Section 15: Submission of Test report by the competent person

The Tamil Nadu Lifts and Escalators Rules,1997State Rules of Tamil Nadu · 1997

Every lift or escalator shall be maintained, inspected, tested at an interval of every one year by a competent person authorized under rule 14 and shall submit the test report to the Inspector regarding the condition of lift or escalator in the Form ‘’O’’ or ’’P” ,as the case may be.

https://www.tnei.tn.gov.in/ 9 ANNEXURE-I [See rule 13(1)] AUTHORIZATION FOR ERECTION, MAINTENANCE, INSPECTION AND TESTING OF LIFTS OR ESCALATORS

1. Requirements for authorization.- An application for authorization for erection , maintenance, inspection and testing of lifts or escalator, as the case may be, under the provisions of rule 13 of the Tamil Nadu Lifts and Escalators Rules,1997 may be made in the prescribed Form - “J” along with the prescribed fee by a person fulfilling the following criteria:-

(i) shall have an independent office premises with an independent telephone connection within the State of Tamil Nadu.

(ii) shall have to produce a certificate from any nationalized bank to the effect that he is solvent to the extent of rupees eight lakh.

(iii)shall have in his regular employment the following minimum staff (copies of appointment letter, proof of academic qualification and field experience to be enclosed).

(a) At least one engineer possessing (i) a degree in mechanical engineering or its equivalent qualification from the recognized university or institution and having an experience of at least five years in the field of lifts or escalators, as the case may be; or (ii) a diploma in mechanical engineering from a recognized institute and having an experience of at least eight years in the field of lifts or escalators, as the case may be.

(b) At least one engineer possessing (i) a degree in electrical and electronics engineering or its equivalent qualification from the recognized university or institution and having an experience of atleast five years in the field of lifts or escalators as the case may be or (ii) a diploma in electrical engineering from a recognized institute and having an experience of at least eight years in the field of lifts or escalators as the case may be.

(c) At least one person possessing a certificate in the trade of electrical or electronics from the Industrial Training Institute or any other recognized institution and possessing Wireman competency certificate issued by Tamil Nadu Electrical Licensing Board and having an experience of at least five years in the field of Lifts or escalators, as the case may be.

(d) Erection staff of one Industrial Training Institute electrician, one Industrial Training Institute fitter and one helper for erecting every ten new lifts/escalators to be erected in a year.

(e) Maintenance staff of one Industrial Training Institute electrician, one Industrial Training Institute fitter and one helper for every fifty lifts/escalators to be maintained in a year and;

10

(f) Clerk/attendant round the clock having the presence in the service station for responding to the complaint calls from the owners.

(iv) shall have a workshop in his own possession within the State of Tamil Nadu equipped with minimum area of 100 square meters with independent facility and telephone and separate power connection of at least 15 HP Such workshop shall be equipped with the following minimum machineries and testing instruments either stationary or portable.

(a) Lathe machine.

(b) Drill machine

(c) Welding machine of 5 kVA or above.

(d) Hacksaw machine

(e) Chain pulley block of 3 tonne capacity.

(f) Standard weight trolley

(g) Clip-on meter for measurement of voltage , current etc.,

(h) Tachometer

(i) Megger

(j) Earth tester

Provided that when the authorized person is having his own manufacturing unit within the State of Tamil Nadu, he shall not be required to have a separate workshop but he shall be required to have the minimum machineries and instruments as mentioned above.

(v) shall have necessary safety gadgets, like safety belts and head gears for entire staff engaged in the work of erection and maintenance.

(vi) shall have suitable means of transportation at his disposal for transportation of material.

(vii) shall have group insurance covering all staff

Provided that a staff register and the relevant records related with erection, testing and maintenance work shall be maintained by such person and the same shall be produced for verification as and when directed by the Chief inspector. The specimens of such staff register as well as the guide lines to be followed for maintaining the records of erection, testing and maintenance shall be prescribed by the Chief Inspector.

2. Grant of certificate of authorization: -(1) The Chief Inspector may after such enquiries and tests as may be considered necessary, grant a certificate of authorization in Form “K”, in case of lifts and in Form “L”, in case of escalators to an applicant who fulfill the above requirements.

(2) The Chief Inspector may after giving an opportunity to the persons authorized under section 10(3) of the Act of being heard, cancel the authorisation, if the person has reason to believe that he -

(i) has violated any condition stipulated in the authorisation; or

(ii) has acted in a manner inconsistent with the intent or the purpose of this Act or the rules made thereunder; or has omitted to act as required under the Act 11 and rules made thereunder or found to be guilty of negligence, incompetence;

or

(iii) for any other reason to be recorded in writing.

3. Documents tobe enclosed along with renewal application :- Every authorization granted under rule 14 shall be valid for 2 years. The authorization may be renewed on an application made in that behalf to the Chief Inspector along with following documents before three months from the date of expiry of licence.

(a) Certificate of Authorization in original.

(b) A receipted challan in original

(c) A copy of the staff register attested by a gazetted officer.

(d) A statement indicating the numbers of lifts or escalators erected during the valid period of authorisation.

(e) Number of lifts or escalators maintained during the valid period of authorisation.

(f) A certificate from any nationalized bank to the effect that the applicant continues to be solvent to the extent of Rupees eight lakhs.

(g) A copy of the application made, if any, for renewal of the registration granted under the Factories Act, 1948.

(h) Updated list of machineries, equipment and testing instruments in possession.

(i) Details of safety gadgets for staff.

(j) Details of vehicles in possession for transportation of materials.

12 ANNEXURE-II [See rule 13(2)] AUTHORISATION FOR MAINTENANCE, INSPECTION AND TESTING OF LIFTS OR ESCALATORS.

1. Requirements for authorization.

An application for authorization for maintenance, inspection and testing of lifts or escalator, as the case may be, under the provisions of rule 13 of The Tamil Nadu Lifts and Escalators Rules, 1997 may be made in the prescribed Form-“J” along with the prescribed fee, fulfilling the following criteria.

(i) shall have an independent office premises with an independent telephone connection within the State of Tamil Nadu.

(ii) shall have to produce a certificate from any nationalized bank to the effect that he is solvent to the extent of rupees three lakhs.

(iii) shall have in his regular employment following the minimum staff (copies of appointment letter, proof of academic qualification and field of experience to be enclosed).

(a) At least one engineer possessing (a) a degree in mechanical engineering or its equivalent qualification from the recognized university or institution and having an experience of at least five years in the field of elevators or escalators, as the case may be or (ii) a diploma in mechanical engineering from a recognized Institute and having an experience of at least eight years in the field of elevators or escalators as the case may be.

