Section 14: Method of determining compensation.

The Coal Bearing Areas (Acquisition and Development) Act, 1957Central Act · Act 20 of 1957

(1) Where the amount of any compensation payable under this Act can be fixed by agreement, it shall be paid in accordance with such agreement.

(2) Where no such agreement can be reached, the Central Government shall constitute a Tribunal consisting of a person who is or has been or is qualified to be a Judge of a High Court for the purpose of determining the amount.

(3) The Central Government may in any particular case nominate a person having expert knowledge in mining to assist the Tribunal, and where such nomination is made, the person or persons interested may also nominate any other person for the same purpose.

(4) At the commencement of the proceedings before the Tribunal the Central Government and the person interested shall state what in their respective opinions is a fair amount of compensation.

(5) The Tribunal shall after hearing the dispute, make an award determining the amount of compensation which appears to it to be just, and specify the person or persons to whom the compensation shall be paid; and in making the award the Tribunal shall have regard to the circumstances of each case and to the foregoing provisions of this Act with respect to the manner in which the amount of compensation shall be determined in so far as the said provisions or any of them may be applicable.

(6) Where there is a dispute as to the person or persons entitled to compensation and the Tribunal finds that more persons than one are entitled to compensation, it shall apportion the amount thereof among such persons and in such manner as it thinks fit.

(7) Nothing in the Arbitration Act, 1940 (10 of 1940), shall apply to any proceedings under this section.

[(8) The Tribunal, in the proceedings before it, shall have all the powers which a civil court has while trying a suit under the Code of Civil Procedure, 1908 (5 of 1908), in respect of the following matters, namely:--

(i) summoning and enforcing the attendance of any person and examining him on oath;

(ii) requiring the discovery and production of any document;

(iii) reception of evidence on affidavits;

(iv) requisitioning any public record from any court or office; and

(v) issuing commissions for examination of witnesses.]

Where this provision sits

ActThe Coal Bearing Areas (Acquisition and Development) Act, 1957
Section14
Marginal noteMethod of determining compensation.
JurisdictionCentral
StatusIn force as published by the source

How this provision has been amended

Taken from the footnotes printed with the provision by the source. Where a footnote names the amending instrument, it is quoted as printed.

  • inserted. . Ins. by s. 5, ibid. (w.e.f. 11-12-1971).

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Coal Bearing Areas (Acquisition and Development) Act, 1957 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.