Section 14: Renovation and Modernisation

The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011State Regulations of Himachal Pradesh · 2003

(1) The generating company for meeting the expenditure on renovation and modernization for the purpose of extension of life beyond the useful life of the generating station or a unit thereof shall make an application before the Commission for approval of the proposal with a Detailed Project Report giving 1 Sub. vide Not. No. HPERC-F(1)-2/2018 dated 22 nd November, 2018 published in the R.H.P. 27 th November, 2018 at p. 6249-6255. Before its substitution it read as under:

“(2) The capital expenditure incurred on the following counts after the cut off date may, in its discretion, be admitted by the Commission, subject to prudence check,:-

(a) liabilities to meet award of arbitration or for compliance of the order or decree of a court;

(b) change in law;

(c) any expenditure which has become necessary on account of damage caused by natural calamities (but not due to flooding of power house attributable to the negligence of the generating company) including due to geological reasons after adjusting for proceeds from any insurance scheme, and expenditure incurred due to any additional work which has become necessary for successful and efficient plant operation:

Provided that in any expenditure on acquiring the minor items or the assets like tools and tackles, furniture, airconditioners, voltage stabilizers, refrigerators, coolers, fans, washing machines, heat convectors, mattresses, carpets etc.

brought after the cut-off date shall not be considered for additional capitalisation for determination of tariff w.e.f.

01.04.2011.” 14 Compendium of HPERC Regulations, March 2021 complete scope, justification, cost-benefit analysis, estimated life extension from a reference date, financial package, phasing of expenditure, schedule of completion, reference price level, estimated completion cost including foreign exchange component, if any, record of consultation with beneficiaries and any other information considered to be relevant by the generating company.

(2) Where the generating company makes an application for approval of its proposal for renovation and modernisation, the approval shall be granted after due consideration of reasonableness of the cost estimates, financing plan, schedule of completion, interest during construction, use of efficient technology, cost-benefit analysis, and such other factors as may be considered relevant by the Commission.

(3) Any expenditure incurred or projected to be incurred and admitted by the Commission after prudence check based on the estimates of renovation and modernisation expenditure and life extension, and after deducting the accumulated depreciation already recovered from the original project cost, shall form the basis for determination of tariff:

1 [Provided that variations in capital cost of such Renovation and Modernization works on account of cost overruns beyond the value at which the works and/ or supplier are awarded to EPC contractors/ Suppliers, 100% of the variation shall be considered as part of the capital cost of the project if such can be attributed to a force majeure event or any other reason beyond the control of the generator and if such cannot be attributed to any reason beyond the control of the generator, then 50% of variation shall be considered as part of the capital cost of the project.]

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011
Section14
Marginal noteRenovation and Modernisation
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determin… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.