(b) At least one engineer possessing (i) a degree in electrical and electronics engineering or its equivalent qualification from the recognized university or institution and having an experience of atleast five years in the field of elevators or escalators as the case may be or (ii) a diploma in electrical engineering from a recognized Institute and having an experience of at least eight years in the field of elevators or escalators as the case may be.

(c) At least one person possessing a certificate in the trade of electrical or electronics from the Industrial Training Institute or any other recognized Institution and possessing “Wireman competency certificate” issued by Tamil Nadu Electrical Licensing Board and having an experience of at least five years in the field of Lifts or escalators, as the case may be.

(d) Maintenance staff of one Industrial Training Institute electrician, one Industrial Training Institute fitter and one helper for every fifty lifts/ escalators to be maintained in a year

(e) Clerk/attendant round the clock having the presence in the service station for responding to the complaint calls from the owners. Provided that the employment of such clerk/attendant shall not be necessary during night 13 hours if facilities for better communication like mobile phone, pager system etc. are available during such hours.

(iv) Shall have a workshop in his own possession within the State of Tamil Nadu equipped with minimum area of 100 square meters with independent facility and telephone and separate power connection of at least 15 HP Such workshop shall be equipped with the following minimum machineries and testing instruments either stationary or portable.

(a) Lathe machine.

(b) Drill machine

(c) Welding machine of 5 kVA or above.

(d) Hacksaw machine

(e) Chain pulley block of 3 tonne capacity.

(f) Standard weight trolley

(g) Clip-on meter for measurement of voltage, current etc.

(h) Tachometer

(i) Megger

(j) Earth tester

Provided that when the authorized person is having his own manufacturing unit within the State of Tamil Nadu, he shall not be required to have a separate workshop but he shall be required to have the minimum machineries and instruments as mentioned above.

(v) shall have necessary safety gadgets, like safety belts and head gears for entire staff engaged in the work of maintenance.

(vi) shall have suitable means of transportation at his disposal for transportation of material.

Provided that a staff register and the relevant records related to maintenance shall be maintained by such person and the same shall be produced for verification as and when directed by the Chief inspector. The specimens of such staff register as well as the guide lines to be followed for maintaining the records of maintenance shall be prescribed by the Chief Inspector.

2. Grant of Certificate of authorization:

(1) The Chief Inspector may after such enquiries and tests as may be considered necessary grant a certificate of authorization in Form “M’’, in case of lifts and in Form “N’’, in case of escalators set out in this annexure to an applicant who fulfill the above requirements.

(2) The Chief Inspector may after giving an opportunity to the persons authorized under section 10(3) of the Act of being heard, cancel the authorisation, If the person has reason to believe that he -

(i) has violated any condition stipulated in the authorisation; or 14

(ii) has acted in a manner inconsistent with the intent or the purpose of this Act or the rules made thereunder; or has omitted to act as required under the Act and rules made thereunder or found to be guilty of negligence, incompetence; or

(iii) for any other reason to be recorded in writing.

3. Documents to be enclosed herewith along with renewal application:

Every authorization granted under rule 14 shall be valid for two year. The authorization may be renewed on an application made in that behalf to the Chief Inspector along with following documents before three month from the date of expiry of licence.

(a) Certificate of Authorization in original.

(b) A receipted challan in original

(c) A copy of the staff register attested by a Gazetted Officer.

(d) Details of lifts maintained during the validity period of authorisation.

(e) A certificate from any nationalized bank to the effect that the applicant continues to be solvent to the extent of Rupees Five lakhs.

(f) A copy of the application made, if any, for renewal of the registration granted under the Factories Act, 1948.

(g) Updated list of machineries, equipment and testing instruments in possession.

(h) Details of safety gadgets for staff.

(i) Details of vehicles in possession for transportation of materials.

15 “FORMS FORM ‘A’ (see rule 3 ) APPLICATION FOR PERMISSION * TO INSTALL* ------------------ A LIFT OR AN ESCALATOR * TO MAKE ADDITIONS AND ALTERATIONS TO To The Inspector of Lifts and Escalators.

1 Full Name and Address of the Applicant 2 Contact Number and E- mail id 3(a) Address of the premises where the Lift or Escalator *is to be * Installed *make additions or alterations

(b) Approval reference of Urban Local Body concerned for the Building Plan (Copy of approval letter, approved plan and elevation drawings to be enclosed).

4 Whether a licence has been previously granted (details to be given).

5 Type and Make of Lift or Escalator* (A sketch of the erection plans as per rule 3 shall be attached).

6 (a)The rated maximum speed of the Lift;

The Maker’s or Designer’s rated capacity in Weight (in kg).*

(b)The rated speed of Escalator (m/sec);

The Maker’s or Designer’s rated capacity (in persons /hr).* 7 The maximum number of passengers in addition to the lift operator which the lift can carry* 8 The total weight of the lift car carrying the maximum load (Weight of car plus maximum allowable load)* 9 The weight of the counter-weight for Lift (kg )* 16 10 System of roping: (The number, description, weights

(kgs) and size (in Sq.mm) of the supporting ropes of the Lift )* 11 Lift *:The depth of the pit from lowest part of the car when at the lowest floor (in mms) Escalator*:The depth of the pit (both upper and lower) (in mms) 12 Details of the construction of the Overhead Arrangement with weight (in kg.) and size (in mms) of beams or any other arrangement * 13 Total Number of landings of the Lift* 14 (a)Angle of inclination of escalator*

(b)Vertical rise of the escalator (in mms)

(c)Width of the escalator

(d) Number of flat steps 15 (a)Type of balustrading in escalator:

(b) Height of balustrade 16 Details of

(a) hand rails

(b) steps treads

(c) landing

(d)comb plates

(e) trusses or girders, Skirting brush

(f)step wheel tracks in escalator 17 (a)Drive chain factor of safety whether all the electrical and mechanical safety devices as per standards provided in the escalator

(b) Illumination level provided for comb lights ( in lux) 18 Details of fee paid Date: Signature of the Applicant.

Encl: 1.Original remitted chalan/e-receipt.

2. Copy of approval obtained from the local body for the building.

3. Drawings of Lift or Escalator*Installation (Both Electrical and Mechanical) ---------------------------------------------------- * Strike off whichever is inapplicable.

17 FORM ‘B’ (See rule 3(2)) Government of Tamil Nadu Letter No………………… Dated ____________ To ………………………..

………………………..

………………………...

………………………..

