up period, Current Year and each of ensuing years separately.

55 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Form No: F5

(h) Capital Cost Estimates and Schedule of commissioning for New Projects Particulars Present Day Cost Completed Cost Date of approval of the Capital cost estimates:

Price level of approved estimates As of End of ________ Qtr. Of the year _________ As on Scheduled COD of the Station Foreign Exchange rate considered for the Capital cost estimates Capital Cost excluding IDC, FC, FERC & Hedging Cost Foreign Component, if any (In Million US $ or the relevant Currency) Domestic Component (Rs. crores) Capital cost excluding IDC, FC, FERC & Hedging Cost (Rs. crores) IDC, FC, FERC & Hedging Cost Foreign Component, if any (In Million US $ or the relevant Currency) Domestic Component (Rs. crores) Total IDC, FC, FERC & Hedging Cost (Rs. crores) Rates, taxes & duties considered Capital cost Including IDC, FC, FERC & Hedging Cost Foreign Component, if any (In Million US $ or the relevant Currency) Domestic Component (Rs. crores) Capital cost Including IDC, FC, FERC & Hedging Cost (Rs. crores) Schedule of Commissioning ((Scheduled DOC elementwise)) ------------------------- ------------------------- --------------------------- COD of last Unit/ Block Note:

1. Copy of approval letter should be enclosed.

2. Details of Capital cost are to be furnished as per Form F5-5 or Form 14(Additional Capitalization) as applicable.

3. Details of IDC & Financing Charges are to be furnished as per Form 20 Signature of Petitioner 56 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee

(i) Break-up of Project Cost for Transmission System Form No: F5 Rs. Crores No Break Down As per original estimates Actual capital expenditure ( Opening ) Variation (B-C) Reasons for Variation A B C D E A Transmission Line 1 Preliminary works

1.1 Design & Engineering

1.2 Priliminary investigation,Right of way, forest clearance, PTCC , general civil works etc.

Total Preliminary works - - 2 Transmission Lines material

2.1 Towers Steel

2.2 Conductor

2.3 Earth Wire

2.4 Insulators

2.5 Hardware Fittings

2.6 Conductor & Earthwire accessories

2.7 Spares

2.8 Erection, Stringing & Civil works including foundation Total Transmission Line Materials - - 3 Taxes and Duties

3.1 Custom Duty

3.2 Other Taxes & Duties * Pertaining to Transmission Business Only, SLDC shall file separately - - Total -Transmission lines - - B. Substations 4 Preliminary works & land

4.1 Design & Engineering

4.2 Land

4.3 Site preparation Total Preliminary works & land - - 5 Civil Works

5.1 Control Room & Office Building including HVAC

5.2 Township & Colony

5.3 Roads and Drainage

5.4 Foundation for structures

5.5 Misc. civil works Total Civil Works - - 6 Substation Equipments

6.1 Switchgear (CT,PT, Circuit Breaker, Isolator etc) 57 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018

6.2 Transformers

6.3 Compensating Equipment (Reactor, SVCs etc)

6.4 Control , Relay & Protection Panel

6.5 PLCC

6.6 HVDC package

6.7 Bus Bars/ conductors/Insulators

6.8 Outdoor lighting

6.9 Emergency D.G. Set

6.1 Grounding System

6.1 Structure for switchyard Total Substation Equipments - - - 7 Spares 8 Taxes and Duties

8.1 Custom Duty

8.2 Other Taxes & Duties Total Taxes & Duties - - Total (Sub-station) - - - 9 Construction and precommissioning expenses

9.1 Site supervision & site admn.etc.

9.2 Tools and Plants

9.3 construction Insurance Total Construction and pre commissioning expenses - - - 10 Overheads 10 Establishment 10 Audit & Accounts 10 Contingency Total Overheads - - - 11 Total Cost - - 12 IDC, FC, FERV & Hedging Cost 12 Interest During Construction (IDC) 12 Financing Charges (FC) 12 Foreign Exchange Rate Variation (FERV) 12 Hedging Cost Total of IDC, FC, FERV & Hedging Cost - - 13 Capital Cost incl. IDC, FC, FERV & Hedging Cost - - Note:

1. In case of time & Cost over run, a detailed note giving reasons of such time and cost over run should be submitted clearly bring out the agency responsible and whether such time & cost over run was beyond the control of the transmission licensee.

2. Above statement to be provided separately for each transmission line commissioned during the ARR period 58 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee

(j) Break-up of Construction/ Supply/ Service packages Form No: F5 SL. Particulars 1 2 3 4 5 6 ---- 1 Name/ No. of Construction / Supply / Service Package (and Schemes/plan) 2 Scope of works1 (in line with head of cost break-ups as applicable) 3 Whether awarded through ICB/DCB/ Departmentally/ Deposit Work 4 No. of bids received 5 Date of Award 6 Actual Date of Start of work Original Scheduled date of Start of work 7 Actual date of Completion of Work Original Scheduled date of Completion of work 8 Value of Award2 in (Rs. Lakhs) 9 Firm or With Escalation in prices 10 Actual capital expenditure till the completion or up to COD whichever is earlier for work capitalized during the period(Rs.Cr.)

