Section 6: Institutional framework for DSM

The Himachal Pradesh Electricity Regulatory Commission (Demand Side Management) Regulations, 2011State Regulations of Himachal Pradesh · 2003

(1) In order to discharge the DSM related functions in a smooth manner, the licensee may within three months from the date of commencement of these regulations constitute DSM Cell and the DSM Cell so constituted shall be provided with necessary resources to execute the DSM related functions.

(2) The DSM related functions of the licensee shall be as under, namely:-

(a) Load research, consumer survey, development of baseline data and recasting at aggregate system level, segment level and end use level,

(b) Formulation of DSM Plan,

(c) Design and development of DSM programmes including cost benefit analysis, plans for implementation, monitoring and reporting and for measurement and verification for each measure,

(d) Seeking necessary approvals of the Commission to the Draft DSM Plan and DSM programmes,

(e) Implementation of DSM programmes,

(f) Liaison with the State Designated Agency at planning and implementation stage to avoid duplication of DSM and/or Energy Efficiency activity in the State of Himachal Pradesh,

(g) Validation and Updation of master plan and submission of the same for approval of the Commission, alongwith the DSM programmes on annual basis,

(h) Evaluation, Measurement and Verification of DSM programme, and

(i) any other additional DSM related function that may be assigned by the Commission from time to time.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Demand Side Management) Regulations, 2011
Section6
Marginal noteInstitutional framework for DSM
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Demand Side Management) Regulatio… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.