Section 12: For Schedule II appended to the principal Rules, the following Schedule shall be substituted, namely

Maharashtra Factories (Safety Audit) (Amendment ) Rules, 2024State Rules of Maharashtra · 1948

Schedule II [See rules 8 and 9(1)] Proforma for Safety Audit Report Part-A (to be furnished by the Safety Auditor)

(1) Name and address of the factory:

(2) Name of the Occupier:

(3) (a) Date and time of opening meeting of safety audit:

(b) Date and time of closing meeting of safety audit:

(c) Total man days taken to conduct the safety audit:

(4) List of raw material with maximum storage quantity and its mode of storage:

(5) List of finished products with maximum storage quantity and its mode of storage:

(6) Manufacturing process flow chart (attach separate sheet):

(7) List of dangerous operations carried out in the factory as defined in rule 114 of the Maharashtra Factories Rules, 1963 :

(8) (a) Name/s of the Safety Auditor/s:

(b) Certificate no. and it’s validity duration:

भााग एक-ल-६६–३अ 16 महाारााष्ट्र शाासन रााजपत्र असााधाारण भााग एक-ल, जूून १९, २०२४/ज्येेष्ठ २९, शकेे १९४६

(9) Whether enclosed Safety Audit Report is as per the Indian Standard, IS 14489 : Code of Practice on Occupational Safety and Health Audit, or any such standards prevailing at the relevant time, whichever is latest : (mention standards, check list, guidelines used in addition to the Indian Standard, IS 14489 : Code of Practice on Occupational Safety and Health Audit) (Detailed Safety Audit Report along with recommendations to be attached.)

Date of submission of Safety Audit Report to the factory:

Digital Signature of Safety Auditor/s or employee/s of an Institution authorized to carry out safety audit.

In case of Internal Safety Audit Signatures of Team of Plant Personnel.

Part-B (to be furnished by the occupier) Date of receipt of safety audit from the Safety Auditor:

I ………………………………… undersigned occupier of the factory …………………………………….

situated at .................................... hereby declare that, I have thoroughly reviewed and taken appropriate actions based on the findings and recommendations mentioned in Safety Audit Report by safety auditor/s namely ………………………..

In response to the Safety Audit Report I have taken appropriate measures and report of the same is attached herewith.

Digital Signature of the Occupier.

महाारााष्ट्र शाासन रााजपत्र असााधाारण भााग एक-ल, जूून १९, २०२४/ज्येेष्ठ २९, शकेे १९४६ 17 Schedule III [See rule 9(2)] Proforma for verification of action taken report

(1) Name and address of the factory :

(2) Name of the Occupier :

(3) Name of Safety Auditor :

(4) Date of Safety Audit :

(5) Date of submission of Safety Audit report to Occupier :

(6) Date of action taken report submitted by Occupier :

(7) Date of visit for verifying action taken report :

(8) Details of non-compliance observed, if any:

I ……………., hereby declare that I have verified all the observation / recommendation mentioned in Safety Audit report and action taken report submitted by the occupier of the factory.

Digital signature of the Safety Auditor.”.

13. In Form A appended to the principal Rules,—

(1) in entry at serial number (5), the word “Fax” shall be deleted;

(2) in entry at serial number (6) the word “Diploma” shall be deleted;

(3) in entry at serial number (7) the word “Diploma” shall be deleted;

(4) after entry at serial number (9), the following entries shall be inserted, namely :— “(10) Details of the training attended (attach copies).

Sr. No. Name of the Institution Subject / Topics of the training Duration From To

(11) Details of Payment of fees for application :

Challan No./ Reference No. Amount Date”.

(6) in the DECLARATION, for clause (c) the following clause shall be substituted, namely :— “(c) The list showing the name, address of the factory and date of audits are attached herewith.”.

14. In Form B appended to the principal Rules,—

(1) in entry at serial number (3), sub-entry (d) shall be deleted;

(2) in entry at serial number (5), for the words “bio-data” the word “details ” shall be substituted;

18 महाारााष्ट्र शाासन रााजपत्र असााधाारण भााग एक-ल, जूून १९, २०२४/ज्येेष्ठ २९, शकेे १९४६

(3) after entry at serial number (7) the following entry shall be inserted, namely :— “(8) Challan No./ Reference No. Amount Date”;

(4) in the DECLARATION,—

(i) for clause (c), the following clause shall be substituted, namely :— “(c) The list showing the name, address of the factory and date of audits are attached herewith.”;

(ii) in clause (d), for the words “bio-data it” the word “details” shall be substituted ;

(5) in Annexure,—

(i) in entry at serial number (5), the word “Fax” shall be deleted ;

(ii) in entry at serial (6), the word “Diploma” shall be deleted ;

(iii) in entry at serial (7), the word “Diploma” shall be deleted ;

(iv) after entry at serial number (8), the following entry shall be added, namely :— “9. Details of the training attended (attached copies).

Sr. No. Name of the Institution Subject / Topics of the training Duration From To”.

Where this provision sits

ActMaharashtra Factories (Safety Audit) (Amendment ) Rules, 2024
Section12
Marginal noteFor Schedule II appended to the principal Rules, the following Schedule shall be substituted, namely
JurisdictionState of Maharashtra
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Maharashtra Factories (Safety Audit) (Amendment ) Rules, 2024 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.