Sub: Permission for * erection of Lift or Escalator * or making additions or alterations of existing Lift or Escalator *at the …………………….. Granted.

*Under sub-section (3) in section 4 of the Tamil Nadu Lifts and Escalators Act,1997 (Tamil Nadu Act 35 of 1997), permission is hereby granted to erect Lift or Escalator * under section 9 of the Tamil Nadu Lifts and Escalators Act,1997 (Tamil Nadu Act 35 of 1997), *permission is hereby granted to make additions or alterations of existing Lift or escalator * at the premises ……………………………………………… owned by ……………………… subject to the provisions of the Tamil Nadu Lifts and Escalators Act,1997 (Tamil Nadu Act 35 of 1997) and the Tamil Nadu Lifts and Escalator Rules, 1997.

The permission shall be valid for a period of six months from the date on which it is granted.

The lift or Escalator* shall not be worked until a licence is granted by the Inspector of Lifts and Escalators for working of the lift or escalator in accordance with rule 4 of the Tamil Nadu Lifts and Escalator Rules, 1997.

Signature------------------------------------------------- The Inspector of Lifts and Escalators, Government of TamilNadu * Strike off whichever is inapplicable.

18 FORM C (see rule 4 (1) ) NOTICE INTIMATING THE COMPLETION OF THE WORK OF ERECTION OF LIFT OR AN ESCALATOR AND APPLICATION FOR A LICENCE TO WORK THE LIFT OR AN ESCALATOR To The Inspector of Lifts and Escalators Sir, Sub: Erection of Lift or Escalator *at the ……….

With reference to your letter No.___________________dated______________ by which permission has been granted to erect a Lift or an Escalator* at the above mentioned premises, I/We have to state that the work of erection of the lift or Escalator* was completed on _________________________ by Thiru.___________________________________________.

I/We further request that a licence for working the lift or Escalator* may be granted. The work of erection of the lift or Escalator* has been carried out in accordance with the provisions of the Tamil Nadu Lifts and Escalator Rules, 1997.

A work Completion Report of the manufacturer of lifts or escalators* or Company of the Electrical and Mechanical Engineers, Completion Report of the licensed Electrical Contractor, and copy of Insurance Policy taken by the owner(s) of the Lift or Escalator* covering insurance for the persons using the Lift or Escalator* are enclosed.

Yours faithfully, Signature of the owner of the lift or escalator* Encl.: (1) Original remitted chalan/e-receipt.

(2) Work Completion Report of the manufacturer of lifts or escalators* or the Company of Electrical and Mechanical Engineers.

(3) Work Completion Report of the Electrical Contractor.

(4) Copy of Insurance Policy.

* Strike off whichever is inapplicable.

19 FORM D [See Rule 4 (1) ] To The Inspector of Lifts and Escalators Sir, Sub: Erection of Lift or Escalator*----------------------------------------------------------------- Submission of Completion Report -------------------- We ------------------------------------------------------------------------(Name of the manufacturer of Lifts or Escalators*or Company of Electrical and Mechanical Engineers) having undertaken the work of erection of the lifts or escalators at the premises of ------------------------------------------------------ ---- and having completed the erection of the said lift or escalator *hereby certify that the work of erection of the lift or escalator complies with the provisions of the Tamil Nadu Lifts and Escalator Rules, 1997. We further certify that the erection and testing of the lift or escalator* has been carried out in accordance with the provisions of the Tamil Nadu Lifts and Escalators Act, 1997 (Tamil Nadu Act 35 of 1997) and the Tamil Nadu Lifts and Escalator Rules,1997 and confirm that the Lift car, motor, controller, ropes, governor and all the systems and components of the Lift have been tested conforming to the Bureau of Indian Standards or relevant International Standards *or the Escalators have been tested conforming to the Bureau of Indian Standards or relevant International Standards.

It is certified that the Building in which the lift or escalator* is erected is structurally sound and stable. We further certify that the lift or escalator * installation is ready for Inspection which is required to be made for the purpose of Issuing a licence under the said Act and the Rules, for working the same.

We undertake the full responsibility of the Installation to be handed over duly to the owner after Inspection and compliance of provisions of the said Act and Rules.

*Details of Lift Installation:

(i) Make of Lift and Serial No.

(ii) Type of Lift

(iii) Type of Control

(iv) Capacity 20 *Details of Escalator:

(i) Make of Escalator and Serial No __________________________________

(ii) Angle of inclination of Escalator ___________________________________

(iii) Width of the escalator ___________________________________

(iv) Vertical rise of the escalator ___________________________________

(v) Rated load ___________________________________

(vi) Rated speed ___________________________________ Yours faithfully, Signature of the Manufacturer of the lifts or escalators* or the Company of the Electrical and Mechanical Engineers.

Registration certificate No:

Validity:

* Strike off whichever is inapplicable.

21 FORM E [See rule 4 (1)] FORM OF COMPLETION REPORT FROM LICENSED CONTRACTOR FOR ELECTRICAL WORKS OF LIFT OR ESCALATOR* We report that the electrical installation detailed below has been installed by us and tested and that to the best of our knowledge and belief it complies with the Central Electricity Authority (MSES) Regulations, 2010 as well as the Indian Standard code of practices for electrical installations.

(1) Electrical Installation at _________________________________________

(2) Voltage and System supply _________________________________________

(3) PARTICULARS OF WORKS:

(a) MV installation:

Sl.

No.

Equipment Capacity in KW Voltage Fed from Distribution Board/Switch Board

(1) (2) (3) (4) (5)

(b) Lighting load: _____________________________ N.B.- Additional sheets to be used, if needed, for furnishing details against any items.

(c) Test results:

I. (1) Insulation resistance for the whole Installation

(2) Between Phases.

(3) Between each phase and earth II. (1) Resistance of earth electrode for earthing system

(2) Maximum earthing resistance of Installation Signature of Supervisor Signature of Electrical Contractor Name and address Name and address ____________________________ ___________________________________ ____________________________ ____________________________________ COMPETENCY CERTIFICATE ELECTRICAL CONTRACTOR LICENCE No._________________________ No.________________________________ Valid upto____________________ Valid upto___________________________ Dated ______________________ Dated______________________________ 22 FORM ‘F’ [see rules 4(2), 5(2) and 6 ] LICENCE TO WORK / RENEWAL OF LICENCE TO WORK A LIFT OR AN ESCALATOR (This licence is not transferable or assignable to any person, company, body of individuals or firm. This licence is to be renewed once in three years and must be produced to the Licensing Authority when called for.)

