Section 9: Criteria for long-term and medium-term open access
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Relate…State Regulations of Himachal Pradesh · 2003
(1) Before awarding longterm access, the nodal agency shall have due regard to the augmentation of intra-State transmission/distribution system in accordance with the perspective transmission/ distribution plans developed by the State Transmission Utility/ licensee.
(2) Medium-term open access shall be granted if the resultant power flow can be accommodated in the existing transmission/distribution system or the transmission/ distribution system under execution:
Provided that no augmentation shall be carried out to the transmission/distribution system for the sole purpose of granting medium-term open access:
Provided further that construction of dedicated transmission/distribution line shall not be construed as augmentation of the transmission/distribution system for the purpose of this regulation.
Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.