Section 9: Additional charges for crossing Deviation Volume Limits

The Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018State Regulations of Himachal Pradesh · 2003

(1) In addition to charges for Deviation as stipulated under Regulation 7 of these regulations, additional charge for Deviation shall be applicable for incremental over-drawal as well as under-injection of electricity for each slab in respect of each time block in excess of the volume limit specified in regulation 8 above, when average grid frequency of the time block is 2 [49.85 Hz] and above but upto 50.05 Hz” at the rates specified in the Table-2 below.

1 Sub. for regulation 8 in sub-regualtion (1) & (2) and provisio for words and figures “49.70Hz” for vide not. No. HPERC/428 dated 29th June, 2019, published in R.H.P. dated 3rd July, 2019 at p. 3131-

3137.

2 Sub. for regulation 9 in sub-regualtion (1) for words and figures “49.70Hz” for vide not. No.

HPERC/428 dated 29th June, 2019, published in R.H.P. dated 3rd July, 2019 at p. 3131-3137.

14 Compendium of HPERC Regulations, March 2021 Table-2 Additional Charges for Deviation beyond the limits on Deviation Volume

1. For over drawal of electricity by any buyer in excess of 12% and up to 15% of the schedule in a time block Equivalent to 20% of the charge for Deviation corresponding to average grid frequency of the time block.

2. For over drawal of electricity by any buyer in excess of 15 % and upto 20% of the schedule in a time block Equivalent to 40% of the charge for Deviation corresponding to average grid frequency of the time block.

3. For over drawal of electricity by any buyer in excess of 20 % of the schedule in a time block Equivalent to 100% of the charge for Deviation corresponding to average grid frequency of the time block.

4. For under injection of electricity by any seller in excess of 12% and upto 15% of the schedule in a time block Equivalent to 20% of the charge for Deviation corresponding to average grid frequency of the time block.

5. For under injection of electricity by any seller in excess of 15% and upto 20% of the schedule in a time block Equivalent to 40% of the charge for Deviation corresponding to average grid frequency of the time block.

6. For under injection of electricity by any seller in excess of 20% of the schedule in a time block Equivalent to 100% of the charge for Deviation corresponding to average grid frequency of the time block.

Provided that any drawal of power by a generating station prior to COD of a unit for the start up activities shall be exempted from the levy of additional charges of Deviation.

(2) In addition to the Charges for Deviation as specified under regulation 7 of these regulations, additional charge for Deviation shall be payable for the over-injection and/or under drawal of electricity for each time block by a seller and/or buyer, as the case may be, 1 [when grid frequency is “50.10 Hz and above” at the rate of Deviation charges applicable for the frequency range of 50-50.01 Hz for that day as per the Table-1 under regulation 7.]

(3) In addition to the charges for Deviation as stipulated under regulation 7 of these regulations, additional charge for Deviation shall be payable for over-drawal and/or under injection of electricity for each time block by a buyer and/or seller, as the case may be, when grid frequency is “below 2 [49.85] and the rate for the same shall be equivalent to 100% of the charge for Deviation corresponding to the grid frequency of “below 49.85 Hz” i.e.

2 [800 Paise/kWh].

3 [9A. Additional Charges for not meeting the requirements for Change in sign of deviations.— "In the event of sustained deviation from schedule in one direction (positive or negative) by any State Entity (buyer or seller), such entity shall correct its position in the manner as specified in following clauses (a) and (b) of this Regulation.

1 Sub. for regulation 9 in sub-regualtion (2) vide not. No. HPERC/428 dated 29 th June, 2019, published in R.H.P. dated 3 rd July, 2019 at p. 3131-3137 and before its substitution read as under:

“ when grid frequency is ‟50.10 Hz and above” at the rate of 178 paise per kWh.” 2 Sub. for regulation 9 in sub-regualtion (3) for words and figures “49.70Hz and 824.04 Paise/kWh” for vide not. No. HPERC/428 dated 29 th June, 2019, published in R.H.P. dated 3 rd July, 2019 at p. 3131-3137.

3 Ins. regulation 9A vide not. No. HPERC/428 dated 29 th June, 2019, published in R.H.P. dated 3 rd July, 2019 at p. 3131-31373.

Compendium of HPERC Regulations, March 2021 15

(a) on or before 31-03-2020, if the sustained deviation from schedule continues for 12 time blocks, the State Entity (buyer or seller), shall correct its position either by changing the sign of its deviation from schedule or by restricting the sustained deviation to the permissible limits as specified in Table-3 below with reference to its schedule for the time block to be reckoned for violation, at least once, latest by 13 th time block.

