Section 24: Curtailment

The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Relate…State Regulations of Himachal Pradesh · 2003

(1) When for the reason of operational constraints or in the interest of grid security, it becomes necessary to curtail power flow on a transmission/distribution Compendium of HPERC Regulations, March 2021 13 corridor, the transactions already scheduled may be curtailed by the State Load Despatch Centre.

(2) In case of curtailment of the approved schedule by the State Load Despatch Centre, transmission/distribution charges shall be payable pro-rata in accordance with the curtailed schedule:

Provided that operating charges shall not be revised in case of such curtailment.

Explanation. – For the purpose of this regulation, the expression “operational constraints” shall include the availability of the adequate capacity in the transmission/distribution system, appropriate metering and energy accounting system where the electricity to be transmitted/ wheeled can be correctly measured and accounted for and such other factors which may have an impact on the licensee’s business of supplying electricity to consumers in the area of supply.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010
Section24
Marginal noteCurtailment
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.