CourtMesh

Section 38: Central Transmission Utility and functions.

The Electricity Act, 2003Central Act · Act 36 of 2003

(1) The Central Government may notify any Government company as the Central Transmission Utility:

Provided that the Central Transmission Utility shall not engage in the business of generation of electricity or trading in electricity:

Provided further that the Central Government may transfer, and vest any property, interest in property, rights and liabilities connected with, and personnel involved in transmission of electricity of such Central Transmission Utility, to a company or companies to be incorporated under the Companies Act, 1956 (1 of 1956) to function as a transmission licensee, through a transfer scheme to be effected in the manner specified under Part XIII and such company or companies shall be deemed to be transmission licensees under this Act.

(2) The functions of the Central Transmission Utility shall be--

(a) to undertake transmission of electricity through inter-State transmission system;

(b) to discharge all functions of planning and co-ordination relating to inter-State transmission system with--

(i) State Transmission Utilities;

(ii) Central Government;

(iii) State Governments;

(iv) generating companies;

(v) Regional Power Committees;

(vi) Authority;

(vii) licensees;

(viii) any other person notified by the Central Government in this behalf;

(c) to ensure development of an efficient, co-ordinated and economical system of inter-State transmission lines for smooth flow of electricity from generating stations to the load centres;

(d) to provide non-discriminatory open access to its transmission system for use by--

(i) any licensee or generating company on payment of the transmission charges; or

(ii) any consumer as and when such open access is provided by the State Commission under sub-section (2) of section 42, on payment of the transmission charges and a surcharge thereon, as may be specified by the Central Commission:

Provided that such surcharge shall be utilised for the purpose of meeting the requirement of current level cross-subsidy:

Provided further that such surcharge and cross subsidies shall be progressively reduced *** in the manner as may be specified by the Central Commission:

* * * * *

Provided also that the manner of payment and utilisation of the surcharge shall be specified by the Central Commission:

Provided also that such surcharge shall not be leviable in case open access is provided to a person who has established a captive generating plant for carrying the electricity to the destination of his own use.

Where this provision sits

ActThe Electricity Act, 2003
Section38
Marginal noteCentral Transmission Utility and functions.
JurisdictionCentral
StatusIn force as published by the source
Judgments citing it4

How this provision has been amended

Taken from the footnotes printed with the provision by the source. Where a footnote names the amending instrument, it is quoted as printed.

  • omitted, Act 26 of 2007. . The words "and eliminated" omitted by Act 26 of 2007, s. 4 (w.e.f. 15-6-2007).
  • omitted. . The third proviso omitted by s. 4, ibid. (w.e.f. 15-6-2007)

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Electricity Act, 2003 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.