(1) The developer or the applicant applying for supply of electricity from the Licensee shall provide free of charge, the applicable space of requisite dimensions as notified in the Commission’s Orders, at a convenient location, as may be mutually agreed between the consumer and the Licensee, for erection and installation of grid substations, transformers, switch gear, meter, equipment, etc.:
Provided that if there is no specific developer in an area and the augmentation of the existing distribution system requires the space for installation of grid substations, transformers, switch gears, etc. to meet out the load demand, the distribution licensee shall approach the Government of National Capital Territory of Delhi, within fifteen days of such requirement, for allotment of space, indicating the probable space available in such areas:
(2) Except for HT or EHT networks, the Licensee shall have no right to utilize the sub-station in the consumer’s premises, without his consent, for the supply of electrical energy to other consumers:
80 DELHI GAZETTE : EXTRAORDINARY PART III]
Provided that the utilization of such assets for providing electricity to other consumers shall not in any manner affect the supply to the consumers for which such assets were originally installed.