CourtMesh

Section 30: Payment of transmission/wheeling charges and fees and Charges for the State Load Despatch Centre

The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Relate…State Regulations of Himachal Pradesh · 2003

(1) The transmission/wheeling charges in respect of the long-term customer and medium-term customer shall be payable directly to the respective licensee:

Provided that the State Transmission Utility/licensee/nodal agency may be designated by the Commission as the agency for the purpose of collecting and disbursing the transmission/wheeling charges for intra-State transmission/ distribution system:

Provided further that when the State Transmission Utility/ licensee/nodal agency is so designated as the agency as aforesaid, the transmission/wheeling charges shall be paid to it:

Provided further that the State Transmission Utility/licensee/nodal agency so designated, shall enter into agreements with the long-term customers and medium-term customers for collection of transmission/wheeling charges and with the transmission/ distribution licensees whose intra-State transmission/ distribution system is being used, for disbursement of transmission/wheeling charges as received, pro rata to the transmission /wheeling charges payable to the licensees and to the State Transmission Utility:

Provided further that the State Transmission Utility/licensee/nodal agency, so designated, shall be entitled to reimbursement of reasonable costs incurred by it in collecting the transmission/wheeling charges of the other transmission/distribution licensees, as approved by the Commission.

(2) The fees and charges for the State Load Despatch Centre shall be directly payable by the long-term customer and medium-term to the State Load Despatch Centre.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010
Section30
Marginal notePayment of transmission/wheeling charges and fees and Charges for the State Load Despatch Centre
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.