The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011State Regulations of Himachal Pradesh · 2003
(1) The baseline values (operating and cost parameters) for the control period shall be determined by the Commission, based on previously approved values, the latest audited accounts, estimate of the actuals for the relevant year, prudence check and other factors considered appropriate by the Commission.
(2) The Commission shall normally not revisit the performance targets even if the targets are fixed on the basis of un-audited accounts.
Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determin… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.