CourtMesh

Section 6: Appraisal Committee

The Himachal Pradesh Electricity Regulatory Commission (Power System Development Fund) Regulations, 2020State Regulations of Himachal Pradesh · 2003

(1) The Commission may constitute an Appraisal Committee under the chairmanship of the Executive Director (Technical) of the Commission with General Manager (Projects), State Transmission Utility, Chief Engineer (System Planning) of Distribution Licensee, Sr. Accounts Officer of the Commission, as its members and the Superintending Engineer (HPSLDC) as its Member Secretary:

Provided that the Commission may nominate any other person not below the rank of Superintending Engineer as a Member of the Committee.

(2) (a) The Appraisal Committee shall carry out the techno-economic appraisal of the proposals submitted to it by the Nodal Agency, under clause (ii)(b) of sub-regulation 2 of regulation 5, keeping in view, the eligibility criteria as per regulation 3 of these regulations and shall finalize its findings/ recommendations on each scheme submitted to it. The schemes received by the Nodal Agency from the concerned Project Entity in a quarter shall be considered simultaneously;

Compendium of HPERC Regulations, March 2021 5

(b) The Member Secretary of the Appraisal Committee shall duly compile and process the recommendations of the Appraisal Committee and shall expedite the submission of the self-contained proposals by the nodal agency to the Commission in accordance with clause (iii) of sub-regulation 2 of regulation 5; and

(c) any other functions as may be specifically assigned to it by the Commission or Monitoring Committee or which may otherwise be required to discharge by it for smooth implementation of its role under these regulations.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Power System Development Fund) Regulations, 2020
Section6
Marginal noteAppraisal Committee
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Power System Development Fund) Re… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.