Section 31: Consequence of making the meter inaccessible for reading

Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017Union territory Regulations of Delhi · 2003

(1) If the meter is rendered inaccessible on any meter reading date, the Licensee shall issue a 7 (seven) days prior notice to the consumer, specifying the date and time of the meter reading for the next billing cycle, to keep the meter accessible on such date and the time:

84 DELHI GAZETTE : EXTRAORDINARY PART III]

Provided that the consumer may request the Licensee to fix another date and time for such meter reading.

(2) If meter is not made accessible even on the date specified in the notice or as mutually agreed, the Licensee shall issue a second 7 (seven) days prior notice to the consumer, specifying the date and time of the meter reading for the next billing cycle, to keep the meter accessible on such date and the time.

(3) If meter is not made accessible even on the date specified in the notice or as mutually agreed, the Licensee shall serve 15 (fifteen) days clear disconnection notice to the consumer:

Provided that the consumer may send the picture of the meter indicating the meter reading and date of meter reading through registered mobile or through e-mail.

(4) If the consumer fails to provide access for the meter reading even during such notice period, the Licensee may disconnect the supply after expiry of the notice period and reconnection of supply shall be effected only after taking the reading and payment of all the dues by the consumer.

(5) The provisions of the above sub-regulations shall not apply in all such cases where the consumer whose payment is up to date and has given an advance intimation to the Licensee of the inaccessibility of his meter for reading, specifying the reason, and has also deposited fixed charges for such period in advance:

Provided that, in all such cases, as and when the meter is made accessible by the consumer for taking the meter reading, the entire consumption shall be taken as if the consumption was for the period excluding the intimated period of inaccessibility.

Where this provision sits

ActDelhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017
Section31
Marginal noteConsequence of making the meter inaccessible for reading
JurisdictionUnion territory of Delhi
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulatio… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.