Section 8: Cessation of powers given by an order
The Himachal Pradesh Aerial Ropeways Act, 1968State Act of Himachal Pradesh · Act 7 of 1969
If a promoter authorised by an order to construct an aerial ropeway does not, within the time specified in the order,-
(a) succeed in raising the full amount of capital required for the completion of the aerial ropeway;
(b) make, in the opinion of the State Government, substantial progress with the construction of the aerial ropeway; or
(c) complete the construction thereof;
the powers given to the promoter by such order shall, unless the State Government prolongs the time so specified, cease to be exercised
Where this provision sits
Find the provision, not just read it
The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:
- Search 49,000+ Central and State enactments by what a provision says, not by its number
- Jump from any section to every judgment that has applied it
- Search 300 million+ Indian court records alongside the statute
- Ask a research agent to find and read the case law on a provision for you
Free account. No card. About a minute to create.
Create a free account