- Taxes & Duties and IEDC (included in above) - IDC, FC, FERV & Hedging Cost(included in above) 11 Actual capital expenditure till the end of the period(Rs.Cr.) for Capital work under progress - Taxes & Duties and IEDC (included in above)- IDC, FC, FERV & Hedging Cost(included in above) 12 Actual capital expenditure already capitalized in earlier years(Rs.Cr.)

- Taxes & Duties and IEDC (included in above) - IDC, FC, FERV & Hedging Cost(included in above) 13 Sub -total (10+11+12) Note:

1. Above statement to be provided separately for each work commissioned during the period, work under progress and part capitalization done in earlier years.

2. Statement as Per Form F5-6 to be duly reconciled with corresponding Cost Break Up to be provided as per Form F5-5 , for each transmission line commissioned during the True-up, Review and ARR period * Pertaining to Transmission Business Only, SLDC shall file separately Signature of Petitioner 59 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee

(k) Statement of Additional Capitalization Form No: F5 Rs. Crores No Year Work/ Equipment proposed to be added after COD up to Cut off Date/ Beyond Cut off Date Amount capitalised and Proposed to be capitalised Justification Regulations under which covered Admitted Cost1 1 2 3 4 5 6 7 8 9 10 11 12 13 Note:

1 Fill the form in chronological order year wise along with detailed justification clearly bring out the necessity and the benefits accruing to the beneficiaries.

2 In case initial spares are purchased alongwith any equipment, then the cost of such spares should be indicated separately.

* Pertaining to Transmission Business Only, SLDC shall file separately 60 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee

(l) Statement of Capital Works in Progress Form No: F5 Rs. Crores Particulars Previous Year Current Year (i. e.

RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) A a Opening Capital Expenditure(CWIP) b Amount of IDC, FC, FERV & Hedging cost included in a above B a Addition/Adjustment in Capital Expenditure(CWIP) during the period b Amount of IDC, FC, FERV & Hedging cost included in a above C a Capitalization/Transfer to Gross Fixed asset during the period b Amount of IDC, FC, FERV & Hedging cost included in a above D a Closing Capital Expenditure(CWIP) b Amount of IDC, FC, FERV & Hedging cost included in a above * Pertaining to Transmission Business Only, SLDC shall file separately 61 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Form No: F5

(m) Capital Work-In-Progress (CWIP) ((Rs. Crores)) S.N Particulars Previous year (Actuals) Current year (RE) Ensuing year (s) (Projections) Loan Grant Equity Loan Grant Equity Loan Grant Equity 1 Opening CWIP 2 New Investment 3 Less Capitalization(a+b) a) CWIP Capitalization b) New Investment capitalization 4 Closing CWIP (1+2- 3) * Pertaining to Transmission Business Only, SLDC shall file separately 62 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Normative Parameters Considered for Tariff Computations Form No: F6 Particulars Previous Year Current Year (i. e. RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) 1 Target Availability % AC System % 98 98 HVDC bi-pole links % 92 92 92 HVDC back-to-back Stations % 95 95 95 2 Normative O&M per ckt.km, if any Rs.

Crores 1 1 1 3 Normative O&M per bay, if any Rs.

Crores

0.25 0.25 0.25 4 Normative A&G expenses per ckt.km, if any Rs.

Crores

0.30 0.30 0.30 5 Normative A&G per bay, if any Rs.

Crores

0.10 0.10 0.10 6 Normative R&M expenses % of GFA 1 1 1 7 Maintenance Spares for Working Capital, if any % of O&M 40% 40% 40% 8 Receivables for Working Capital in Months 2 2 2 9 Effective Rate of Return on Equity % 10 Base Rate of Reserve Bank as on ________________ % 11 State Bank one-year ‘MCLR’ as on ___ % 12 Bank Rate as on ___ % 63 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee

(a) Reconciliation of Gross Fixed Assets(GFA) admitted with Gross Fixed Assets(GFA) of Financial Account Form No: F7 Rs. Crores Particulars Previous Year Current Year (i. e. RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) A Gross Fixed Assets ( as at beginning of the year):

1.GFA as per (Financial/Statutory Account)

2.Expenditure allowed but not capitalized in Financial/Statutory Account

3.Expenditure Capitalized in Financial/Statutory Account but not allowed.

4. Admitted GFA(1+2-3) B Addition/ adjustment to Gross Fixed Assets (During the year):

5.Expenditure capitalized in Financial/Statutory Account

6.Expenditure allowed but not capitalized in Financial/Statutory Account

7.Expenditure Capitalized in Financial/Statutory Account but not allowed.

C Gross Fixed Assets (as at end of the year) Admitted by the commission( 4+5+6-7) Signature of Petitioner 64 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Form No: 7

(b) Gross Fixed Assets (GFA) (Information to be supplied for the previous year (actuals), current year (RE) and the ensuring year (s) (projections) (Rs. in Cr.)

S.

N Particular s(i.e Assets Group) GFA at the beginning of the year Addition to GFA during the year Adjustment to GFA on account of assets sold/discarded etc GFA at the end of the year C o n s u m e r C o n trib u tio n B y g ra n ts L o a n E q u ity T o ta l C o n s u m e r C o n trib u tio n B y g ra n ts L o a n E q u ity T o ta l C o n s u m e r C o n trib u tio n B y g ra n ts L o a n E q u ity T o ta l C o n s u m e r C o n trib u tio n B y g ra n ts L o a n E q u ity T o ta l 1 2 3 4 5 6 8 9 10 11 12 13 14 15 16 17 18 19 1 Land and land rights 2 Buildings 3 Hydraulic works 4 Other civil works 5 Plant and Machinery 6 Lines and cable network 7 Vehicles 8 Furniture and Fixtures 9 Office equipment 10 Others, if any (pl.

specify) Total

(c) Bifurcation of Fixed Assets into IDC and IEDC etc.

