Section 23: Exit option for medium-term open access customers

The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Relate…State Regulations of Himachal Pradesh · 2003

A medium-term open access customer may relinquish its rights, fully or partly, by giving at least 30 days prior notice to the nodal agency:

Provided that the medium-term open access customer relinquishing its rights shall pay applicable transmission/wheeling charges for the period of relinquishment or 30 days whichever is lesser.

CHAPTER – 7 CONDITIONS OF LONG-TERM AND MEDIUM-TERM OPEN ACCESS

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010
Section23
Marginal noteExit option for medium-term open access customers
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.