Section 22: Time frame for implementation

Solid Waste Management Rules 2016Central Rules · 1986

Necessary infrastructure for implementation of these rules shall be created by the local bodies and other concerned authorities, as the case may be, on their own, by directly or engaging agencies within the time frame specified below:

Sl. No. Activity Time limit from the date of notification of rules

(1) (2) (3)

1. identification of suitable sites for setting up solid waste processing facilities 1 year ¹Hkkx IIµ[k.M 3(ii)º Hkkjr dk jkti=k % vlk/kj.k 63

2. identification of suitable sites for setting up common regional sanitary landfill facilities for suitable clusters of local authorities under 0.5 million population and for setting up common regional sanitary landfill facilities or stand alone sanitary landfill facilities by all local authorities having a population of 0.5 million or more .

1 year

3. procurement of suitable sites for setting up solid waste processing facility and sanitary landfill facilities 2 years

4. enforcing waste generators to practice segregation of bio degradable, recyclable, combustible, sanitary waste domestic hazardous and inert solid wastes at source , 2 years

5. Ensure door to door collection of segregated waste and its transportation in covered vehicles to processing or disposal facilities.

2 years

6. ensure separate storage, collection and transportation of construction and demolition wastes 2 years

7. setting up solid waste processing facilities by all local bodies having 100000 or more population 2 years

8. Setting up solid waste processing facilities by local bodies and census towns below 100000 population.

3 years 9 setting up common or stand alone sanitary landfills by or for all local bodies having 0.5 million or more population for the disposal of only such residual wastes from the processing facilities as well as untreatable inert wastes as permitted under the Rules 3 years

10. setting up common or regional sanitary landfills by all local bodies and census towns under 0.5 million population for the disposal of permitted waste under the rules 3years

11. bio-remediation or capping of old and abandoned dump sites 5years

Where this provision sits

ActSolid Waste Management Rules 2016
Section22
Marginal noteTime frame for implementation
JurisdictionCentral
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Solid Waste Management Rules 2016 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.