S.N Particulars Previous Year Current Year (RE) Ensuing years Approved in MYT/RE Actual 1 Opening Gross Fixed Assets a Additions in Gross Fixed Assets b Amount of IDC, FC, FERV & Hedging cost included in B(a) above c Amount of IEDC (excluding IDC, FC, FERV & Hedging cost) included in B(a) * Pertaining to Transmission Business Only, SLDC shall file seperately 2 Closing Gross Fixed Assets 65 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018

(d) Bifurcation of Fixed Assets into Depreciable and Non-depreciable assets etc.

*grants includes consumer contributions.

1 Gross fixed assets of the beginning of the year Less: Value of non depreciable assets (i.e land) 2 Additions during the year Less: Value of non depreciable assets (i.e land) 3(i) IDC, FC, FERV & Hedging cost 3(ii) Amount of IEDC 4 Adjustment for assets sold/discarded etc 5 Closing GFA 6 Average GFA (Excluding Value of non depreciable assets) 7 Weighted Average Rate of Depreciation 8 Gross Depreciation 9 Opening grants* 10 Grants* during the year 11 Adjustment for assets sold/discarded etc 12 Total Grants* 13 Average Grants* 14 Weighted Average rate of Depreciation 15 Depreciation for GFA on Grants 16 Net Depreciation of GFA(8-15) 66 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee

(e) Value of Depreciation Charges (Rs. Crores) Form No: 7 S.

N Particulars (i.e Assets Group) Accumulated Depreciation Accumulated Accumulated depreciation at the beginning of the year charges during the year depreciation adjustment on account of assets sold/discarded etc depreciation at the end of the year C o n s u m e r C o n trib u tio n B y g ra n ts L o a n E q u ity T o ta l C o n s u m e r C o n trib u tio L o a n E q u ity T o ta l C o n s u m e r C o n trib u tio n B y g ra n ts L o a n E q u ity T o ta l C o n s u m e r C o n trib u tio B y g ra n ts L o a n E q u ity T o ta l 1 2 3 4 5 6 8 9 10 11 12 13 14 15 16 17 18 19 1 Land and land rights 2 Buildings 3 Hydraulic works 4 Other civil works 5 Plant and Machinery 6 Lines and cable network 7 Vehicles 8 Furniture and Fixtures 9 Office equipment 10 Others, if any (pl.

specify) Total * Pertaining to Transmission Business Only, SLDC shall file separately 67 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee

(d) Statement of Assets Not in Use Form No: F7 Rs. Crores Financial Year* Sl. No. Date of Acquisition/Installation Historical Cost/Cost of Acquisition Date of withdrawal operations Accumulated Depreciation on date of withdrawal Written down value on date of withdrawal - - - *Note:- Information to be provided for Previous Year, Current Year & Ensuing Control Period Signature of Petitioner 68 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee User contributions and grants towards cost of capital assets (Rs. Crores) Form No: F8 Particulars Previous Year Current Year Ensuing Year/years B a la n c e a t th e s ta rt o f th e y e a r A d d itio n s B a la n c e a t th e e n d o f th e Y e a r A d d itio n s B a la n c e a t th e e n d o f th e Y e a r A d d itio n s B a la n c e a t th e e n d o f th e Y e a r 1 User contributions Towards Cost Of Capital Assets - 2 Grant Towards Cost Of Capital Assets A Total (1+2) - - - - - - Amount utilized for Assets forming part of Depreciable GFA 3 User contributions Towards Cost Of Capital Assets - 4 Grant Towards Cost Of Capital Assets B Total (3+4) - - - - Amount utilized for Assets forming part of non- Depreciable GFA 5 User contributions Towards Cost Of Capital Assets - 6 Grant Towards Cost Of Capital Assets C Total (5+6) - Amount remains un-utilized (A-B-C) 7 User contributions Towards Cost Of Capital Assets - 8 Grant Towards Cost Of Capital Assets C Total (7+8) D Amount utilized for CWIP out of "C" above E Amount kept in Bank out of "C" above F Depreciation on assets created out of grants (Admitted) G Depreciation. on assets created out of grants (Financial/Statutory Account) * Pertaining to Transmission Business Only, SLDC shall file separately 69 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee

(a) Details of Loans for the year Form No: F9 S.N Particulars Purpose of loan Opening balance Rate of Interest Addition during the year Repaymen t during the year Closing balance Amount of interest paid* 1 2 3 4 5 6 7 8 *The amount of penal interest, if any, to be shown separately.

(b) Further Details in case of Foreign Loans S.N Particulars Date Amount (Foreign Currency) Exchange Rate Amount in Rs.

Crore Name of Currency Loan drawal Scheduled Principal Repayment Actual Principal Repayment Scheduled Interest payment Actual Interest payment Period of hedging Cost of hedging * Pertaining to Transmission Business Only, SLDC shall file separately Note: Information to be supplied separately for the previous year (actuals), current year(RE) and ensuing years

(c) Information Regarding Restructuring of Outstanding Loans During the Year S.

