Each State Load Despatch Centre shall post following information on their websites in a so separate web page titled "Open access information"
(i) Floor rate of rupees per MW per day for the short-term customers {ST _RATE) for each system of the State Transmission Utility or the State Electricity Board or any other transmission/distribution licensee with details calculations in support of such rate in respect of all the transmission/distribution licensees situated within the State.
(ii) A status report on the current short-term customers indicating:
(a) Name of customers;
(b) Period of the access granted.(start date and end date);
(c) Point(s) of Injection;
(d) Point(s) of drawal;
(e) Transmission system/distribution system used (in terms of region and ownership;
(f) Reserved capacity; and
(g) Applicable rate (Rs. per MW per day).
Note.-The status report shall be updated upon every change in status.
(iii) Month-wise and year-wise on past short-terms customers indicating:
(a) Name of.the customers;
(b) Period of the access granted (start date and end date);
(c) Point(s) of injection;
S. No. Phases Contracted electrical Date from which Open Access power. shall be allowed to open access customers 1 Phase I 25 MW and more November 1, 2005 2 Phase! 10 MW or more April 1, 2006 3 Phase II 1 MW or more April 1, 2008
(iv) The collection and disbursement of the unscheduled Inter-change charges and the reactive energy charges shall be governed In accordance with the procedure and methodology specified by the Commission from time to time.