Section 2: In the Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007 (hereinafter referred to as the said regulations), in regulation 2

Central Electricity Authority (Technical Standards for Connectivity to the Grid ) (Amendment ) Regulations, 2019Central Regulations · 2003

(a) after clause (16), the following clause shall be inserted, namely:— ‘(16A) “installed capacity”,-

(i) in case of coal, lignite, gas engines and hydro stations, means the summation of the name plate capacities of all the units of the generating station or Maximum Continuous Rating of the generating station; and

(ii) in case of wind generating stations and generating stations using inverters, means the summation of the name plate capacities of wind turbines or solar generating units, as the case may be;’;

(b) for clause (25), the following clause shall be substituted, namely: - ‘(25) “requester” includes a generating company, captive generating plant, energy storage system, transmission licensee (other than Central Transmission Utility and State Transmission Utility), distribution licensee, solar park developer, wind park developer, wind-solar photo voltaic hybrid system, or bulk consumer seeking connection for its new or expanded electrical plant to the Grid at voltage level 33 kV and above;’;

(c) for clause (34), the following clause shall be substituted, namely: - ‘(34) “user” includes a generating company, captive generating plant, energy storage system, transmission licensee (other than the Central Transmission Utility and State Transmission Utility), distribution licensee, solar park developer, wind park developer, wind-solar photo voltaic hybrid system, or bulk consumer whose electrical plant is connected to the Grid at voltage level 33 kV and above;’;

(d) after clause (35), the following clause shall be inserted, namely:— ‘(36) “wind farm developer” means a person who has developed or proposes to develop the wind generating station or wind generating farm comprising more than one wind generating unit owned by the developer or any other person;’;

‘(37) “solar park developer” means a person who has developed or proposes to develop the solar park or solar generating station comprising more than one solar generating unit owned by the developer or any other person;’;

‘(38) “wind - solar photo voltaic hybrid system” means a system of electricity generation, which has combination of wind and solar photo voltaic resources, with or without storage system;’.

Where this provision sits

ActCentral Electricity Authority (Technical Standards for Connectivity to the Grid ) (Amendment ) Regulations, 2019
Section2
Marginal noteIn the Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007 (hereinafter referred to as the said regulations), in regulation 2
JurisdictionCentral
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Central Electricity Authority (Technical Standards for Connectivity to the Grid ) (Amendm… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.