Section 64: Interference with signalling equipment and points and crossings

GSR 765 (E) Dedicated Freight Corridor Railway General Rules, 2018.Central Rules · 1989

(1) No railway servant shall interfere with any signalling equipment, including points and crossings for the purpose of effecting testing or overhauling or maintenance or repairs or for any other purpose without the prior permission of the signal inspector, or any competent railway servant appointed in this behalf by Dedicated Freight Corridor Railway administration; and the railway servant who gives such permission shall himself be present to superintend such work.

(2) No work requiring interference with signalling equipment or points and crossings shall be commenced without the prior permission of station master on duty. When it is considered necessary to disconnect any of the signalling equipment, the signal inspector or a railway servant of signal department authorised to do so, shall advise station master on duty in writing through a disconnection memo in form 1 prepared in two foils and commence work only after it has been acknowledged and permitted by station master on duty on the record copy.

(3) The disconnection memo shall clearly bring out the details of the signalling equipment to be disconnected and for which kind of train movement interlocking cover shall not be available, as also for which kind of train movement interlocking cover shall still be available, if any.

(4) Having acknowledged the dis-connection memo it shall be duty of the station master to undertake train operation for those portions where interlocking cover is not available only in the manner as is permitted under these rules during failures, unusual occurrences, accidents as per Chapter IX.

(5) After the work has been completed, the signal inspector or a railway servant of signal department authorised to do so shall ensure, after testing, that the disconnected signalling equipment reconnected are in proper working order and only thereafter, shall advise station master on duty through a second written memo prepared in two foils giving reference of the disconnection memo previously issued.

(6) Station master on duty after satisfying that the reconnected signalling equipment are in working order, shall acknowledge on the record foil of the reconnection memo. The station master on duty shall make a note of these transactions in the station diary and preserve his copy of the disconnection and reconnection memo by pasting on the opposite pages of the register kept for this purpose.

¹Hkkx IIµ[k.M 3(i)º Hkkjr dk jkti=k % vlk/kj.k 183

(7) Works which do not involve any disconnection shall be determined under special instructions.

Where this provision sits

ActGSR 765 (E) Dedicated Freight Corridor Railway General Rules, 2018.
Section64
Marginal noteInterference with signalling equipment and points and crossings
JurisdictionCentral
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? GSR 765 (E) Dedicated Freight Corridor Railway General Rules, 2018. is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.