The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions…State Regulations of Himachal Pradesh · 2003
Mechanism for grid connectivity shall be as under-
(a) the renewable energy generator shall construct, operate and maintain the project line(s) at his cost;
(b) the licensee shall, at the cost of renewable energy generator, provide, operate and maintain the interconnection facilities;
(c) the transmission licensee and/or the distribution licensee shall bear the cost of augmentation/establishment of network beyond the inter-connection point under the CAPEX PLAN and the new or the augmented network shall form part of the assets of the transmission or the distribution licensee, as the case may be.
Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.