Section 12: Substitution of regulation for regulation 20.1 of Principal Regulations For regulation 20.1 of Principal Regulations, the following regulations shall be substituted, namely
CSERC Regulations may be called Chhattisgarh State Electricity Regulatory Commission (Grid Interactive.State Regulations of Chhattisgarh · 2003
20.1 In case of IDRES, the Interconnection Point shall mean a point on the network of the licensee, including a sub-station or a switchyard, where the interconnection is established between the IDRES and the Licensee's system and where electricity injected into the Licensee' s system can be measured unambiguously.
Provided that, the Interconnection Point shall be as per CEA (Installation and Operation of Meters), Regulations, 2006 and subsequent amendments thereof.
Substitution of regulation for regulation 20.1 of Principal Regulations For regulation 20.1 of Principal Regulations, the following regulations shall be substituted, namely
Jurisdiction
State of Chhattisgarh
Status
In force as published by the source
Find the provision, not just read it
The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:
Search 49,000+ Central and State enactments by what a provision says, not by its number
Jump from any section to every judgment that has applied it
Search 300 million+ Indian court records alongside the statute
Ask a research agent to find and read the case law on a provision for you
Need this as data, not as a page? CSERC Regulations may be called Chhattisgarh State Electricity Regulatory Commission (Gri… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.