Registration No._____________________ Under sub-section (3) of section 5 of the Tamil Nadu Lifts and Escalators Act, 1997) (Tamil Nadu Act 35 of 1997), Thiru_______________________________________ are hereby granted / renewed licence to work or cause to be worked or allow the working of the lift or escalator* erected and inspected on__________at the premises No. ______________________________________ ___________________________ subject to the provisions of the Tamil Nadu Lifts and Escalators Act,1997 (Tamil Nadu Act 35 of 1997) and the Tamil Nadu Lifts and Escalators Rules,1997, the particulars of which are given below:- The licence shall remain valid from ________________to ____________ and is issued, subject to the conditions set out below:- *PARTICULARS

(i) Make of Lift and Serial No. ___________________________________

(ii) Type of Lift ___________________________________

(iii) Type of Control ___________________________________

(iv) Capacity ___________________________________ *PARTICULARS

(i) Make of Escalator and Serial No ___________________________________

(ii) Angle of inclination of Escalator ___________________________________

(iii) Width of the escalator ___________________________________

(iv) Vertical rise of the escalator ___________________________________

(v) Rated load ___________________________________

(vi) Rated speed ___________________________________ Date _______________ Inspector of Lifts and Escalators Date of Inspection

(1) Valid from

(2) Valid upto

(3) Signature of the Officer renewing the Licence

(4) 23 CONDITIONS

(1) The lift or escalator* and its installation shall be worked and maintained in conformity with the provisions of the Tamil Nadu Lifts and Escalators Act,1997 and the Tamil Nadu Lifts and Escalators Rules, 1997.

(2) If the holder of this licence does not reside in the Town or Village in which the lift or Escalator* has been erected, he shall within one month from the date of this licence appoint an agent, authorized signatory of the licensee who shall be resident in the Town or Village in which the lift or escalator* has been erected. The agent, authorized signatory of the licensee so appointed shall be responsible for the working and maintenance of the lift or escalator *in conformity with the provisions of the said Act and Rules. The name of every such agent, authorized signatory of the licensee shall be communicated to the Inspector of Lifts and Escalators. Any change of agent, authorized signatory of the licensee shall also be similarly communicated.

(3) The holder of this licence, within one month from the date of this licence, appoint a manufacturer of lift or escalator* or a company of Electrical and Mechanical Engineers for the maintenance of the lift or escalator* and shall communicate the same to the Inspector.

Any change of the above so appointed shall also be communicated.

(4) The licensee shall produce test reports obtained from the competent person authorized under rule 14 for the lift installation in Form “O” or Form “P” for the escalator installation, at the end of every year from the date of grant or renewal of licence.

(5) No additions or alterations to the lift or escalator *and its installation shall be carried out without previous permission in writing of the Inspector.

(6) The licensee shall not use the lift or escalator *which is not in a safe condition and shall be solely responsible for the safe maintenance of the lift or escalator*, so that the Tamil Nadu Lifts and Escalators Rules, 1997 are always complied with.

(7) If the holder of this licence ceases to have interest in the lift or escalator *installation for which the licence is granted, the licence shall be deemed to be invalid and it shall be returned to the Inspector.

(8) If any direction issued under sub –section (2-A) of Section 11 of the Act has not been carried out, such lift in case is found being used, shall be ordered to be stopped forthwith and sealed by the Inspector.

(9) The insurance policy shall be annually renewed at the end of its validity.

(10) Whoever contravenes any of the provisions of the Act or the Rules made thereunder or the terms and conditions of a permission or of a licence or a direction given by the Inspector or any person appointed under Section 14 of the Act to assist him, shall be punishable with fine which may extend to one thousand rupees and in the case of a continuing contravention with a further fine which may extend to fifty rupees for every day during which such contravention is continued after such conviction.

* Strike off whichever is inapplicable.

24 FORM G [See rule 5(1)] APPLICATION FOR RENEWAL OF LICENCE FOR WORKING A LIFT OR AN ESCALATOR* To The Inspector of Lifts and Escalators, __________________ Sir, Sub:- Application for renewal of Licence for working the Lift or Escalator * at ____________________________________________________________ As required under rule 5(1) of the Tamil Nadu Lifts and Escalators Rules, 1997, I/We hereby apply for the renewal of licence for working the lift or escalator* and the required particulars are furnished below and request that renewal of licence may be granted:-

1. Full Name and Address of the Applicant

2. Contact Number and E-mail id:

3. Address of the place where the lift or escalator has been erected together with the name of the owner thereof.

4. Details of licence previously granted

5. Details of fee paid.

6. Whether a copy of valid Insurance Policy taken by the Owner of the lift or escalator* covering insurance for persons using the lift or escalator* is enclosed.

7. Whether a copy of Annual Maintenance contract for the lift or escalator is enclosed.

8. Whether a copy of the test reports issued by the authorised competent person is enclosed.

Yours faithfully, Signature of the Owner of the lift or Escalator* Encl: (1) Original remitted Challan/e-receipt

(2) Copy of Insurance Policy.

(3) A copy of Annual Maintenance Contract for the lift

(4) A copy of the Test Report issued by the competent person

(5) The stability Certificate obtained from the registered Structural Engineer for the buildings which are constructed before the formation of Urban Local Body (if applicable) * Strike off whichever is inapplicable.

25 FORM H (see rule (6) ) APPLICATION FOR LICENCE FOR WORKING AN ESCALATOR ERECTED PRIOR TO THE COMMENCEMENT OF THE TAMIL NADU LIFTS AND ESCALATORS ACT, 1997 To The Inspector of Lifts and Escalators, ……………………….

………………………

1. Full name and address of the applicant

2. Name and address of the authorized signatory

3. Address of the place where the Escalator has been erected together with the name of the owner thereof.

4. Date of erection

5. Type of Escalator

6. Name of Manufacturer and Serial Number of Escalator

7. Vertical rise of the Escalator in millimeter

8. The rated speed of the Escalator (m/s)

9. The rated load (in Kilogram) of the Escalator

10. Rated Capacity in persons/hour

11. Angle of inclination of escalator

12. Type of balustrading in escalator

13. Width between balustrades in escalator

14. Details of handrails, steps treads, landing, comb plates, trusses or girders and step wheel tracks in escalator

15. The Factor of safety based on the static loads

16. Whether all the Electrical and Mechanical safety devices are provided as per standards

17. Details of fee paid Signature of the Owner of the Escalator Date:

Enclosure: (1) Copy of Insurance Policy taken by the owner of the escalator covering insurance for the persons using the escalator.

