The Chairperson, when sanctioning the erection of a building or execution of a work, shall specify a reasonable period after the commencement of the building or work within which the building or work is to be completed and if the building or work is not completed within the period so specified, it shall not be continued thereafter without fresh sanction obtained in the manner hereinbefore provided, unless the Chairperson on application made therefor has allowed an extension of that period.
Section 246: Period for completion of building or work.
The New Delhi Municipal Council Act, 1994Central Act · Act 44 of 1994
Where this provision sits
| Act | The New Delhi Municipal Council Act, 1994 |
|---|---|
| Section | 246 |
| Marginal note | Period for completion of building or work. |
| Jurisdiction | Central |
| Status | In force as published by the source |
Find the provision, not just read it
The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:
- Search 49,000+ Central and State enactments by what a provision says, not by its number
- Jump from any section to every judgment that has applied it
- Search 300 million+ Indian court records alongside the statute
- Ask a research agent to find and read the case law on a provision for you
Free account. No card. About a minute to create.
Create a free accountNeed this as data, not as a page? The New Delhi Municipal Council Act, 1994 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.