Section 7: After regulation 11 of the said regulations, the following regulation shall be inserted, namely

Central Electricity Authority (Technical Standards for Connectivity of the Distributed Generation Resources) Amendment Regulations, 2019Central Regulations · 2003

“11A. Standards for charging station, prosumer, or a person connected or seeking connectivity to the electricity system. -

(1) The applicant shall provide a reliable protection system to detect various faults and abnormal conditions and provide an appropriate means to isolate the faulty equipment or system automatically.

(2) The applicant shall ensure that fault of his equipment or system does not affect the grid adversely.

(1) The appropriate licensee shall carry out adequacy and stability study of the network before permitting connection with its electricity system.

(2) The limits of injection of current harmonics at the point of common coupling by the user, method of harmonic measurement and other such matters, shall be in accordance with the IEEE 519-2014 standards, as amended, from time to time.

(3) The measuring and metering of harmonics shall be a continuous process with power quality meters complying with the provisions of IEC 61000-4-30 Class A.

(6) The data measured and metered as mentioned in sub-regulation (5), shall be available with the distribution licensee and be shared with the consumer periodically.

(7) The applicant seeking connectivity at 11 kV or above shall install power quality meters and share the recorded data thereof with the distribution licensee with such periodicity as may be specified by the appropriate Electricity Regulatory Commission:

Provided that the user connected at 11 kV and above shall comply with the provision of this sub-regulation within twelve months from the date of commencement of the Central Electricity Authority (Technical Standards for Connectivity of the Distributed Generation Resources) Amendment Regulations, 2018.

(8) In addition to harmonics, periodic measurement of other power quality parameters such as voltage sag, swell, flicker, disruptions shall be done by the distribution licensee as per relevant IEC standard and the reports thereof shall be shared with the consumer”.

Where this provision sits

ActCentral Electricity Authority (Technical Standards for Connectivity of the Distributed Generation Resources) Amendment Regulations, 2019
Section7
Marginal noteAfter regulation 11 of the said regulations, the following regulation shall be inserted, namely
JurisdictionCentral
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Central Electricity Authority (Technical Standards for Connectivity of the Distributed Ge… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.