(2) Original remitted Chalan

(3) Test Reports obtained from the authorised competent Person

(4) Structural Stability Certificate obtained from registered Structural Engineer for the building where the escalator is installed.

26 FORM I [See rule 10] NOTICE OF ACCIDENTS IN LIFTS OR ESCALATORS To 1) The Inspector of Lifts and Escalators ------------------------------------------------- 2) The commissioner of Police in the City of Chennai, Madurai, Coimbatore, Salem, Tiruchirappalli, Tirunelveli or Tiruppur and elsewhere to the District Magistrate and such other officer as the Government may, by order, specify in this behalf.

Under Section 13 of the Tamil Nadu Lifts and Escalators Act, 1997 (Tamil Nadu Act 35 of 1997), I/We hereby inform you that an accident has occurred in the operation of *Lifts/*Escalators at the place owned by me/us on -------------------------------------------------------------------------------------------------- --------------------------- I/We have discontinued the working of a Lift/Escalator, pending permission of the Inspector to resume the working.

Yours faithfully, Dated : Signature of the owner of the Lift/Escalator * Strike off whichever is inapplicable.

27 FORM- J (see rule 14) APPLICATION FOR OBTAINING AUTHORISATION OR RENEWAL FOR ERECTION, MAINTENANCE, INSPECTION AND TESTING OF LIFTS OR ESCALATORS/ MAINTENANCE INSPECTION AND TESTING OF LIFTS OR ESCALATORS*

1. Name of the applicant ___________________________________

2. Name of authorized person with designation

3. Legal status (whether individual firm or company) (Registration Number, GST No., and names of Partners or Directors to be given in case of firm or company, as the case may be.)

4. Business Address _________________________________________ (Details about possession, e-mail address, phone number)

5. Whether certificate of authorization was issued in the past in the same name. If so, give number and date of certificate of authorization.

6. (A) Particulars relating to erection and maintenance of lifts/escalators. Details of lifts/escalators erected and maintained to be furnished along with licence details.* (B) Particulars relating to maintenance of lifts/escalators. Details of lifts/escalators maintained to be furnished along with licence details. *

7. Whether solvency certificate is attached.

8. (A) Details of entire staff employed for Erection and Maintenance* (Copies of appointment letter, proof of academic qualification and field experience to be enclosed) (B) Details of entire staff employed for Maintenance* (copies of appointment letter, proof of academic qualification and field of experience to be enclosed)

9. Details of workshop with machineries.

10. Details of testing instruments.

11. Details of safety gadgets/tools.

12. Details of facilities of vehicles.

13. Details of payment of fee (Original receipted Chalan to be attached)

14. Group Insurance scheme/workman compensation policy for the employees

15. Remarks.

I/We hereby declare that the particulars stated above are correct to the best of my/our knowledge.

Place :

Date :……………….. Signature:______________ Name:__________________ Designation: _____________ 28 Notes: (1) Any person who makes, procures to be made or assist in making any false statement for the purpose of obtaining for himself or any other person a certificate of authorization for erection and maintenance of lifts/escalators shall render himself liable to prosecution.

(2) If additional space is required for completing any items, additional sheet may be attached to this Form.

---------------------------------------------------- * Strike off whichever is inapplicable.

DECLARATION BY THE ORGANISATION (IF EMPLOYED) I, certify that Thiru/Thirumathi……………………………….whose details are furnished above, is in our employment and nominate him on behalf of the organisation for the purpose of being declared as an authorized person under the Act. I also undertake to

(a) notify the Inspector in case the authorized person leaves our employment;

(b) take responsibility for any lapse on the part of the authorized person in the performance of his function.

Signature :

Designation :

(Head of the Organisation or Authorised Signatory) Telephone No. :

Office Seal :

29 Form K (see rule 14) GOVERNMENT OF TAMIL NADU ELECTRICAL INSPECTORATE CERTIFICATE OF AUTHORISATION or RENEWAL OF AUTHORISATION FOR ERECTION ,MAINTENANCE, INSPECTION AND TESTING OF LIFTS REGISTRATION NO :

DATE OF REGISTRATION :

Under Section 10 of the Tamil Nadu Lifts and Escalators Act, 1997, (35 of 1997) Thiru…………………………………………………………………………………………………… ………………………………………………………………………………………………………… ………………………………………………………….are hereby authorized to carry out erection, maintenance, inspection and testing of lift installation within the State of Tamil Nadu, subject to the compliance of instructions set out in the Annexure I and fulfillment of the conditions detailed below.

Chief Inspector of Lifts and Escalators Authorization Valid from

(1) Authorization Valid upto

(2) Initial of Chief Inspector of Lifts and Escalators

(3) 30 CONDITIONS ERECTION / MAINTENANCE / INSPECTION / TESTING 1) (i) This certificate is valid for a period of one year and shall be returned to Chief Inspector of Lifts and Escalators for renewal along with application for the purpose three months before the expiry of validity

(ii) In the event of the holder of registration failing to get the registration renewed in the said manner before the date of expiry, the registration shall become void and fresh registration shall have to be obtained.

2) The firm/company holding this registration can undertake the work of erections, additions or alterations of Lift.

3) The holder of this certificate of registration shall be in possession of the latest copy of Tamil Nadu Lifts and Escalators Act, 1997 and Tamil Nadu Lifts and Escalators Rules, 1997 and relevant specifications and code of practices of Bureau of Indian Standards.

4) (i) It shall be the responsibility of the person authorized to ensure that all materials, fittings, appliances, equipments etc used in the lift which he undertakes to erect/add/alter conform to the relevant specifications as laid down by Bureau of Indian Standards.

(ii) All the works for erection/addition/alteration of Lift undertaken by the holder of this certificate of registration shall be done as per the provisions of the Lift and Escalators Rules and the holder thereof shall be responsible for proper erection.

5) The holder of this certificate of registration

(i) shall maintain a register of technical personnel employed by him for erection and that register shall be produced for inspection on demand by Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators or any other person authorised by him in this behalf.

(ii) shall maintain a register of lifts erected indicating the date of commencement of completion.

(iii) The list of lifts erected as on 31st March of every year, after the receipt of the approval, shall be submitted before 30th April of the year to Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators and the Inspector of lifts of the District/Area concerned.

6) Any change in address of the place of business of the holder of this certificate of registration shall be communicated to Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators within 2 weeks of such change. Any change of Agent or Manager, if any shall be similarly notified within fiftee days of such change.

7) Permission to erect a lift or for making addition or alteration to existing lift should be arranged to be obtained from Inspector of Lifts of District concerned.

