(1) Where mining operations have been undertaken before the commencement of these rules without an approved mining plan, the holder of such mining lease shall submit a mining plan within a period of one year from the date of commencement of these rules, 5 [ to the Regional Controller or the authorised officer or the officer authorised in this behalf by the State Government, as the case may be, for approval.]

(2) If a holder of a mining lease has not been able to submit the mining plan within the specified time for reasons beyond his control, he may apply for extension of time giving reasons to the following authorities :

______________________________________________________________________________

1. Inserted by G.S.R. 55 (E), dated 17.1.2000. 2. Ibid. 3. Ibid.

4. Substituted by G.S.R. 22 (E), dated 11.1.2002. 5. Substituted by G.S.R. 55 (E), dated 17.1.2000.

9

(a) to the Regional Controller for extension of time up to six months;

(b) to the Controller of Mines for extension of time exceeding six months but not exceeding one year;

(c) to the Chief Controller of Mines for extension of time beyond one year;

1 [(d) to the officer authorised in this behalf by the State Government in respect of mining plan approved by the State Government.]

2 [(3) The Regional Controller, Controller of Mines, the Chief Controller of Mines or the authorised officer or the officer authorised in this behalf by the State Government, as the case may be, on receiving an application made under sub-rule (2) may, on being satisfied, extend the period for submission of the mining plan for the period mentioned in clause (a), (b), (c) or (d) of the said sub-rule.]

(4) The Regional Controller 3 [or the officer authorised in this behalf by the State Government, as the case may be,] may approve the plan as submitted by the lessee under subrule (1) or may require modifications to be carried out in the plan and the lessee shall carry out such modifications and resubmit the modified plan for 4 [omitted.] approval.

5 [(5) The Regional Controller or the officer authorised in this behalf by the State Government, as the case may be, shall, within a period of 90 days from the date of receipt of the mining plan or the modified mining plan, convey approval or disapproval to the applicant and in case of disapproval shall also convey the reasons for disapproving the said mining plan or the modified mining plan.]

(6) If no decision is conveyed within the period stipulated under sub-rule (5), the mining plan or the modified mining plan, as the case may be, shall be deemed to have been provisionally approved and such approval shall be subject to the final decision whenever communicated.

(7) The mining plan submitted under sub-rule (1) shall be prepared by a recognised person.

Where this provision sits

ActMineral Conservation and Development Rules, 1988
Section11
Marginal noteMining plan to be submitted by the existing lessee
JurisdictionState of Haryana
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Mineral Conservation and Development Rules, 1988 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.