(1) No land within Gandhidham shall be used for the purposes of a charcoalkiln, pottery-kiln or time-kiln, and no land within Gandhidham shall be used for the purposes of a brick-field or brick-kiln except in accordance with the directions issued under clause (j) of sub-section (2) of section 6 and under and in accordance with the conditions of, a licence from the authority, which may be renewed annually.
(2) Every person desiring to obtain or renew a licence under sub-section (1) shall make an application to the Authority in such form and containing such information as may be prescribed.
(3) On receipt of an application under sub-section (2), the Authority after making such inquiry as it considers necessary in relation to any direction issued under section 6 or in relation to any other matter, shall, by order in writing, either grant the licence subject to such conditions in respect thereof and on payment of such fee as may be prescribed, or refuse the licence.
(4) Where the licence is refused, the grounds of such refusal shall be communicated to the applicant in the prescribed manner.
10. No compensation shall be claimed by any person for damage or loss sustained or alleged to have been sustained by him in consequence of— Control of development and building operations in Gandhidham.
Application for permission.
Prohibition of use of any land as brickfield, etc., without licence.
Bar of compensation [1958 : Bom. XIX Gandhidham (Development and Control on Erection of Buildings) Act, 1957
(a) any order made by the Authority under sub-section (2) of section 8 or subsection (3) of section 9 ; or
(b) anything which is in good faith done or intended to be done under this Act.
11. The Authority may authorise any person to enter into or upon any site of building with or without assistants or workmen, for the purpose of—
(a) making any inquiry, inspection, measurement or survey, or taking levels of such site or building ;
(b) examining works under construction or ascertaining the course of sewers or drains ;
(c) ascertaining whether any site is being or has been developed, or any building is being or has been erected, in contravention of any direction issued under section 6 or without the permission referred to in section 7 or in contravention of any condition subject to which such permission has been granted ; or
(d) ascertaining whether any land is being or has been used for the purposes of a charcoal-kiln, pottery-kiln or lime-kiln without a licence or in contravention of any condition subject to which such licence has been granted:
Provided that no entry shall be made except between the hours of sunrise and sun-set and without giving not less than twenty-four hours written notice to the occupier, or if there be no occupier, to the owner of the building or land.