N Source of loan Amount of original loan Old rate of interest Amou nt alread y restruc tured Revise d rate of interest Amount now being restructur ed New rate of interest 1 2 3 4 5 6 7 8 70 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee

(d) Domestic loans, bonds and financial leasing Form No: F9 Rs. Crores Sl.

No.

Particulars Opening Balance at the beginning of the year Amount received during the year Principal repayment Interest Closing Balance P rin c ip a l n o t o v e rd u e P rin c ip a l o v e rd u e In te re s t o v e rd u e T o ta l D u e P a id D u e P a id % P rin c ip a l In te re s t O v e rd u e A LONG-TERM 1 LIC 2 REC 3 PFC 4 Bonds 5 Bank 6 APDRP 7 Any Other, please specify Sub Total (A) - - - - - - - - - - - B SHORT-TERM 1 2 3 4 Sub Total (A) - - - - - - - - - - - Total (A+B) - - - - - - - - - - - *Note:- Loanwise information to be provided for Previous Year, Current Year & Control period. Also indicate rate of interest and other conditions.

* Pertaining to Transmission Business Only, SLDC shall file separately Signature of Petitioner 71 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Form No: F9

(e) Statement of Reconciliation of Net Actual Loan ( opening ) with Net Normative Loan ( Opening ) (Rs. In Crore) Particulars Previous year Current year (RE) Ensuing Years FY (n+1) FY (n+2) FY (n+3) Net Actual Loan as per Books of Accounts as on :

Domestic Foreign - - - - - Add: Repayment Made till Date Gross Actual Loan - - - - - Add: Equity considered as normative loan Gross Normative Loan - - - - - Less : Depreciation Recovered as per ARR till Date Net Normative Loan - - - - - * Pertaining to Transmission Business Only, SLDC shall file separately 72 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Details of Equity Form No: F10

(a) Details of Foreign Equity Rs. Crores S.

N o.

Particulars Previous Year Current Year (i. e. RE) Ensuing years (Projection) D a te A m o u n t (F o re ig n C u rre n c y ) E x c h a n g e R a te A m o u n t in In d ia n R u p e e D a te A m o u n t (F o re ig n C u rre n c y ) E x c h a n g e R a te A m o u n t in In d ia n R u p e e D a te A m o u n t (F o re ig n C u rre n c y ) E x c h a n g e R a te A m o u n t in In d ia n R u p e e Currency1 1 1 Infusion 2 Currency2 1 1 Infusion 2 Total 1 Name of the currency to be mentioned e.g. US $, etc.

2 In case of equity infusion more than once during the year, Exchange rate at the date of each infusion to be provided

(b) Details of Indian Equity Rs. Crores S.No. Particulars Previous Year Current Year (i.

e. RE) Ensuing years (Projection) Date Amount Date Amount Date Amount 1 Infusion 2 - 3 - Total * Pertaining to Transmission Business Only, SLDC shall file separately

(c) Total return on equity Rs. Crores 1 Amount of total asset created during the year 2 Less asset created from grant 3 Less asset created from users contribution 4 Net asset Created 5 Amount of equity addition 6 Equity (Opening Balance) 7 Equity (Closing Balance) 8 Average Equity 9 Base rate of Return on Equity% Tax Rate ( Enclose detailed calculation alongwith supporting documents)% Effective Rate of Return on Equity 10 Return o Equity (Rs. In crore) 11 Equity entitled to incentive 12 Incentive 13 Additional Return 14 Total Return on Equity 73 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018

(d) Details of total equity infused S.No. Particulars Previous year Current year (RE) Ensuing Years Shareholders’ Funds 1 Equity Share Capital 2 Share Premium utilized for Capital Expenditure 3 Free Reserves utilized for Capital Expenditure Total Equity 74 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Interest and Finance Charges(Rs. Crores) Form No: F11 S.N. Source of loan Purpose of loan Previous year (Actuals) Current year (RE) Ensuing year (s) 1 2 3 4 5 6 1 SLR Bonds 2 Non SLR Bonds 3 LIC 4 REC 5 PFC 6 Commercial Banks 7 Bills discounting 8 Lease rental 9 Others, if any (Please specify) 10 Total 11 Add State Govt. Loan 12 Total (10 +11) 13 Less IDC 14 Net Interest 15 Add prior period adjustment * 16 Total Interest 17 Finance charges 18 Total Interest and finance charges * Year-wise details should be submitted with documentary evidence. Further Rate of interest of various loans to be indicated in a separate sheet.

* Pertaining to Transmission Business Only, SLDC shall file separately Particulars Quantum in Foreign currency Exchange Rate on draw down date Amount in Indian Rupee Note: Drawal of debt and equity shall be on paripassu basis to meet the commissioning schedule. Drawal of higher equity in the beginning is permissible. Also specify basis of allocation to particular project.

1 Loans

1.1 Foreign Loans

1.1.1 Foreign Loan 1 Draw down Amount IDC Financing charges

1.1.2 Foreign Loan 2 - - - - Total Draw down Amount - - - Total IDC - - - Total Financing charges 75 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Interest (IDC) Capitalized S.N. Name of scheme /Project Source of loan Interest capitalized As on beginning of previous year During Previous year (Actuals) During Current year (RE) During ensuing year (s) 1 2 3 4 5 6 1 2 76 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Lease details(Rs. Crores) Form No: F12 S.

