(1) Before initial filling of any reservoir of a specified dam, the agency responsible for its design shall draw the filling criteria and prepare an initial filling plan, with adequate time for monitoring and evaluating the performance of the dam and its appurtenant structures.

(2) Before initial filling of the reservoir is taken up, the State Dam Safety Organisation shall inspect or cause to be inspected the specified dam either through its own engineers or by an independent panel of experts, who shall also examine the initial filling programme and prepare a detailed report thereof duly certifying the fitness of dam for filling.

Where this provision sits

ActThe Dam Safety Act, 2021
Section27
Marginal noteInitial filling of reservoirs.
JurisdictionCentral
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Dam Safety Act, 2021 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.