Section 5: Electricity Connection to telecommunication company

Uttar Pradesh Electricity Regulatory Commission (Facilitation of Telecommunication Network) Regulations, 2022State Regulations of Uttar Pradesh · 2003

5.1. In case electricity connection is required for facilitation of such telecommunication network including 5G network infrastructure, separate Electricity connection shall be given to the telecommunication company at the point of installation of distribution assets.

8 mÙkj izns'k vlk/kkj.k xtV] 17 uoEcj] 2022 bZ0

Provided that the connection agreement can be signed collectively for all the distribution assets within a distribution division depending upon the convenience of distribution licensee.

However, the connection agreement will entail the location coordinates or GPS location or pole number or DT number or name of sub- station allotted to a telecom company within a division.

5.2. All electricity consumption by telecommunication network installed on distribution assets of the distribution licensee shall be metered at the point of installation through a Smart Meter and the billing of such consumption shall also be done at the point of installation as individual connections are be released on each point of installation. However, the Consolidated bill of all the connections of a particular Telecom licensee within a distribution division or equivalent, can be generated with connection wise details for convenience of billing & collection. The cost of the connection and meter shall be borne by the telecom company.

5.3. The revenue generated from such Electricity connection or use of electricity shall from part of the Tariff income of Distribution Licensee.

Where this provision sits

ActUttar Pradesh Electricity Regulatory Commission (Facilitation of Telecommunication Network) Regulations, 2022
Section5
Marginal noteElectricity Connection to telecommunication company
JurisdictionState of Uttar Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Uttar Pradesh Electricity Regulatory Commission (Facilitation of Telecommunication Networ… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.