N Name of Lesser Assets Leased Lease Rentals Primary Period Secondary Descriptions Gross Amount on ended / ending by period ending by 1 2 3 4 5 6 7 8 Note: Statement showing Cost benefits analysis of lease must be accompanied.

77 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Operations & Maintenance Cost Form No: F13 Rs. Crores Sl.No Particulars Previous Year Current Year (i. e. RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) 1 Repair & Maintenance Expenses 2 Employee Expenses 2 Administrative and General Expenses Less :

4 Expenses Capitalized Net O&M Expenses - - - - - - Signature of Petitioner * Pertaining to Transmission Business Only, SLDC shall file separately 78 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee

(a) Employee Expenses Form No:F14 Rs. Crores S.N Particulars Previous Year Current Year(RE) Ensuing Year (s) Approved in MYT/RE Actual 1 Salaries & Allowances

(i) Existing Employees

(ii) New Employees

(ii) Total 2 Contribution to Terminal Benefits (Accrual Basis) 3 Total of Salary & Allowances and Terminal Benefits 4 Amount Capitalised 5 Net Amount 6 Grand Total Note:

(i) Terminal benefits paid for the period before the date of reorganisation i.e.

01.11.2012, shall not be considered.

(ii) In respect of continuing employees as on the date of reorganisation and newly appointed employees after re-organisation date the terminal benefits shall be allowed.

(iii) In respect of item 6, a brief description to be appended.

* Pertaining to Transmission Business Only, SLDC shall file separately 79 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee

(b) Consumer Price Inflation Form No: F14 Particulars PY 5 PY 4 PY3 PY 2 PY 1 CY Ensuing years (Projection) FY (n-5)) FY (n- 4) FY (n-3) FY (n-2) FY (n-1) FY

(n) FY (n+1) FY (n+2) FY (n+3) Annual Average CPI Index CPI Inflation ##### ##### ##### Annual Average WPI Index WPI Inflation Note CPI and WPI Inflation computed for current year shall be considered for control period at the time of filing of ARR.CPI inflation shall be determined at the time of truing up.

Signature of Petitioner * Pertaining to Transmission Business Only, SLDC shall file separately 80 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee

(c) Employee Strength Form No: F14 S.N Particulars Previous year (Actuals) Current Year (R.E) Ensuing years (Projection) 1 2 3 4 5 6 7 1 Number of employees at the beginning of FY _______ a) Technical b) Non Technical (Administration) c) Non Technical(Revenue, Finance and Accounts) 2 No. of employees added during FY ______ a) Technical b) Non Technical (Administration) c) Non Technical(Revenue, Finance and Accounts) 3 Number of employees retiring/ leaving during the FY_____ a) Technical b) Non Technical (Administration) c) Non Technical(Revenue, Finance and Accounts) 4 Number of employees at the end of the FY (1+2-3) a) Technical b) Non Technical (Administration) * Pertaining to Transmission Business Only, SLDC shall file separately 81 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Form No: F14

(d) Employees Productivity Parameters (in Crore) S.N Particulars Previous year Current Ensuing Year (R.E) years (Projection) Approved in MYT/RE (Actuals) 1 2 3 4 5 6 7 8 1 Number of employees 2 Number of Sub-stations 3 Total capacity of Substations (MVA) 4 Transmission line length in ckt/km 5 Energy Received at STU- CTU interface (Units) 6 Employees per MU of energy handled (5/1) 7 Employees cost 8 Employees cost in paise / kWh (7/5) 82 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee R&M Expenses Form No: F15 Rs. Crores Particulars Previous Year Current Year (i. e.

RE) Ensuing years (Projection) *Normative/A pproved in MYT/RE Actu al FY (n) FY (n+1) FY (n+2) FY (n+3) 1 Average Gross Fixed Assets 2 Percentage point as per the norm (%) 3 Repair & Maintenance Expenses 0 0 0 0 0 *Normative/Approved in MYT/RE: If norms are specified by the Commission for concern year, Normative figures shall be given. In case norms are not specified latest approved figures in MYT or Revised Estimate(RE) as the case may be shall be given.

Further details of component wise R&M Expenses Particulars Previous Year Current Year (i.

e. RE) Ensuing years (Projection) *Normative/ Approved in MYT/RE Actual FY (n) FY (n+1) FY (n+2) FY (n+3) 1 Plant & Machinery 2 Building 3 Hydraulic works & civil works 4 Line cable & network * Pertaining to Transmission Business Only, SLDC shall file separately 6 Furniture & fixtures 7 Office equipments 8 Any other expenses (please specify) 9 Total expenses 10 Less capitalized 11 Net Expenses 12 Total expenses charged to revenue * Year-wise details of these charges may be provided with documentary evidence 83 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Administration and General Expenses Form No: F16 Rs. Crores Particulars Previous Year Current Year (i.

e. RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) Rent, rates & taxes Insurance Telephone, postage & Telegrams Consultancy fees Technical fees Other professional charges Conveyance & travel expenses Electricity & Water charges Freight Other material related expenses Penalty/Fine Paid (if any) Any other expenses (please specify) Total expenses Less Capitalised Net expenses Total expenses charged to revenue * Year-wise details of these charges may be provided with documentary evidence.

