Section 8: Limits on Deviation Volume

The Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018State Regulations of Himachal Pradesh · 2003

(1) The over-drawal/under-drawal of electricity by any buyer during the time block shall not exceed 12% of its scheduled drawal, when grid frequency is 1 [49.85Hz] and above” but “below 50.05 Hz”:

Provided that no over-drawal of electricity by any buyer shall be permissible when grid frequency is “below 1[49.85Hz]” and no under-drawal of electricity by any buyer shall be permissible when grid frequency is “50.05 Hz and above”.

(2) The under-injection/over-injection of electricity by a seller during a time-block shall not exceed 12% of the scheduled injection of such seller, when frequency is 1 [49.85Hz] and above but below 50.05 Hz”:

Provided that no under injection of electricity by a seller shall be permissible when grid frequency is "below 1[49.85Hz]" and no over injection of electricity by a seller shall be permissible when grid frequency is "50.05 Hz and above”:

Provided further that any injection of infirm power by a generating station prior to COD of a unit during testing and commissioning activities shall be exempted from the volume limit specified above for a period not exceeding 6 months or the extended time allowed by the Commission:

Provided further that any drawal of power by a generating station prior to COD of a unit for the start up activities shall be exempted from the volume limit specified above when grid frequency is “[49.85Hz] and above".

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018
Section8
Marginal noteLimits on Deviation Volume
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism an… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.