CourtMesh

Section 18: Capacity Determination

Companies (cost records and audit) Amendment Rules, 2017.Central Rules · 2013

(a) Capacity shall be determined in terms of units of production or services or equivalent machine or man hours.

(b) Installed capacity is determined based oni) Manufacturers' technical specifications;

ii) Capacities of individual or interrelated production centres;

iii) Operational constraints or capacity of critical machines; or iv) Number of shifts

(c) In case manufacturers' technical specifications are not available, the estimates by technical experts on capacity under ideal conditions shall be considered for determination of installed capacity. In case any production facility is added or discarded the installed capacity shall be reassessed from the date of such addition or discard. ln case the same is reassessed as per direction of the Government, it shall be in accordance with the principles laid down in the said directives. In case of improvement in the production process, the installed capacity shall be reassessed from the date of such improvement.

(d) Normal capacity shall be determined vis-a-vis installed capacity after carrying out adjustments for:

i) Holidays, normal shut down days and normal idle time;

O ii) Normal time lost in batch change over;

iii) Time lost due to preventive maintenance and normal break downs of equipments;

iv) Loss in efficiency due to ageing of the equipment; or v) Number of shifts

(e) Capacity utilisation is the actual production measured as a per cent. of installed capacity.

19. Work-in-Progress and Finished Stock,- The method followed for determining the cost of work-in-progress and finished stock of the goods and for services under delivery or in-process shall be appropriate and shall be indicated in the cost records so as to reveal the cost element that have been taken into account in such computation. All conversion costs incurred in bringing the inventories to their present location and condition shall be taken into account white computing the cost of work-in-progress and finished stock. The method adopted for determining the cost of work-in progress and finished goods shall be followed consistently.

Where this provision sits

ActCompanies (cost records and audit) Amendment Rules, 2017.
Section18
Marginal noteCapacity Determination
JurisdictionCentral
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Companies (cost records and audit) Amendment Rules, 2017. is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.