(1) The cess levied under Sub-sec. (1) of Sec. 3 of the Act shall be paid by an employer, within thirty days of completion of the construction project or within thirty days of the date on which assessment of cess payable is finalized, whichever is earlier, to the cess collector.

(2) Notwithstanding the provisions of Sub-rule (1), where the duration of the project or construction work exceeds one year, cess shall be paid within thirty days of completion of one year from the date of commencement of work and every 1 Notification No G.S.R 149(E), dated 26th March, 1998. Published in Gazette of India, Extra Part II, Sec. 3(i) dated 26th March 1998.

146 The Building & other Construction Workers‘ Welfare Cess Rules, 1998 Rule 5 year thereafter at the notified rates on the cost of construction incurred during the relevant period.

(3) Notwithstanding the provisions of Sub-rule (1) and Sub-rule (2), where the levy of cess pertains to building and other contraction work of a Government or of a Public Sector Undertaking, such Government or the Public Sector Undertaking shall deduct or cause to be deducted the cess payable at the notified rates from the bills paid for such works.

(4) Notwithstanding the provisions of Sub-rule (1) and Sub-rule (2), where the approval of a construction work by a local authority is required, every application for such approval shall be accompanied by a crossed demand draft in favour of the Board and payable at the station at which the Board is located for an amount of cess payable at the notified rates from the estimated cost of construction:

Provided that if the duration of the project is likely to exceed one year, the demand draft may be for the amount of cess payable on cost of construction estimated to be incurred during one year from the date of commencement and further payment of cess due shall be made as per the provisions of Sub-rule (2).

(5) An employer may pay in advance an amount of cess calculated on the basis of the estimated cost of construction along with the notice of commencement of work under Sec. 46 of the Main Act by a crossed demand draft in favour of the Board and payable at the station at which the Board is located:

Provided that if the duration of the project is likely to exceed one year, the demand draft may be for the amount of cess payable on cost of construction estimated to be incurred during one year from the date of such commencement and further payment of cess due shall be made as per the provisions of Sub-rule

(2).

(6) Advance cess paid under Sub-rules (3), (4) and (5), shall be adjusted in the final assessment made by the Assessing Officer.

Where this provision sits

ActThe Building & Other Construction Workers’ Welfare Cess Rules, 1998
Section4
Marginal noteTime and manner of collection
JurisdictionUnion territory of Chandigarh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Building & Other Construction Workers’ Welfare Cess Rules, 1998 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.