31 8) Before commencement of the work of erection, addition to or alteration to a lift installation, intimation shall be given to Inspector of lifts of concerned district within 7 days from the commencement of work 9) On completion of the erection works completion report should be sent to the Inspector of Lifts and Escalators for obtaining the license and lifts should be commissioned only after obtaining the license.

10) A record of tests carried out during initial erection and tests carried on the lifts installation shall be recorded in a register to be maintained for the purpose by the holder of this certificate and every such report shall be produced to the Inspector of Lifts and Escalators concerned during the Inspection.

11) The holder of this certificate should mention the approval registration number with its validity in all their correspondence to this office and to any Inspector of Lifts and Escalators and only the authorized signatory shall sign in all the correspondences.

12) The holder of this certificate should depute one of his authorised Representative/ Engineer to be present at the time of inspection by the Inspector of Lifts and Escalators or his representative of the lift Installation erected by him.

13) If there is change in ownership or the name and style in which the approval is granted then the holder of the certificate shall seek fresh certificate of authorisation.

14) Atleast 3 persons who are ordinarily the occupants or residents of premises in which the lift is to be installed, shall be trained by the holder of this certificate of registration in respect of rescue operation in case of power failure.

15) The holder of this certificate of registration shall report the occurrence of any fatal or non-fatal accident in writing to Chief Inspector of Lifts and Escalators and the Inspector of Lifts and Escalators concerned within 24 hours of the occurrence of such accident.

16) The group Insurance Scheme/Workman compensation policy for the employees should be kept alive.

17) Issue of Duplicate copy of Certificate of Registration:

(i) A duplicate copy of certificate of registration will be issued on the request made by the applicant in case of loss of original certificate, to the satisfaction of Chief Inspector of Lifts and Escalators

(ii) On issue of duplicate copy of certificate, the original certificate shall be deemed to be invalid and if found shall be returned to Chief Inspector of Lifts and Escalators 18) If the holder of this certificate is found to be guilty of negligence or incompetence or in case of breach of the provisions of the Tamil Nadu Lifts and Escalators Act, 1997 and Tamil Nadu Lifts and Escalators Rules, 1997 and the above instructions contained in this registration or for the malpractice or misconduct or misbehavior or any other reason in public interest, the Chief Inspector of Lifts and Escalators may suspend or cancel the approval after giving show cause notice.

32 Form L (See rule 14) GOVERNMENT OF TAMIL NADU ELECTRICAL INSPECTORATE CERTIFICATE OF AUTHORIZATION FOR ERECTION, MAINTENANCE, INSPECTION AND TESTING OF ESCALATORS REGISTRATION NO :

DATE OF REGISTRATION :

Under Section 10 of Tamil Nadu Lifts and Escalators Act,1997, Thiru/Thirumathi ………………………………………………………………………………………………………… ………………………………………………………………………………………………………… ………….are hereby authorized to carry out erection, maintenance, inspection and testing of escalators installation within the State of Tamil Nadu subject to the compliance of instructions set out in the Annexure I and fulfillment of the conditions detailed below.

Chief Inspector of Lifts and Escalators Authorization Valid from

(1) Authorization Valid upto

(2) Initial of Chief Inspector Lifts and Escalators

(3) 33 CONDITIONS ERECTION/MAINTENANCE/INSPECTION/TESTING

(1) (i) This certificate is valid for a period of one year and shall be returned to Chief Inspector of Lifts and Escalators for renewal along with application for the purpose three months before the expiry of validity.

(ii) In the event of the holder of registration failing to get the registration renewed in the said manner before the date of expiry, the registration shall become void and fresh registration shall have to be obtained.

(2) The firm/company holding this registration can undertake the work of erections, additions or alterations of escalators.

(3) The holder of this certificate of registration shall be in possession of the latest copy of the Tamil Nadu Lifts and Escalators Act, 1997 and The Tamil Nadu Lifts and Escalators Rules, 1997 and relevant specifications and code of practices of Bureau of Indian Standards.

(4) (i) It shall be the responsibility of the person authorized to ensure that all materials, fittings, appliances, equipments etc used in the escalators which he undertakes to erect/add/alter conform to the relevant specifications as laid down by Bureau of Indian Standards.

(ii) All the works for erection/addition/alteration of escalators undertaken by the holder of this certificate of registration shall be done as per the provisions of the Lift and Escalators Rules and the holder thereof shall be responsible for proper erection.

(5) The holder of this certificate of registration,--

(i) shall maintain a register of technical personnel employed by him for erection and register shall be produced for inspection on demand by Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators or any other person authorised by him in this behalf.

(ii) shall maintain a register of escalators erected indicating the date of commencement of completion.

(iii) The list of escalators erected as on 31st March of every year, after the receipt of the approval, shall be submitted before 30th April of the year to Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators and the Inspector of lifts of the District/Area concerned.

(6) Any change in address of the place of business of the holder of this certificate of registration shall be communicated to Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators within two weeks of such change. Any change of Agent or Manager, if any shall be similarly notified within fifteen days of such change.

(7) Permission to erect a escalators or for making addition or alteration to existing escalators should be arranged to be obtained from Inspector of Lifts and Escalators of District concerned.

34

(8) Before commencement of the work of erection, addition to or alteration to an escalators installation, intimation shall be given to Inspector of Lifts and Escalators of concerned district within 7 days from the commencement of work.

(9) On completion of the erection works completion report should be sent to the Inspector of Lifts and Escalators for obtaining the license and escalators should be commissioned only after obtaining the license.

(10) A record of tests carried out during initial erection and tests carried on the escalators installation shall be recorded in a register to be maintained for the purpose by the holder of this certificate and every such report shall be produced to the Inspector of Lifts and Escalators concerned during the Inspection.

(11) The holder of this certificate should mention the approval registration number with its validity in all their correspondence to this office and to any Inspector of Lifts and Escalators and only the authorised signatory shall sign in all the correspondences.

(12) The holder of this certificate should depute one of his authorised Representative/Engineer to be present at the time of inspection by the Inspector of Lifts and Escalators or his representative of the escalators Installation erected by him.

(13) If there is change in ownership or the name and style in which the approval is granted then the holder of the certificate shall seek fresh certificate of authorisation.

(14) Atleast 3 persons who are ordinarily the occupants or residents of premises in which the escalators are installed, shall be trained by the holder of this certificate of registration in respect of rescue operation in case of power failure.

