Section 14: Provisional order.

The Boilers Act, 2025Central Act · Act 12 of 2025

(1) Where the Inspector reports the case of any boiler to the Chief Inspector under sub-section (4) of section 12, he may, if the use of such boiler or its components is not prohibited under clause (f) of sub-section (1) of section 13 as being in a dangerous condition, grant to the owner thereof a provisional order in writing, permitting the boiler to be used at a pressure not exceeding such maximum pressure as he thinks fit and in accordance with the regulations made under this Act, pending the receipt of the order of the Chief Inspector.

(2) Such provisional order shall cease to be in force---

(i) on the expiry of six months from the date on which it is granted; or

(ii) on receipt of the orders of the Chief Inspector; or

(iii) in any of the cases referred to in clauses (b), (c), (d), (e) and (f) of sub-section (1) of section 13,

and on so ceasing to be in force, shall be surrendered to the Inspector.

Where this provision sits

ActThe Boilers Act, 2025
Section14
Marginal noteProvisional order.
JurisdictionCentral
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Boilers Act, 2025 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.