Section 3B: Modification of scheme of reconnaissance
Mineral Conservation and Development Rules, 1988State Rules of Haryana · 1992
(1) A reconnaissance scheme prepared and submitted under rule 3A may be modified at any time on geological considerations by the holder of a reconnaissance permit during continuance of the reconnaissance permit.
(2) Any modification carried out under sub-rule (1) shall be intimated to the Controller General and the Regional Controller or the authorised officer by the holder of reconnaissance permit within a period of fifteen days.