(15) The holder of this certificate of registration shall report the occurrence of any fatal or non-fatal accident in writing to Chief Inspector of Lifts and Escalators and the Inspector of Lifts and Escalators concerned within 24 hours of the occurrence of such accident.

(16) The group Insurance Scheme/Workman compensation policy for the employees should be kept alive.

(17) Issue of Duplicate copy of Certificate of Registration:

A duplicate copy of certificate of registration granted under these rules will be issued on request made by the applicant in case of loss of original certificate to the satisfaction of Chief Inspector of Lifts and Escalators On issue of duplicate certificate, the original certificate shall be deemed to be invalid and if found shall be returned to Chief Inspector of Lifts and Escalators

(18) If the holder of this certificate is found to be guilty of negligence or incompetence or in case of breach of the provisions of the Tamil Nadu Lifts and Escalators Act, 1997 and the Tamil Nadu Lifts and Escalators Rules, 1997 and the above instructions contained in this registration or for the malpractice or misconduct or misbehavior or any other reason in public interest, the Chief Inspector of Lifts and Escalators may suspend or cancel the approval after giving a show cause notice.

35 Form M (See rule 14) GOVERNMENT OF TAMIL NADU ELECTRICAL INSPECTORATE CERTIFICATE OF AUTHORISATION FOR MAINTENANCE, INSPECTION AND TESTING OF ESCALATORS REGISTRATION NO :

DATE OF REGISTRATION :

Under Section 10 of the Tamil Nadu Lifts and Escalators Act, 1997, Thiru…………………………………………………………………………………………………… ………………………………………………………………………………………………………… ………………………………………………………….are hereby authorized to carry out maintenance, inspection and testing of lifts within the State of Tamil Nadu subject to the compliance of instructions set out in the Annexure II and fulfillment of the conditions detailed below.

Chief Inspector of Lifts and Escalators Authorization Valid from

(1) Authorization Valid upto

(2) Initial of Chief Inspector Lifts and Escalators

(3) 36 CONDITIONS MAINTENANCE/INSPECTION/TESTING 1) (i) This certificate is valid for a period of one year and shall be returned to Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators for renewal along with application for the purpose three months before the expiry of validity

(ii) In the event of the holder of registration failing to get the registration renewed in the said manner before the date of expiry, the registration shall become void and fresh registration shall have to be obtained.

2) The firm/company holding this registration can undertake the work of maintenance of work.

3) The holder of this certificate of registration shall be in possession of the latest copy of the Tamil Nadu Lifts and Escalators Act, 1997 and Tamil Nadu Lifts and Escalators Rules,1997 and relevant specifications and code of practices of Bureau of Indian Standards.

4) It shall be responsibility of the person authorized to ensure that all materials, fittings, appliances, equipments etc used in the lift which he undertakes to maintain conform to the relevant specifications as laid down by Bureau of Indian Standards.

5) The holder of this certificate of registration,-

(i) shall maintain a register of technical personnel employed by him for maintenance and register shall be produced for inspection on demand by Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators or any other person authorised by him in this behalf.

(ii) The list of lifts maintained as on 31st March of every year, after the receipt of the approval, shall be submitted before 30th April of the year to Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators of the District/Area concerned.

6) Any change in address of the place of business of the holder of this certificate of registration shall be communicated to Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators within two weeks of such change. Any change of Agent or Manager, if any shall be similarly notified within fifteen days of such change.

7) The holder of this certificate should mention the approval registration number with its validity in all their correspondence to this office and to any Inspector of Lifts and Escalators and only the authorised signatory shall sign in all the correspondences.

8) The holder of this certificate should depute one of his authorised Representative/Engineer to be present at the time of inspection by the Inspector of Lifts and Escalators or his representative of the escalator Installation erected by him.

37 9) If there is change in ownership or in the name and style in which the approval is granted then the holder of the certificate shall seek fresh certificate of authorisation.

10) Atleast three persons of the owner of the lifts who ordinarily are the occupants or residents of premises in which the lift is installed, shall be trained by holder of this certificate of registration in respect of rescue operation in case of power failure.

11) The holder of this certificate of registration shall report the occurrence of any fatal or non-fatal accident in writing to Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators concerned within 24 hours of the occurrence of such accident.

12) The group Insurance Scheme/Workman compensation policy for the employees should be kept alive.

13) Issue of Duplicate copy of Certificate of Registration:

(i) A duplicate copy of certificate of registration will be issued on the request made by the applicant in case of loss of original certificate to the satisfaction of Chief Inspector of Lifts and Escalators

(ii) On issue of duplicate copy of certificate, the original certificate shall be deemed to be invalid and if found shall be returned to Chief Inspector of Lifts and Escalators 14) If the holder of this certificate is found to be guilty of negligence of incompetence or a breach of the provisions of the Tamil Nadu Lifts and Escalators Act, 1997 and Tamil Nadu Lifts and Escalators Rules,1997 and the above instructions or for the malpractice or misconduct or misbehavior or any other reason in public interest, the Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators may suspend or cancel the approval after giving a show cause notice.

38 Form N (See rule 14) GOVERNMENT OF TAMIL NADU ELECTRICAL INSPECTORATE CERTIFICATE OF AUTHORISATION FOR MAINTENANCE, INSPECTION AND TESTING OF ESCALATORS REGISTRATION NO :

DATE OF REGISTRATION :

Under Section 10 of the Tamil Nadu Lifts and Escalators Act,1997, Thiru…………………………………………………………………………………………………… ………………………………………………………………………………………………………… ………………………………………………………….are hereby authorized to carry out maintenance, inspection and testing of escalators within the State of Tamil Nadu subject to the compliance of instructions set out in the Annexure II and fulfillment of the conditions detailed below.

Chief Inspector of Lifts and Escalators Authorization Valid from

(1) Authorization Valid upto

(2) Initial of Chief Inspector Lifts and Escalators

(3) 39 CONDITIONS MAINTENANCE/INSPECTION/TESTING 1) (i) This certificate is valid for a period of one year and shall be returned to Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators for renewal along with application for the purpose three months before the expiry of validity

(ii) In the event of the holder of registration failing to get the registration renewed in the said manner before the date of expiry, the registration shall become void and fresh registration shall have to be obtained.

2) The firm/company holding this registration can undertake the work of maintenance of work.

3) The holder of this certificate of registration shall be in possession of the latest copy of the Tamil Nadu Lifts and Escalators Act, 1997 and Tamil Nadu Lifts and Escalators Rules,1997 and relevant specifications and code of practices of Bureau of Indian Standards.

