The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions…State Regulations of Himachal Pradesh · 2003
(1) The due date for payment of bills shall be 60 days from the date of billing.
(2) For payment of bills of the renewable energy generator through letter of credit, a rebate of 2% shall be allowed.
(3) Where payments are made other than through letter of credit within a period of one month of presentation of bills by the renewable energy generator, a rebate of 1% shall be allowed.
Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.