Section 11: Tariff design

The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions…State Regulations of Himachal Pradesh · 2003

(1) The single part levellised tariff structure shall be followed for the renewable energy technologies:

Provided that for renewable energy technologies having fuel cost component, like biomass power projects and non-fossil fuel based cogeneration, single part tariff with two components, i.e. fixed cost component and fuel cost component, shall be determined.

(2) The following fixed cost components shall be included for determining the tariff:-

(a) Return on equity;

(b) Interest on loan capital;

(c) Depreciation;

(d) Interest on working capital; and

(e) Operation and maintenance expenses.

(3) The generic or project specific tariff shall be determined on levellised basis for the tariff period:

Provided that tariff for renewable energy technologies, having single part tariff with two components, referred to in the proviso to sub-regulation (1), shall be determined on 1 Ins. vide Not. No. HPERC/428 dated 31 st March, 2017 published in the R.H.P. dated 6 th April, 2017 at p. 235-237.

2 Add. proviso the word “further” vide Not. No. HPERC/428 dated 31 st March, 2017 published in the R.H.P. dated 6 th April, 2017at p. 83-85.

12 Compendium of HPERC Regulations, March 2021 levellised basis for the tariff period in respect of the fixed cost component and the fuel cost component shall be specified on year of operation basis.

(4) For the purpose of levellised tariff computation, the discount factor equivalent to the post tax weighted average cost of capital shall be considered.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012
Section11
Marginal noteTariff design
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.