Section 6: Coordination in Operations

Central Electricity Authority (Grid Standards) Regulations, 2010Central Regulations · 2003

(1) No Entity shall introduce or take out the element of the grid without the concurrence of the Appropriate Load Despatch Centre except in case of imminent risk of safety of plant and personnel in which case it must intimate Appropriate Load Despatch Centre giving reasons therefore.

(2) The Appropriate Load Despatch Centre shall inform all affected parties of the outage.

Page 9 of 19

Where this provision sits

ActCentral Electricity Authority (Grid Standards) Regulations, 2010
Section6
Marginal noteCoordination in Operations
JurisdictionCentral
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Central Electricity Authority (Grid Standards) Regulations, 2010 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.