(1) If any grant is made for purposcs of agriculture and the grantee is also allowed a site in the abadisite of the chak or village for constructing a building for residential purposes, the grantce shall be and remain bound by the following obligation and shall be deemed to have entered into a covenant for their due performance and observance:— To commence the construction of the building within six months from the date of the grant in accordance with a standard plan or modifications of that plan approved by the Collector.
To complete the building to the satisfaction of the Collector within eightecn months of the date of grant.
(c) To maintain the building thereafter in good repair in accordance
(d) (e} U] with any directions from time to time issued by the Collector.
Not to let the building on rent or use it for any purposc other than that for residential purposes or gencrally subservient thereto, and not to permit or suffer such usage, without the permission of the Collector.
Not lo make any excavation on the land, village streets and lanes or open areas adjoining thereto or permit or suffer any excavation to be made.
Not to sow on the land any crop which are prohibited by the Collector or permit or suffer any such crops to be sown.
(2) This condition shall not apply to grant of land for residential purposes to any person who has not been granted, any land for agricultural purposes also and such persons shall be governed by separate statement of conditions sanctioned for them.
626 THE RAJ. COL. (GENERAL COLONY) CONDITIONS, 1955 Con. 22 PENALTIES FOR BREACH OF CONDITIONS