Table-3 Maximum permissible limits for Sustained Deviation from Schedule Sl.

No.

Schedule for relevant time block to be reckoned for violation Maximum permissible limits (in one direction of sustained deviation) in MW

1. Up to 10 MW 0.5

2. Upto 25MW 1.0

3. Upto 100MW 2.00

4. Above 100 MW 10.00

Provided that each violation of the requirement under this clause shall attract an additional charge of 10% on the time block DSM payable/ receivable as the case may be;

(b) on or after 01-04-2020, if the sustained deviation from schedule continues for 6 time blocks, the State Entity (buyer or seller), shall correct its position, either by changing the sign of its deviation from schedule or by restricting the sustained deviation to the permissible limits as specified in Table-3 above with reference to its schedule for the time block to be reckoned for violation, at least once, latest by 7th time block:

Provided that violation of the requirement under this clause shall attract an additional charge as specified in the table-4 below:

Table-4 Additional Charge for Violation in Sustained Deviation from Schedule:

No. of Violation in a Day Additional Change Payable From first to fifth violation For each violation, an additional charge @ 3% of daily base DSM ayable/receivable.

From sixth to tenth violation For each violation, an additional charge @ 5% of daily base DSM payable/receivable.

From eleventh violation onwards For each violation, an additional charge @ 10% of daily base DSM payable/receivable.

Provided further that counting of number of sign change violations under clauses

(a) & (b) of this Regulation shall start afresh at 00.00 Hrs. for each day:

Provided further also that payment of additional charge for failure to adhere to sign change requirement as specified under clauses (a) & (b) of this regulation shall not be applicable to—

(i) any infirm injection of power by a generating station prior to CoD of a unit during testing and commissioning activities, in accordance with the Connectivity Regulations; and 16 Compendium of HPERC Regulations, March 2021

(ii) any drawal of power by a generating station for the start-up activities of a unit.

Explanation.—For the purpose of this Regulation, sustained deviation means continuous deviation outside the maximum permissible limit as specified in Table-3 above, such range being a subset of the volume limit as specified in sub-regulations (1) and (2) of regulation 8. In other words, if the deviation is brought within the range as specified in Table-3 or it remains within the range specified in Table-3, it will not be considered as sustained deviation, even if the change in sign of deviation has not taken place.

Illustrations:—

(i) Illustration to clause (a) of this regulation.—A State Entity having a sustained deviation from time blocks t1 to t12, should correct its position either by changing the sign of its deviation (from positive to negative or negative to positive as the case may be) or come back in the permissible limits as specified in Table-3 above with reference to its schedule latest in the end of time block t13. In case, such sign change does not take place or it fails to come back in the range as specified in Table-3 above in the end of time block t13, but such correction of position takes place from time block t14 up to time block t24, then the additional charge shall be levied equivalent to one violation.

The above violation shall attract an additional charge at the rate of 10% of the time block DSM for t13. Further, in case, sign change does not take place or it fails to come back to the range as aforesaid even latest in the end of t25, but correction of position takes place from time block t26 up to time block t36, then the additional charge shall be levied equivalent to two violations. The above violation shall attract an additional charge at the rate of 10% of the time block DSM for t13 & t25, and so on.

(ii) Illustration to clause (b) of this regulation.—On or after 01-04- 2020, if a State Entity having a sustained deviation from time blocks t1 to t7, should correct its position either by changing the sign of its deviation (from positive to negative or negative to positive as the case may be) or come back in the range as specified in Table-3 above with reference to its schedule latest in the end of time block t7. In case, such sign change does not take place or it fails to come back in the aforesaid range in the end of time block t7, but such correction of position takes place from time block t8 up to time block t12, then additional charge shall be levied equivalent to one violation. Further, in case, sign change does not take place or it fails to come back in the range as aforesaid latest in the end of t13, but correction in position takes place from time block t14 up to time block t18, then the additional charge shall be levied for two violations and so on.

The additional charge shall be at the rate as specified in Table-4 above of this Regulation.

(iii) In case the State Entity effects change in the sign of its deviation from the schedule, or otherwise restricts the deviation to the permissible Compendium of HPERC Regulations, March 2021 17 limit as per Table-3, before the expiry of latest time block in which it was required to do so, the violations, if any, for the remaining period of the day shall be counted with reference to the time block in which it has actually complied the said requirement prior to the expiry of that time block.

(iv) The additional charge as per this regulation shall be computed on the sum total of the mode values (i.e. by ignoring the sign) of the amount payable and receivable for that day under regulation 7.]

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018
Section9
Marginal noteAdditional charges for crossing Deviation Volume Limits
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism an… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.