Central Electricity Authority (Grid Standards) Regulations, 2010Central Regulations · 2003
(1) The Regional Power Committees shall prepare Islanding schemes for separation of systems with a view to save healthy system from total collapse in case of grid disturbance.
(2) The Entities shall ensure proper implementation of the Schemes referred to in sub-regulation (1).
Explanation.- For the purposes of this regulation ‘Islanding Scheme’ means a scheme for the separation of the Grid into two or more independent systems as a last resort, with a view to save healthy portion of the Grid at the time of grid disturbance.
Need this as data, not as a page? Central Electricity Authority (Grid Standards) Regulations, 2010 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.