Section 18: Application for medium-term open access
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Relate…State Regulations of Himachal Pradesh · 2003
(1) The application for grant of medium-term open access shall contain such details as may be laid down under the detailed procedure and shall, in particular, include the point of injection into the grid, point of drawl from the grid and the quantum of power for which medium-term open access has been applied for.
(2) The start date of the medium-term open access shall not be earlier than 5 months and not later than 1 year from the last day of the month in which application has been made.
Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.