4) It shall be responsibility of the person authorized to ensure that all materials, fittings, appliances, equipments etc used in the escalators which he undertakes to maintain conform to the relevant specifications as laid down by Bureau of Indian Standards.

5) The holder of this certificate of registration

(i) shall maintain a register of technical personnel employed by him for maintenance and register shall be produced for inspection on demand by Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators or any other person authorised by him in this behalf.

(ii) The list of escalators maintained as on 31st March of every year, after the receipt of the approval, shall be submitted before 30th April of the year to Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators of the District/Area concerned.

6) Any change in address of the place of business of the holder of this certificate of registration shall be communicated to Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators within two weeks of such change. Any change of agent or Manager, if any shall be similarly notified within fifteen days of such change.

7) The holder of this certificate should mention the approval registration number with its validity in all their correspondence to this office and to any Inspector of Lifts and Escalators and only the authorised signatory shall sign in all the correspondences.

8) The holder of this certificate should depute one of his authorised Representative/Engineer to be present at the time of inspection by the Inspector of Lifts and Escalators or his representative of the escalator Installation erected by him.

40 9) If there is change in ownership or in the name and style in which the approval is granted then the holder of the certificate shall seek fresh certificate of registration.

10) Atleast 3 persons of the owner of the escalators who ordinarily are the occupants or residents of premises in which the escalators is installed, shall be trained by holder of this certificate of registration in respect of rescue operation in case of power failure.

11) The holder of this certificate of registration shall report the occurrence of any fatal or non-fatal accident in writing to Chief Inspector of Lifts & Escalators and Inspector of Lifts and Escalators concerned within 24 hours of the occurrence of such accident.

12) The group Insurance Scheme/Workman compensation policy for the employees should be kept alive.

13) Issue of Duplicate copy of Certificate of Registration:

(i) A duplicate copy of certificate of registration will be issued on the request made by the applicant in case of loss of original certificate to the satisfaction of Chief Inspector of Lifts and Escalators

(ii) On issue of duplicate copy of certificate, the original certificate shall be deemed to be invalid and if found shall be returned to Chief Inspector of Lifts and Escalators 14) If the holder of this certificate is found to be guilty of negligence or incompetence or a breach of the provisions of the Tamil Nadu Lifts and Escalators Act , 1997 and Tamil Nadu Lifts and Escalators Rules,1997 and the above instructions contained in this registration or for the malpractice or misconduct or misbehavior or any other reason in public interest, the Chief Inspector of Lifts and Escalators and Inspector of Lifts and Escalators may suspend or cancel the approval after giving a show cause notice.

41 FORM O (see rule 15) TEST REPORT ISSUED BY THE COMPETENT PERSON FOR LIFT Licence No.

Date of Inspection:

Year:

Lift situated at:

Details of machine:

Number of floors Name and address of the owner No. of persons and load Type of doors Sl.

No.

Description Remarks

1. Counterweight guard screen

2. Provision of pit switch / provision of pit switch unit with arrangement for lighting the pit

3. Condition of pulley of safety governor rope

4. Display of car capacity

5. Provision of emergency alarm bell

6. Provision of light point

7. Operation of stop button / switch (Push button type only)

8. In case of manually operated car door, open the car door while the lift is moving.

9. In case of power operated car door, while lift is moving operate the “DOOR OPEN” button.

10. In case of power operated car door, and landing doors when they are about to close at landing operate the “DOOR OPEN” button.

11. In case of power operated car door, and landing doors when they are about to close at landings place around object of a normal finger size in the air.

12. In case of manual operated doors reverse the order of closing the doors by closing the car door and not closing landing door. Operate the floor button from inside the car or from landing side.

13. In case of goods lifts, when the lift halts either above or below the landing level say by about + or – 180 mm, operate the inching, device if provided.

14. Operation of lever of landing gates locks i.e., pressing the lever from the car top during travel in 42 “UP” or “DOWN” direction.

15. Operation of landing gate from the car top i.e., press the landing gate if, it is swing type and try to open the sliding type at every landing during travel of lift in “UP” and “DOWN” direction.

16. Observe whether the retiring cam comes in contact with the lever of landing gate locks.

17. Operation of safety switches on car top

18. Observe whether the counter weight stacks are firmly secured to the frame by tie-rod or other suitable means.

19. Condition of gathering clips, rope fastening of suspension ropes near counterweight and near car top.

20. Provision of separate main switches for power and light

21. Provision of three pin plugs in m/c room

22. Provision of brake releasing device

23. Condition of main suspension ropes

24. Condition of ropes of over speed governor.

25. Condition of limit switches operation rope when provided.

26. Condition of wiring at control panel

27. Operation of up final limit switch

28. Operation of over speed governor

29. Provision of delocking arrangement at every landing.

30. Opening of any landing doors while lift is passing through a landing zone to another floor.

Signature of the Competent Person 43 FORM P (see rule 15) TEST REPORT ISSUED BY THE COMPETENT PERSON FOR ESCALATOR LICENCE NO……… DATE OF INSPECTION …….

YEAR:

1. Name and Address of the owner :

2. Name and Address of the authorized person by whom the escalator is erected or maintained. :

3. Escalator erected at :

4. Angle of inclination :

5. Width between balustrades :

6. Width of the steps :

7. Details of balustrading :

Type Construction Condition

8. Details of handrails :

Type Construction Condition

9. Details of step treads and landings :

10. Details of comb plates :

11. Details of girders :

12. Details of track arrangement :

13. Rated load :

14. Rated speed :

15. Machine room :

Size Height Height above machine room Platform Placement of machine Distance from wells

16. Details of Motor :

17. Details of Machine :

44

18. Details of control panel :

19. Provision of phase failure or reversal :

20. Protection relay :

21. Condition of wiring :

22. Main switches :

23. Power main capacity :

24. Lighting main switch capacity and condition :

25. Lighting of machine room :

26. Ventilation :

27. Protection from rain :

28. Approach to machine room :

29. Details of earthing :

30. Earthing of parts :

31. Details of chains :

32. Details and condition of safety devices :

safety/over speed Governor operation

33. Lighting details of step treads :

34. Rated load test :

35. Over speed test :

36. Reversal test :

37. Broken chain test :

38. Other remarks, if any :

Signature of the Competent Person Md. NASIMUDDIN, Principal Secretary to Government

Where this provision sits

ActThe Tamil Nadu Lifts and Escalators Rules,1997
Section15
Marginal noteSubmission of Test report by the competent person
JurisdictionState of Tamil Nadu
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Tamil Nadu Lifts and Escalators Rules,1997 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.