CourtMesh

Section 69: Notice to telegraph authority.

The Electricity Act, 2003Central Act · Act 36 of 2003

(1) A licensee shall, before laying down or placing, within ten meters of any telegraph line, electric line, electrical plant or other works, not being either service lines, or electric lines or electrical plant, for the repair, renewal or amendment of existing works of which the character or position is not to be altered,--

(a) submit a proposal in case of a new installation to an authority to be designated by the Central Government and such authority shall take a decision on the proposal within thirty days;

(b) give not less than ten days' notice in writing to the telegraph authority in case of repair, renewal or amendment of existing works, specifying--

(i) the course of the works or alterations proposed;

(ii) the manner in which the works are to be utilised;

(iii) the amount and nature of the electricity to be transmitted;

(iv) the extent to, and the manner in which (if at all), earth returns are to be used,

and the licensee shall conform to such reasonable requirements, either general or special, as may be laid down by the telegraph authority within that period for preventing any telegraph line from being injuriously affected by such works or alterations:

Provided that in case of emergency (which shall be stated by the licensee in writing to the telegraph authority) arising from defects in any of the electric lines or electrical plant or other works of the licensee, the licensee shall be required to give only such notice as may be possible after the necessity for the proposed new works or alterations has arisen.

(2) Where the works of the laying or placing of any service line is to be executed, the licensee shall, not less than forty-eight hours before commencing the work, serve upon the telegraph authority a notice in writing of his intention to execute such works.

Where this provision sits

ActThe Electricity Act, 2003
Section69
Marginal noteNotice to telegraph authority.
JurisdictionCentral
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Electricity Act, 2003 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.