7.1 Tariff for all other intra-State transmission projects not covered under Regulation 6.1, being part of the STU Transmission Plan, shall be determined in accordance with RTM framework under Section 62 of the Act.
7.2 Implementation of augmentation/ strengthening works (excluding O&M works) at the intra-State transmission substation and/or line, being part of the STU Transmission Plan, shall be carried out by the respective developer in accordance with the provisions under Section 62 of the Act read with UPERC (Multi Year Tariff for Distribution and Transmission) Regulations 2019, as amended from time to time, for which the STU shall obtain prior approval of the Commission on case-to-case basis.
PART-C DISTRIBUTION
8. Retail Tariff of the consumers shall be determined in accordance with Section 62 of the Electricity Act 2003 along with UPERC (Multi Year Tariff for Distribution and Transmission) Regulations 2019, as amended from time to time.
PART-D MISCELLANEOUS