* Pertaining to Transmission Business Only, SLDC shall file separately 84 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Short Term Open Access Consumers Form No: F17 Rs. Crores Particulars Previous Year Current Year (i. e. RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) Number of Short Term Open Access Customers Amount Retained by Licensee 0 0 0 0 0 0 Payable to Beneficiaries 0 0 0 0 0 0 Signature of Petitioner 85 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Details of Non-tariff Income Form No: F18 Rs. Crores No Particulars Previous Year Current Year (i.

e. RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) 1 Profits derived from disposal of assets 2 Rents 3 Income from Investments other than Contingency reserves 4 Interest on Loans and Advances to Lessors 5 Interest on Advances to Suppliers / Contractors 6 Delayed Payment surcharge 7 Meter Rent 8 Miscellaneous Receipts from consumers 9 Interest on loans and Advances to Staff 10 Income/Fee/Collection against staff welfare activities 11 Others, please specify Total - - - - - - * Pertaining to Transmission Business Only, SLDC shall file separately 86 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Working Capital Interest Form No: F19 Rs. Crores Particulars Previous Year Current Year (i.

e. RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) 1 Receivables equivalent to two

(2) month of transmission charges calculated on target availability level

0.00 2 O&M Expenses of one month 3 Maintenance spares@40% of R&M expenses for one month 4 Less:

(i) Depreciation, ROE, and contribution to contingency reserve equivalent to two months.

(ii) Security deposit if any, held during the year

(iii) two months equivalent of grant received from the State Govt.

Total Working Capital Interest Rate 12.50% Interest on Working Capital * Pertaining to Transmission Business Only, SLDC shall file separately 87 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Investments in Non business related activities Form No: F20 Rs. Crores Sl.

No.

Description of investment Balance at the beginning of the year Further Investments during the year Investments realised during the year Balance at the end of the year Remarks Details of Income from Other Business (Rs. In Crore) No Particulars Previous year Current year (RE) Ensuing Years I Receipts from other Business I Less: Expenses from other business E Revenue of other Business R=I-E 0 0 0 0 II Assets of Licensed business utilized in other business A Total assets of other business (including the assets utilized of the Licensed Business) C Allocation of Revenue to Licensed Business decided by the Commission X III Due to Licensed Business (to be deducted from ARR)* X*(R*A/C) Note:- Information to be provided for Previous Year, Current Year & each year of Control period *In case Gross Receipts exceed expenditure of other business in (I) above (where Gross receipt is less than expenditure of other business in (I) above no amount shall be deducted from ARR of Licensee).

* Pertaining to Transmission Business Only, SLDC shall file separately 88 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Details of Expenses Capitalised Form No: F21 Rs. Crores Sl.

No.

Particulars Previous Year Curren t Year (i. e.

RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) 1 Interest & Finance charges Capitalised 175.69 2 Other expenses capitalised:

a. Employee expenses 120.24 b. R&M Expenses 0 c. A&G Expenses 6 d. Depreciation 0 e. Others, if any 0 Total of 2 Grand Total Signature of Petitioner 89 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Net Prior Period Expenses / Income Form No: F22 Rs. Crores Sl.No.

Particulars Previous Year Current year (RE) A Income relating to previous years:

1 Interest income for prior periods 2 Income Tax prior period 3 Excess Provision for Depreciation 4 Excess Provision for Interest and Fin. Charges 5 Other Excess Provision 6 Others (please specify) Sub-Total A - - B Expenditure relating to previous years 1 Employee Cost 2 Depreciation 3 Interest and Finance Charges 4 Admn. Expenses 5 Withdrawal of Revenue Demand 6 Material Related 7 Others (please specify) Sub-Total B - - Net prior period Credit/(Charges) : A-B - - * Pertaining to Transmission Business Only, SLDC shall file separately Sl.No. Particulars 1 Extraordinary Credits a -- TOTAL CREDITS - - 2 Extraordinary Debits a -- TOTAL DEBITS - - 90 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Form No: F23 Contribution to Contingency Reserve(Rs. Crores) S.N Particulars Amount 1 2 3 1 Fixed Assets 2 %age appropriation to the contingency reserve 3 Appropriation to the contingency amount 4 Amount invested in securities 5 Drawal from the contingency reserve (Please specify)

(i)

(ii)

(iii) Total drawal Information Regarding Grant/Subsidy from State Govt/Central Govt.

S.N Particulars Previous Year Current Year Ensuing Years 1 2 3 4 5 A Amount from State Govt.

i) Purpose for which grant received

(a)

(b) ii) Targeted categories for subsidy * Pertaining to Transmission Business Only, SLDC shall file separately

(b) B Amount from Central Govt.

i) Purpose for which grant received

(a)

