Section 20: Grant of medium-term open access

The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Relate…State Regulations of Himachal Pradesh · 2003

(1) On being satisfied that the requirements specified under sub-regulation (2) of regulation 9 are met, the nodal agency shall grant medium-term open access for the period stated in the application:

Provided that for reasons to be stated in writing, the nodal agency may grant medium-term open access for a period less than that sought for by the applicant:

Provided further that the applicant shall sign an agreement for medium term open access with the State Transmission Utility/licensee in case medium-term open access is granted by the nodal agency in accordance with the provisions as may be made, in the detailed procedure. While seeking medium-term open access to an intra-State transmission licensee, other than the State Transmission Utility, the applicant shall sign a tripartite medium-term open access agreement with the State Transmission Utility and the intra-State transmission licensee. The medium-term open access agreement shall contain the date of commencement and end of medium-term open access; payment security mechanism for the term of open access, the point of injection of power into the grid and point of drawl from the grid, the details of dedicated transmission/ distribution lines required, if any, the bank guarantee required to be given by the applicant and other details in accordance with the detailed procedure.

(2) Immediately after grant of medium-term open access, the nodal agency shall inform the State Load Despatch Centre so that it can consider the same while processing requests for grant of short-term open access, received under the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Short Term Open Access) Regulations, 2010 as amended from time to time.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010
Section20
Marginal noteGrant of medium-term open access
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.