Section 23: Exit option for medium-term open access customers
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Relate…State Regulations of Himachal Pradesh · 2003
A medium-term open access customer may relinquish its rights, fully or partly, by giving at least 30 days prior notice to the nodal agency:
Provided that the medium-term open access customer relinquishing its rights shall pay applicable transmission/wheeling charges for the period of relinquishment or 30 days whichever is lesser.
CHAPTER – 7 CONDITIONS OF LONG-TERM AND MEDIUM-TERM OPEN ACCESS
Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.