Section 11: Operational Norms

The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011State Regulations of Himachal Pradesh · 2003

Normative Annual Transmission System Availability Factor (NATAF): The target availability for recovery of full transmission charges during the control period shall be as under: -

(a) the alternating current (AC) System: 98%

(b) the high voltage direct current (HVDC) bi-pole links: 92%

(c) the high voltage direct current (HVDC) back-to-back stations: 95%.

PART-III PRINCIPLES FOR DETERMINATION OF AGGREGATE REVENUE REQUIREMENT (ARR)

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011
Section11
Marginal noteOperational Norms
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determin… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.