The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Relate…State Regulations of Himachal Pradesh · 2003
The application for grant of connectivity or long-term open access or medium-term open access shall be made to the nodal agency :
Provided that an application for connectivity is not required to be made by any transmission/distribution licensee, since transmission/distribution system planning is carried out in co-ordinated manner by the State Transmission Utility and the Central Electricity Authority:
Provided; further that the transmission licensee other than the State Transmission Utility, the distribution licensee, nevertheless shall sign a connection agreement with the State Transmission Utility or the intra-State transmission licensee as provided for in subregulation (5) of regulation 8 of these regulations.
Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.