CourtMesh

Section 5: DSM Master Plan

The Himachal Pradesh Electricity Regulatory Commission (Demand Side Management) Regulations, 2011State Regulations of Himachal Pradesh · 2003

(1) The licensee shall, within 6 months from the commencement of these regulations, prepare a comprehensive draft of DSM Master Plan and submit the same for the approval of the Commission.

(2) The distribution licensee shall prepare DSM Master Plan initially for a period of 5 years and subsequently for the periods as may be directed by the Commission from time to time.

(3) The draft of DSM Master Plan shall act as a reference document for the licensee while preparing the annual DSM programme for the State of Himachal Pradesh.

(4) The draft of the DSM Master Plan shall include the following, namely:-

(a) Demand forecasting study,

(b) Load research, establishment of baseline data, 4 Compendium of HPERC Regulations, March 2021

(c) Walk through Energy audit,

(d) Identification of DSM options,

(e) Cost benefit analysis of each of the DSM options,

(f) Pricing options for DSM,

(g) Financing DSM options,

(h) Prioritization and implementation schedule for each of the measures proposed in the DSM Plan,

(i) DSM targets to be achieved for each of the measures proposed in the DSM Plan,

(j) Institutional arrangement, implementation planning, barriers and mitigation measures, and

(k) any other aspects covered in these regulations or as the Commission may direct.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Demand Side Management) Regulations, 2011
Section5
Marginal noteDSM Master Plan
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Demand Side Management) Regulatio… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.