(b) 91 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Allocation statement of Expenses of SLDC Form No: F24 Rs. Crores Particulars Previous year Current Year Ensuing Years T o ta l E x p e n s e s o f S T U A llo c a te d % S L D C S h a re T o ta l E x p e n s e s o f S T U A llo c a te d % S L D C S h a re T o ta l E x p e n s e s o f S T U A llo c a te d % S L D C S h a re Expenditure a O&M Expenses i R&M Expense ii Employee Expenses ii i A&G Expense Total O&M expenses ( i+ii+iii) 0 0 0 b Depreciation c Interest on Loan f Return on Equity g Others, please specify Total Expenditure 92 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Transmission Losses (For Transmission Licensee) Form No: P1 S.No. Details Previous Year Current Year Ensuing Years A Losses in 400 KV system 1 Total Energy delivered by Generating Stations and Inter State/Intra State tie-links at the interface points of the Intra State Transmission system 2 Energy Delivered to next (Lower) Voltage level of the Transmission System 3 Sum of all the energy delivered at this voltage level to the State Distribution System 4 Transmission loss in system (A1- A2-A3) 5 Transmission loss in (Transco) system (%) {A4/A1} x 100 B Losses in 220 KV system Previous Year Current Year Ensuing Years 1 Total Energy delivered by Generating Stations and Inter State/Intra State tie-links at the interface points of the Intra State Transmission system 2 Energy Delivered to next (Lower) Voltage level 3 Sum of all the energy delivered at this voltage level to the State Distribution System 4 Transmission loss in system (B1- B2-B3) 5 Transmission loss in (Transco) system (%) {B4/B1} x 100 C Loss Calculation at 132 KV Previous Year Current Year Ensuing Years FY (n-1) FY (n) FY (n+1) * Pertaining to Transmission Business Only, SLDC shall file separately 2 Energy Delivered to next (Lower) Voltage level 3 Sum of all the energy delivered at this voltage level to the State 93 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Distribution System 4 Transmission loss in system (C1- C2-C3) 5 Transmission loss in (Transco) system (%) {C4/C1} x 100 D Total Losses in the Transmission system Previous Year Current Year Ensuing Years 1 Total Energy delivered by Generating Stations and Inter State tie-links at the interface points of the Intra State Transmission system 2 Sum of all the energy delivered by the Transmission system in to the State Distribution System 3 Transmission loss in system (D1- D2) 4 Transmission loss in (Transco) system (%) {(D3/D1) x 100} Signature of Petitioner 94 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Energy Delivered by Transmission licensee to the Distribution Licensees/ Bulk consumers at interface points Form No:P2 Voltage level Name of Sub- Station Distribution Licensee / Bulk Consumer Total Energy delivered NBPDCL SBPDCL Others, specify MUs MUs MU MUs 1 2 3 4 9 10 220 KV i ii iii iv 132 kV I ii iii iv 33 kV i ii iii iv * Pertaining to Transmission Business Only, SLDC shall file separately Total for all voltages Details to be provided for previous years, current year and for each year of control period.

95 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission licensee Details of Electrical Accidents Form No:P3 Type of Accident Previous Year Current year (RE) No. of Accidents No. of Accidents Fatal Non Fatal Total Fatal Non Fatal Total Human - - Other, if any, (please specify) - - Total - - - - - - * Pertaining to Transmission Business Only, SLDC shall file separately 96 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of the Transmission Licensee Abstract of Outages due to feeder tripping Form No: P4 SNo. Detail Previous Years Current Years Ensuing Years N o . o f fe e d e rs N o . o f trip p in g s T o ta l D u ra tio n o f T rip p in g s (h rs .)

A v e ra g e d u ra tio n o f in te rru p tio n p e r fe e d e r N o . o f fe e d e rs N o . o f trip p in g s T o ta l D u ra tio n o f T rip p in g s (h rs .)

A v e ra g e d u ra tio n o f in te rru p tio n p e r fe e d e r N o . o f fe e d e rs N o . o f trip p in g s T o ta l D u ra tio n o f T rip p in g s (h rs .)

A v e ra g e d u ra tio n o f in te rru p tio n p e r fe e d e r 1 Feeder voltage Level (400 KV) 2 Feeder voltage Level (220 KV) 3 Feeder voltage Level (132 KV) * Pertaining to Transmission Business Only, SLDC shall file separately 97 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Major System Disturbances Form No: P5 S.

No.

Disturbances Previous Years Current Years Ensuing Years Number Total Duration (Hrs.)

Number Total Duration (Hrs.)

Number Total Duration (Hrs.)

A Disturbances when DISCOM supply has been effected for more than 1 hr.

i Due to 400 kV transformer failures ii Due to 400 kV transmission line outage iii Due to 400 kV substation equipment (CT, CVT etc.) failure iv Due to 220 kV transformer failure v Due to 220 kV transmission line failure vi Due to 220 kV substation equipment (CT, CVT etc). failure vii Due to 132 kV transformer failure viii Due to 132 kV transmission line failure ix Due to 132 kV substation equipment (CT, CVT etc). failure B Estimated unserved energy due to such interruptions C Other Transmission disturbances when DISCOM supply has got effected i ii iii iv v * Pertaining to Transmission Business Only, SLDC shall file separately 98 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Frequency Variation Form No:P6 Sl.

No.

