(1) Save as otherwise provided in section 13, the Executing Officer shall, on the completion of part of any work to be carried out, under a scheme prepare an interim statement specifying therein-

(i) the part of the work carried out;

(ii) the cost of such part calculated on the basis of the works cost as recorded in the works register maintained by the Executing Officer;

(iii) the interim amount to be recovered from the owner in respect of the work so carried out;

(iv) the period within which such amount is to be recovered;

(v) the general rate per acre or per rupee of assessment, per annum at which such amount is to be recovered from the owners;

(vi) if in the case of any survey numbers or sub-divisions of survey numbers, the amount to be recovered under clause (iii) is to be recovered at a rate other than the general rate, such rate;

(vii) the names of the persons from whom such amount is recoverable;

(viii) such other particulars as may be prescribed.

Statement. Bom. XXX of 1958.

Executing Officer to prepare recovery statements and entries to be made in Record of Rights, etc.

Gujarat Land Improvement Schemes Act, 1942.

10 of 18

(2) After the whole of the work under such scheme is carried out the Executing Officer shall prepare-

(a) the final statement specifying therein-

(i) the work carried out;

(ii) the total cost of the whole work;

(iii) the balance after deducting from the total cost the interim amount set out in the interim statement 88[including the rate of interest and the amount to be recovered at such rate and any matter incidental thereto;]

(iv) in relation to such balance, the balance amount to be recovered from the owners as cost or part cost;

(v) the period within which such amount is to be recovered;

(vi) the names of persons from whom such amount is recoverable;

(vii) the general rate per acre or per rupee of assessment, per annum at which the amount specified under clause (iv) should be recovered;

(viii) if in the case of any survey number or sub-division of a survey number the amount recoverable from the owner thereof is to be recovered at a rate other than the general rate, such rate and a list of all such survey numbers or sub-divisions;

(ix) the work which, in his opinion, shall be maintained and repaired individually or jointly and the names of such persons ;

(x) such other particulars as may be prescribed ;

(b) a map showing the work carried out in the village.

(3) The rights and liabilities shown in the interim statement and the final statement shall be entered in the Record of Rights or where there is no Record of Rights in the prescribed village record and in the village accounts in such manner as the State Government may prescribe and shall thereupon form part of such record of rights or as the case may be, the village record and of the village accounts.]

Where this provision sits

ActThe Gujarat Land Improvement Schemes Act, 1942
Section13A
JurisdictionState of Gujarat
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Gujarat Land Improvement Schemes Act, 1942 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.