Section 10: Implementation of DSM programme

The Himachal Pradesh Electricity Regulatory Commission (Demand Side Management) Regulations, 2011State Regulations of Himachal Pradesh · 2003

(1) The licensee shall prepare, plan and undertake implementation of annual DSM programme in line with the implementation guidelines as may be issued by the Commission from time to time

(2) The licensee shall carry out implementation of activities assigned to it either by itself or through engagement of appropriate independent entity. While doing so, the licensee shall ensure that continuity and consistency is maintained and interest of the licensee or that of the consumers is not compromised.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Demand Side Management) Regulations, 2011
Section10
Marginal noteImplementation of DSM programme
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Demand Side Management) Regulatio… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.