CourtMesh

Section 25: Annual Fixed Cost

The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011State Regulations of Himachal Pradesh · 2003

The annual fixed cost (AFC) of a generating station shall consist of the following components:-

(a) Return on equity;

(b) Interest on loan capital;

(c) Depreciation;

(d) Interest on working capital;

(e) Operation and maintenance expenses.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011
Section25
Marginal noteAnnual Fixed Cost
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determin… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.