Frequency Previous Years Current Years Ensuing Years No. of Hours As percentage of total hours in the year (%) No. of Hours As percentage of total hours in the year (%) No. of Hours As percentage of total hours in the year (%) 1 Above 50.5 Hz 2 50.5 - 5.2 Hz 3 50.2 - 49.8 Hz 4 49.8 - 49.5 Hz 5 49.5 - 49.0 Hz 6 49.0 - 48.5 Hz 7 Below 48.5 Hz * Pertaining to Transmission Business Only, SLDC shall file separately 99 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Voltage Fluctuation Form No: P7 Name of Sub- Station Tran sfor mati on Cap acity Reacti ve Comp ensati on provi ded Previous Year Current Year Ensuing Years Time during which voltage in an year Time during which voltage in an year Time during which voltage in an year More than upper limit in %age Between upper & lower limit Less than lower limit in %age More than upper limit in %age Between upper & lower limit Less than lower limit in %age More than upper limit in %age Between upper & lower limit Less than lower limit in %age H o u rs % a g e H o u rs % a g e H o u rs % a g e H o u rs % a g e H o u rs % a g e H o u rs % a g e H o u rs % a g e H o u rs % a g e H o u rs % a g e 400 kV level i ii iii iv 220 kV Level i ii iii iv 132 kV level i ii iii * Pertaining to Transmission Business Only, SLDC shall file separately Note: Upper Limit is 420KVrms and lower limit is 360KVrms in case of 400 kv level Upper Limit is 245KVrms and lower limit is 200KVrms in case of 220 kv level .

Upper Limit is 145 kVrms and lower limit is 120 KV rms in case of 132 kv level 100 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Licensee wise Load shedding carried out during the year Form No: P8 S.

No.

Particulars NBPDCL SBPDCL Load shedding during the Year (In Hrs.)

1 On SLDC's instructions a To control excess drawal b To control equipment damage c Under force majeure conditions 2 Due to maintenance or outage of own network 3 Any other reason Total load shedding for the Year Details to be provided for previous two years, base year and for each year of control period.

101 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Details of Overloaded Feeders Form No:P9 S.No. Voltage Level No. of feeders Feeder length (ckt.

Km.)

No. of feeders overloaded Line length overloaded feeders (ckt.

Km.)

% number of Overloade d feeders in Area % length of overloade d feeders in Area Previous Year 1 400 KV 2 220 KV 3 132 KV Current Year 1 400 KV 2 220 KV 3 132 KV * Pertaining to Transmission Business Only, SLDC shall file separately Note:

Equipment considered as overloaded if carrying more than 110% of rated load for average 1 hour per day.

Details to be provided for previous two years, base year and for each year of control period.

Signature of Petitioner 102 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission licensee Details of over loaded Transformers Form No.: P10 Sl.

No.

Rated Voltage Previous Years Current Years Ensuing Years R a te d C a p a c ity A c tu a l L o a d o n T ra n s fo rm e r % o f T ra n s fo rm e rs o v e r lo a d e d R a te d C a p a c ity A c tu a l L o a d o n T ra n s fo rm e r % o f T ra n s fo rm e rs o v e r lo a d e d R a te d C a p a c ity A c tu a l L o a d o n T ra n s fo rm e r % o f T ra n s fo rm e rs o v e r lo a d e d 1 400/220/33 KV Transformers Capacity i ii iii iv Total - - - - - - - - - 2 220/132/33KV Transformers Capacity i ii iii iv Total - - - - - - - - - 3 220/132KV Transformers * Pertaining to Transmission Business Only, SLDC shall file separately i ii iii iv Total - - - - - - - - - 4 132/33KV Transformers Capacity i ii iii iv Total - - - - - - - - - Note:- Details may be submitted Area wise (Circle wise).

Signature of Petitioner 103 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Failure of Transformers Form No: P11 S.

No.

Transformation ratio Previous Years Current Years Ensuing Years T o ta l N o . o f T ra n s fo rm e rs N o . o f fa ilu re s T o ta l D u ra tio n o f fa ilu re (h rs .)

T o ta l N o . o f T ra n s fo rm e rs N o . o f fa ilu re s T o ta l D u ra tio n o f fa ilu re (h rs .)

N o . o f T ra n s fo rm e rs N o . o f fa ilu re s T o ta l D u ra tio n o f fa ilu re (h rs .)

1 400/220/33 KV Transformers Capacity i ii iii iv Total - - - - - - - - - 2 220/132/33KV Transformers Capacity i ii iii iv Total - - - - - - - - - 3 220/132KV Transformers * Pertaining to Transmission Business Only, SLDC shall file separately i ii iii iv Total - - - - - - - - - 4 132/33KV Transformers Capacity i ii iii iv Total - - - - - - - - - 104 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee Key Ratios Form No: P12 S.No Particulars Previous Year Current Year Ensuing Years A Financial & Material Management 1 Annual capital expenditure/net book value 2 Total Transmission cost/Energy Transmitted 3 Employee cost as a percentage of total cost 4 Operating expenses / Revenue from Transmission of power 5 Cost of capital invested 6 Debt Service Coverage Ratio 7 Cost of total Stores Inventory/100 Km of transmission lines 9 Working Capital to Revenue from Transmission of power B HR Management 1 Energy Transmitted (MU) per Employee 2 Total line length/employee (Km.)

3 Connected Load per Employee (MVA) 4 Transmission Income per Employee 5 Training participation days per employee C Operational Performance 1 Unplanned outage/total outage (Fault breakdown / total outage) * Pertaining to Transmission Business Only, SLDC shall file separately Signature of Petitioner ———— PUBLISHED AND PRINTED BY THE SUPERINTENDENT, BIHAR SECRETARIAT PRESS, PATNA.

Bihar Gazette (Extra) 803—571+400—Egazette Website: http://egazette.bih.nic.in

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Multi Year Transmission Tariff and Sldc Charges Regulations, 2018 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.